| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹35.4 CrAccepted-AOC | L1 | Accepted-AOC L1 1st Lowest | |
| 2 | L2₹37.2 Cr+₹1.8 Cr (5.08%)Rejected-Finance | L2 | Rejected-Finance Second Lowest | |
| 3 | L3₹43.9 Cr+₹8.5 Cr (23.9%)Rejected-Finance | L3 | Rejected-Finance Third Lowest | |
| 4 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Others-Solvency Certificate (IDT-2) Not-Submitted.
Registration Certificate. Not-Submitted. |
Tender Value
Refer Docs
EMD Value
₹88.1 L
Closing Date
9 Apr 2025, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE KCC Pipri Sonbhadra
Office of SE KCC Pipri Sonbhadra 231221
Construction of balance EW of RKC from km 0.102 to km 24.025 from km.25.800 to Km26.700, BS At km.1.81 km.9.225 km.15.365 Box Culvert At km.6.1 km.14.800 PS At km. 12.200 km.13.450 HR for RPBC LPBC At Km.31.500 and Escape at km22.750of RKC
2025_UPIDC_1023949_1
04/SE/2024-25
Open Tender
Civil Works
Item Rate
270 days
Duddhi Sonbhadra
Please Refer Tender Document
2 documents required · 2 mandatory
₹2,360
₹88.1 L
5 Jun 2025
1 Apr 2025
9 Apr 2025
1 Apr 2025
9 Apr 2025
1 Apr 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation in ordinary soil /old PATRA filling for the construction of canal including all lead,lift and T&P etc required for proper completion of work as per direction of Engineer-in-Charge. | 75,484.05 | M3 | - | - |
| 2 | Earth work in excavation in mixed soil with lime stone, sand stone or other soft rock by pick axes but not required blasting for the construction of canal above 10 cum discharges including all lead ,lift, labour and T & P etc required for proper completion of work as per direction of Engineer-in-Charge. | 4,76,183.51 | M3 | - | - |
| 3 | Excavating other rocks by blasting removing muck and stacking including all lift, lead upto 90 m, labour and T & P etc required for proper completion of work as per direction of Engineer-in-Charge. | 1,41,225.91 | M3 | - | - |
| 4 | Excavating other rocks by blasting removing muck and stacking including all lift, lead upto 210 m, labour and T & P etc required for proper completion of work as per direction of Engineer-in-Charge. | 16,482.85 | M3 | - | - |
| 5 | Earth work in filling by power transport for making embankment for the construction of canal section with lead upto 1.0 Km and lift including cost of soil, labour charges and T & P etc with vibro mechanical compaction to achieve min 95.0 % dry density along with proper dressing and watering to bring at O.M.C. required for proper completion of work . | 3,22,991.58 | M3 | - | - |
| 6 | Earth work in filling by power transport for making embankment for the construction of canal section with lead upto 2.0 Km and lift including cost of soil, labour charges and T & P etc with vibro mechanical compaction to achieve min 95.0 % dry density along with proper dressing and watering to bring at O.M.C. required for proper completion of work . | 1,12,435.2 | M3 | - | - |
| 7 | Earth filling with useful quantity of excvavated ordinary soil earth in making canal section including cost of mechanical compaction ,lead upto 210 m, lift, labour and T&P, royalty and taxes etc required for proper completion of work. | 1,20,635.16 | M3 | - | - |
| 8 | Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m. | 2,313.91 | M3 | - | - |
| 9 | Providing and laying of 600 mm dia NP-3 hume pipe at crossing of SUKHARA minor at km 25.850 in R.K.C. with excavation, 90 cm width & 8 cm thick sand filling in bottom of pipe, RCC M-25 color joint 50 cm thick surrounding of pipe, 60 cm width 3 mtr length and 1.5 m height of RRM head wall in 1:3 cement and sand mortar in stone masonary with pointing at end and out of crossing of canal including cost of shuttering, 2.50 MT steel reinforcement in RCC . labour , T&P royalty and taxes etc for proper completion of work. | 80 | Rm | - | - |
| 10 | Providing and laying boulder in rock toe in canal filling including cost of boulder, labour, T&P etc required for proper completion of work. | 3,960.4 | M3 | - | - |
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
Tendernotice_1.pdf
Tender Document • 0.51 MB
TenderDocument.pdf
Tender Document • 1.63 MB
BOQ_1849241.xls
BOQ • 0.35 MB
DetailedBOQ.pdf
BOQ • 0.20 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .