Tender Value
₹93.3 Cr
EMD Value
₹1.9 Cr
Closing Date
16 Jun 2026, 12:00 pmClosed
Yes (up to 3 members)
No
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital (Works)
CE/CON/II
15 conditions · 3 needing a document upload
Submit the scanned copy (In PDF Form) of the documents as per the requirement of financial eligibility criteria of the tender [Refer para 2.3 of tender document {Para 2.3 for tenderer(s) participating as JV firm}]. TENDERS NOT ACCOMPANIED BY THESE DOCUMENTS WILL BE SUMMARILY REJECTED.
Submit the scanned copy (In PDF Form) of the documents for evaluating the Bid Capacity (Please refer Clause 12.25 of tender document). This is applicable in all works contract having tender value of Rs. 10.00 Crore and above. TENDERS NOT ACCOMPANIED BY THESE DOCUMENTS WILL BE SUMMARILY REJECTED.
Submit the scanned copy (In PDF Form) of the work(s) completion certificate(s) as per the requirement of Technical eligibility criteria of the tender [Refer para 2.3 of tender document {Para 2.3 for tenderer(s) participating as JV firm}]. TENDERS NOT ACCOMPANIED BY THESE DOCUMENTS WILL BE SUMMARILY REJECTED.
Defination of Similar Work :- 1. Any Civil Engineering work involving Earthwork in formation, Bridge work and track linking work. Or 2. (i) Any Civil Engineering work involving Earthwork in formation including Bridge works. And (ii) Any Track Linking Work of at least 10% of advertised value of present tender.
27 conditions · 15 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Notes for all schedules: Standard Schedule of Rates (SSOR) Items: Any item of work carried out by the Contractor on the instructions of the Engineer which is not included in the accepted Bill(s) of Quantities but figures in the Standard Schedule of Rates (SSOR), shall be executed at the rates set forth in the "Standard Schedule of Rates (SSOR)" modified by the tender percentage as accepted in the contract for that chapter of Standard Schedule of Rates (SSOR). However, the cumulative value of all such extra item(s) together (modified by the respective tender percentage) shall not exceed 10 % of the original contract value.
Option of Payment through Letter of Credit (L.C.): Tenderer(s) may submit option for taking payment through Letter of Credit (L.C.). [Refer para 7.1 of tender document].
Credentials if submitted in foreign currency shall be converted into Indian currency i.e., Indian Rupee as under: The conversion rate of US Dollars into Rupees shall be the daily representative exchange rates published by the Reserve Bank of India for the relevant date. Where, relevant date shall be as on the last day of month previous to the one in which tender is invited. In case of any other currency, the same shall first be converted to US Dollars as on the last day of month previous to the one in which tender is invited, and the amount so derived in US Dollars shall be converted into Rupees at the aforesaid rate. The conversion rate of such currencies shall be the daily representative exchange rates published by the International Monetary Fund for the relevant date.
Contract under EBR (IF): It is agreed by and between the parties that Railway shall continue to be held responsible for all obligations, risk and liabilities, whatsoever, arising out of or in connection with the Principal agreement and this novation agreement, whether during the progress of the work or after its completion. It is further agreed and understood by and between the parties that IRFC shall be the owner of assets, if any, arising out of execution of works as defined in the Principal Agreement, except the land whose ownership shall continue with Railway. Accordingly, the invoices shall be issued by capturing GSTIN of contractor (as the supplier) and GSTIN of IRFC (as bill to party). Also, the contractor shall submit the invoice, issued in the name of IRFC, to railway for processing payment by Railway to contractor subject to applicable TDS under the Income Tax, GST or any other applicable laws. It is further agreed by and between the Parties that IRFC shall be responsible to comply with Income Tax and GST laws in relation to filling of returns.
There are several changes in the tender document after the new GCC April 2022 is issued. Tenderer(s) are requested to go through the tender document & GCC carefully before the submission of the offer.
Clarification of Bids: To assist in the examination, evaluation & comparison and pre-qualification of the Tender, the Railway may, at its discretion, ask any Bidder for a clarification of its Bid. Any clarification submitted by a Bidder that is not in response to a request by the Railway shall not be entertained or considered. The Railway request for clarification and the response of the bidder in this regard shall be in writing. However, if a Bidder does not provide clarification of its bid by the date and time communicated in the Railway request for clarification, the bid shall be evaluated as per the documents submitted along with the bid.
All General Instructions are available in the uploaded tender document.
The original Bank Guarantee should be delivered in person to the official nominated as indicated in the tender document before closing date for submission of bids (i.e. excluding the last date of submission of bids). Nominated officials are Dy CE/Con/Works & Stores/GRC, S. E. Railway, Kolkata-700043 and Dy CE/Con/Tatanagar, Office of the Dy CE/Con/Tatanagar, S. E. Railway
Yard remodeling of Gamharia, Birarajpur, Kunki & Manikui for construction of formation, extension of minor bridges, FOB, platform, EI Building, approach road, side drain, retaining wall etc. including track linking, Supply & Spreading of ballast other miscellaneous works in connection with proposed 3rd & 4th line between GAMHARIA - CHANDIL Junction under jurisdiction of Dy CE/Con/TATA In construction organisation.
4637-GRC-CE-C-II-19-2026
4637-GRC-CE-C-II-19-2026
Open
Works - General
24 Months
Unknown (Unspecified Location)
₹0
₹1.9 Cr
16 Jun 2026
18 May 2026
2 Jun 2026
349 items across 9 schedules · ₹42,82,90,394.4 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Preparation of foundation for Embankment by clearing, grubbing, stripping top soil (average 150 mm) and stacking beyond foundation area, thereafter ploughing and pulverizing 150 - 200 mm of top of soil with tractor trolley, mixing water to achieve OMC with water sprinkler or left for natural drying, as required, and compaction with vibratory roller of suitable capacity to achieve 98% MDD for laying first layer of soil for embankment construction. | 100 Sqm | 48000.00 | 540.2 | 2,59,296 |
| 2 | Benching of existing embankment manually in steps of 30 cm height for doubling/tripling works in running line to provide proper amalgamation between the old and new embankments as per RDSO latest Specifications and guidelines RDSO/2020//GE: IRS-0004 to the entire satisfaction of Engineer in- charge. The item includes uprooting and disposing of all the vegetation, all lift, descends, ascends and additional earthwork required for filling due to removal of earth in benching in existing bank. Note: (1) The benching Work shall be done for a maximum height of 0.90 m at any time based on the progress of earthwork starting from toe of the embankment. (2) Benching work shall be certified and recorded before starting the earth work. (3) Unit for payment shall be km per metre height of the Bank. Height here means representative average height of the bank in the specified km taken from cross sectional measurements for earthwork. (4) Since the rate includes earthwork in steps, payment under this item shall be made after completion of earthwork to that level. (5) Cut soil from bank shall not be used in embankment construction and disposed off away from bank as per the direction of Engineer-in- charge. | Kilometre | 2.10 | 1,14,035.55 | 2,39,474.66 |
| Earthwork in filling in embankment, guide bunds, around buried type abutments, bridge gaps, trolley refuges, platforms etc. with contractor's own earth conforming to Soil Quality Class SQ1/SQ2/SQ3, after preparation of foundations as applicable, benching in existing banks wherever required, spreading in layers with motor grader, bringing the moisture content to OMC, mechanical compaction to specified density and dressing of bank to final profile as per R DSO Specifications: RDSO/2020/GE: IRS-0004 with latest correction slips. Note: 1) Foundation preparation, Benching including additional earthwork on account of this, wherever required, shall be paid extra under relevant schedule item for benching. 2) Payment for Earthwork under this item shall be made based on the cross section measurements calculated (i) with original ground profile of existing bank based on initial ground levels before doing benching and (ii) final profile of the bank worked out with final levels as per prevailing guidelines. | — | — | — | — | |
| 3 | Using Soil Class SQ1 | cum | 86300.00 | 217.19 | 1,87,43,497 |
| 4 | Using Soil Class SQ2 | cum | 129450.00 | 253.42 | 3,28,05,219 |
| Earthwork in cutting in formation, trolley refuges, side drains, level crossing approaches, platforms, catch water drains, diversion of nallah & finishing to required dimension and slopes to obtain a neat appearance to standard profile inclusive of all labour, materials, plant & machinery, leading all cut spoils either to make spoil dumps or for filling in embankment with leads within 2 km on either side of edge of the cutting(s) including all lifts, ascent, descent, loading, unloading, bailing & pumping out water, if required, clearance of site and all other works incidental thereto for completing the work as per RDSO Specification No. RDSO/2020/GE: IRS- 0004 with latest updated correction slips and to the satisfaction of the Engineer-in-Charge. Note: (i) All usable earth arising from cut spoils shall be led into bank formation and Unusable spoils shall be dumped / stacked away from toe of embankment. (ii) All hard rock /and boulders not fit for filling will be stacked by the contractor and will be property of the Railways. (iii)Cut trees shall be property of Railways and to be deposited in the railway godown unless specified otherwise in the Conditions of Contract. | — | — | — | — | |
| 5 | In all conditions and classifications of soil except rock | cum | 81541.00 | 106.59 | 86,91,455.19 |
| 6 | In hard rock with hammer / chisel / pavement breaker etc. where blasting is not permitted due to special circumstances and if specifically ordered in writing including drilling and all incidental works thereto. | cum | 41902.00 | 958.2 | 4,01,50,496.4 |
| 7 | Mechanical manufacturing of blanketing material by using only hard and durable stone crushed in mechanical crusher to different gradations, wet mixing of the same in designed proportion in Pug mill or wet mix plant to have uniform gradation including all incidental transportation, laying over finished formation in uniform layer(s) with motor grader, compaction with suitable vibratory roller to specified density and finishing to correct profile, complete as per RDSO Specification No. RDSO/2020/GE: IRS-0004 with latest correction slips. Note: This item shall be used only when entire constituent of blanketing material is mechanically manufactured by crushing of hard and durable stone into desired gradation of designed proportion. | cum | 23100.00 | 1,757.35 | 4,05,94,785 |
| Felling trees of girth (measured at a height of 1.0 m above ground level) including leading and stacking of material within 100m. Note : 1. When stumps are grubbed up in addition, the rates shall be doubled for trees cut and grubbed 2. Payment for grubbing shall only be made where specially ordered. 3. Grubbing shall be ordered only where it is essential to remove the stumps, including the roots, as per specification. 4. Grubbing shall include removal of roots of trees and saplings to a depth of 60cm below ground level or 30 cm below formation level or 15 cm below sub grade level, whichever is lower. | — | — | — | — | |
| 8 | Girth over 30 cm and up to 60 cm | Each | 1500.00 | 351.2 | 5,26,800 |
| Turfing / planting, including all lead & lift and watering as required until properly rooted with. Note: Initially payment of only 40% will be made. Balance 60% will be paid after 3 months of maintenance period, only if the turfing is properly rooted on entire turfed area. | — | — | — | — | |
| 9 | Turfing with sods, 10cm thick and 20cm square closely laid. | 100 Sqm | 4800.00 | 5,460.99 | 2,62,127.52 |
| Provision of barricading with contractor's bamboos / ballies vertical post of 100mm dia. planted at every 2m interval, projecting at least 1.5m above ground level and driven firmly (minimum 0.5m) inside ground and including painting verticals & horizontals with red luminous paints / strips at alternative bay on barricade. Barricades shall be maintained through out the execution of the work and shall be removed in workman like manner on completion of the work only after instruction of Engineer in- Charge. Note: (1) 60% payment shall be made on provision of barricading at work-site and balance 40% payment after removal of barricades. (2) The released bamboos / ballies shall be the property of the Contractor. | — | — | — | — | |
| 10 | With 3 horizontal bamboo / balli members of minimum 50mm dia. spaced equally | RM | 8000.00 | 127.48 | 10,19,840 |
| Schedule total | ₹14,32,92,990.77 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
BarChart.pdf
ATTACHMENT
AdvanceCorrectionSlipNo1to11.pdf Advance Correction Slips
ATTACHMENT
TD19-2026.pdf
ATTACHMENT
GCCApril-2022.pdf
ATTACHMENT
AdvanceCorrectionSlipNo1to11.pdf
ATTACHMENT
All_Works_dept_for_Rule_55.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .