| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹28.1 LAccepted-Finance | ₹28.1 L | L1 | Accepted-Finance L1 lowest bidder |
| 2 | L2₹30.2 L+₹2.2 L (7.69%)Accepted-Finance | ₹30.2 L+₹2.2 L (7.69%) | L2 | Accepted-Finance L2 bidder |
| 3 | L3₹31.7 L+₹3.7 L (13.1%)Accepted-Finance | ₹31.7 L+₹3.7 L (13.1%) | L3 | Accepted-Finance L3 bidder |
| 4 | L4₹32.2 L+₹4.1 L (14.6%)Accepted-Finance | ₹32.2 L+₹4.1 L (14.6%) | L4 | Accepted-Finance L4 bidder |
| 5 | L5₹32.3 L+₹4.3 L (15.2%)Accepted-Finance | ₹32.3 L+₹4.3 L (15.2%) | L5 | Accepted-Finance L5 bidder |
Tender Value
₹43.2 L
EMD Value
₹43,200
Closing Date
5 May 2026, 1:00 pmClosed
SE RANDB KHURDA
O/o the SUPERINTENDING Engineer R and B Division, Khurda
Renovation of Boys Hostel ITI Krushnaprasad (such as Fixing of WPC Door and UPVC Window and Internal and External Painting, Tile flooring and Fixing of G.I Grills etc).
2026_EICCL_128371_2
TCN-54/25-26
Open Tender
Civil Works - Buildings
Percentage
90 days
Khordha
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹43,200
Yes
28 Jul 2026
23 Apr 2026
6 May 2026
23 Apr 2026
5 May 2026
23 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Removing old lime or cement plaster from walls including raking out joints 12 mm. Deep (1/2) stackiong the useful materials for reuse and removing the debris within 50 m. lead including all labour, labour cess, T&P etc. complete as directed by the Engineer-in-charge.
in Ground Floor | - | Sqm | - | - |
| 2 | Removing old lime or cement plaster from walls including raking out joints 12 mm. Deep (1/2) stackiong the useful materials for reuse and removing the debris within 50 m. lead including all labour, labour cess, T&P etc. complete as directed by the Engineer-in-charge.
(in First Floor) | - | Sqm | - | - |
| 3 | Removing old lime or cement plaster from walls including raking out joints 12 mm. Deep (1/2) stackiong the useful materials for reuse and removing the debris within 50 m. lead including all labour, labour cess, T&P etc. complete as directed by the Engineer-in-charge.
(inSecond Floor) | - | Sqm | - | - |
| 4 | 16 mm thick cement plaster of proportion (1:6) finished smooth to inside brick work after racking out joints including watering and curing, cost, conveyance, royalities of all materials with all labour, labour cess and T&P required for the work etc complete in all respect as per direction of the Engineer-in-charge
(In ground floor) | - | Sqm | - | - |
| 5 | 16 mm thick cement plaster of proportion (1:6) finished smooth to inside brick work after racking out joints including watering and curing, cost, conveyance, royalities of all materials with all labour, labour cess and T&P required for the work etc complete in all respect as per direction of the Engineer-in-charge
(In First Floor) | - | Sqm | - | - |
| 6 | 16 mm thick cement plaster of proportion (1:6) finished smooth to inside brick work after racking out joints including watering and curing, cost, conveyance, royalities of all materials with all labour, labour cess and T&P required for the work etc complete in all respect as per direction of the Engineer-in-charge
(In Second Floor) | - | Sqm | - | - |
| 7 | Scraping old paint with scrapers, sand papering and washing with soap water or soda including scaffolding charges up to 5m height with cost of all labour, labour cess, T&P required for the work etc complete as per direction of the Engineer-In-Charge. | - | Sqm | - | - |
| 8 | Scraping old paint with scrapers, sand papering and washing with soap water or soda including scaffolding charges above 5m height and upto 8mtr height with cost of all labour, labour cess, T&P required for the work etc complete as per direction of the Engineer-In-Charge. | - | Sqm | - | - |
| 9 | Wall painting two coats to wall surface with any approved Plastic Emulsion paint of approved shade over a coat water bound cement primer on new work to give an even shade after cleaning surface including cost of all materials, labour, labour cess, T&P required for the work etc complete as per direction of the Engineer-In-Charge.
(In Ground Floor) | - | Sqm | - | - |
| 10 | Wall painting two coats to wall surface with any approved Plastic Emulsion paint of approved shade over a coat water bound cement primer on new work to give an even shade after cleaning surface including cost of all materials, labour, labour cess, T&P required for the work etc complete as per direction of the Engineer-In-Charge. (In First Floor) | - | Sqm | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.18 MB
Tendernotice_2.pdf
PDF • 0.50 MB
BOQ_588495.xls
BOQ • 0.41 MB
dtcn2.pdf
Tender Documents • 1.93 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .