| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹5.6 LAdmitted-Finance | -32.70% | ₹5.6 L | L1 | Admitted-Finance |
| 2 | L2₹6.2 L+₹59,446.06 (10.7%)Admitted-Finance | -25.51% | ₹6.2 L+₹59,446.06 (10.7%) | L2 | Admitted-Finance |
| 3 | L3₹6.6 L+₹1.1 L (19.0%)Admitted-Finance | -19.92% | ₹6.6 L+₹1.1 L (19.0%) | L3 | Admitted-Finance |
| 4 | L4₹6.7 L+₹1.1 L (20.2%)Admitted-Finance | -19.11% | ₹6.7 L+₹1.1 L (20.2%) | L4 | Admitted-Finance |
| 5 | L5₹7.2 L+₹1.6 L (29.0%)Admitted-Finance | -13.21% | ₹7.2 L+₹1.6 L (29.0%) | L5 | Admitted-Finance |
Tender Value
₹8.3 L
EMD Value
₹16,536
Closing Date
17 Aug 2026, 6:00 pmClosed
Executive Engineer PWD Dn, Chittorgarh
Office of the Executive Engineer PWD Dn, Chittorgarh
04 - Repair of damaged CD Work Amarpura to Semaliya at Km 0/500
2026_CEPWD_582371_4
NIT - 15/2026-27 EE PWD DN CHITTORGARH
Open Tender
Civil Works
Percentage
30 days
Chittorgarh
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
Through E Gras Challan
₹16,536
Yes
1 Sept 2026
7 Aug 2026
19 Aug 2026
7 Aug 2026
17 Aug 2026
7 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation for foundation of structure complete with all lift, dewatering, shoring and shuttering etc. including refilling of trenches in 250 mm layers, ramming, watering and disposal of surplus earth with all lifts and lead upto 1000 meters exclusive of compensation of earth as per MoRTH specification Clause 301 to 305. In ordinary soil Depth upto 3 metre Depth upto 3 metre | 62.22 | P.Cum | 161 | ₹10,017.42 |
| - | Providing and laying Cement concrete for plain/reinforced concrete in open foundation as per drawing and technical specification as per MoRTH Specification : Section 1500, 1700 & 2100 including form work at any level. For All Rajasthan except Hanumangarh P.C.C. grade M15 | 15.56 | p.sqm | 3,100 | ₹48,220.5 |
| - | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104 including Weepholes as per MoRTH specifications Clauses 2706 In 1:4 cement mortar | 183 | P.Cum | 3,183 | ₹5,82,489 |
| - | Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and MoRTH specification Clauses 1313, 1411 and 2206.6 75 mm thick | 24.4 | p.sqm | 318 | ₹7,759.2 |
| - | Plastering with cement mortar (1:4), 20 mm thick on Stone work. | 207.4 | p.sqm | 132 | ₹27,376.8 |
| - | Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new, plastered / concrete surfaces as per drawing and MoRTH Specification Clause 801 | 207.4 | p.sqm | 66 | ₹13,688.4 |
| - | Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MoRTH Specification Clause 401. For Grading III Material | 111.24 | P.Cum | 407 | ₹45,274.68 |
| - | Supply of Hazard Marker made out of 2 mm thick M.S. sheet size 300x300x3 mm framed with angle iron 25x25x3 mm and fixed on channel posts 75x40x6 mm and hold fast at bottom whole body is painted in white stoving enamel and 6 Nos., 5 cm dia reflective sheet on white reflective background with additional
border of 1.25 cm all arount it. | 4 | Each | 699 | ₹2,796 |
| - | Construction of un-reinforced , plain cement concrete pavement M30 (Grade), thickness as per design, over a prepared sub base, with 43/53 grade cement as per Clause 602, coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 31.5 mm, mixed in fully automatic Computerised Batching Plant compatiable with Printer and Pen Drive and transported to site in transit mixer for having continuous agitated mixer, manufactured as per approved mix design including pumping of R.M.C. from transit mixer to site of laying , with all lead and lift including cost of admixtures in recommended portion as per IS 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in charge laid with a Fixed Form Paver (laying and fixing of 150 micron thick polythene Film and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days using water finishing to lines and grade as per drawing and MoRTH Specification Clause 602 with all required equipments (Dowel Bars & Tie Bar will be paid seprately). | 14 | P.Cum | 5,160 | ₹72,240 |
| - | Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a fully automatic computerised batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing. | 7 | P.Cum | 2,418 | ₹16,926 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.35 MB
Tendernotice_2.pdf
PDF • 0.67 MB
Tendernotice_3.pdf
PDF • 10.18 MB
Tendernotice_4.pdf
PDF • 0.56 MB
BOQ_1034768.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .