Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹1.2 L
EMD Value
₹2,400
Closing Date
4 Dec 2025, 10:30 amClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
EE(C), BR-VII
9/1A, AJC BOSE ROAD, KOL-17
IMPROVEMENT OF UTTARAN SEWER LINE AND ITS RESTORATION AT 31,TANGRA RD NEAR GROSSARY SHOP AND ITS SURROUNDING UTTARAN AREA IN WARD 58
2025_KMC_945103_4
KMC/VII/APAS/25-26/1
Open Tender
CIVIL WORKS
Percentage
30 days
BOROUGH VII, KMC
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹2,400
6 Dec 2025
12 Nov 2025
6 Dec 2025
12 Nov 2025
4 Dec 2025
12 Nov 2025
BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm.
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(ii) 225 mm
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(iii) 150 mm
BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( 3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 1. Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation (b) 1:4:8 proportion. ( 3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 4. Brick-on-edge floor or pavement with 1st class brick set close in cement mortar (1:6) and laid with cushion of sand below (including cost thereof) including ruled or flush pointing with cement mortar (1:4) on top. ( 3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 13. Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (a) In foundation and plinth. ( 3rd Corrigenda & addenda dated 04.06.2018)
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (a) 20 mm thick plaster(3rd Corrigenda & addenda dated 04.06.2018)
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 15 Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m.
SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC. (a) Original Works 1.Constructing Inspection pit of inside measurement 600mm X 600mm X upto 600mm(depth) with 250 mm thick 1st. class brick work in cement mortar (1:4) on all sides, bottom of the pit consisting of 100 mm thick cement concrete (1:3:6) with stone chips over a layer of jhama brick flat soling, 15 mm thick (1:4) cement plaster to inside walls and out-side walls upto G.L. and 20 mm.thick (1:4) plaster to bottom of the pit, providing necessary invert with cement concrete (1:3:6) with stone chips as per direction, neat cement finishing to entire internal surfaces, top of the pit covered with 100 mm thick R.C.C. slab (1:1.5:3) with stone chips and necessary reinforcements upto 1% and shuttering including 6 mm thick cement plaster (1:4) in all external surfaces of the slab and one 560 mm dia. R.C.C. manhole cover of approved make supplied, fitted and fixed in the slab with necessary fittings, necessary earthwork in excavation in all sorts of soil, filling sides of the pit with earth and removing spoils after work complete in all respect with all costs of labour and materials.i) With Pakur variety (Other than SAIL/TATA/RINL).
SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC. (a) Original Works 1.Constructing Inspection pit of inside measurement 600mm X 600mm X upto 600mm(depth) with 250 mm thick 1st. class brick work in cement mortar (1:4) on all sides, bottom of the pit consisting of 100 mm thick cement concrete (1:3:6) with stone chips over a layer of jhama brick flat soling, 15 mm thick (1:4) cement plaster to inside walls and out-side walls upto G.L. and 20 mm.thick (1:4) plaster to bottom of the pit, providing necessary invert with cement concrete (1:3:6) with stone chips as per direction, neat cement finishing to entire internal surfaces, top of the pit covered with 100 mm thick R.C.C. slab (1:1.5:3) with stone chips and necessary reinforcements upto 1% and shuttering including 6 mm thick cement plaster (1:4) in all external surfaces of the slab and one 560 mm dia. R.C.C. manhole cover of approved make supplied, fitted and fixed in the slab with necessary fittings, necessary earthwork in excavation in all sorts of soil, filling sides of the pit with earth and removing spoils after work complete in all respect with all costs of labour and materials.iii) Extra for each additional depth of 150 mm or part thereof beyond initial 600 mm depth.
SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC.8.Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame.As per I.S-12592(M.D) (vi) 5 MT load bearing capacity round manhole cover provided with two lifter hooks fitted with matching frame of size Cover: 565 mm X 65 mm Frame: 665 mm X 125 mm opening: 470mmWeight: 90 kg (approx)
SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC.8.Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame.As per I.S-12592(M.D) (viii) 5 MT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size (viii) 5 MT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size Cover: 470 mm X 420 mm X 80 mm Frame: 590 mm X 550 mm X 170 mm opening: 380mm x 305mm Weight: 100 kg (approx)
Earthwork in cutting to form road section in correct profile including removal of spoils not exceeding initial lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post works) (i) In ordinary soil
ORDINARY CEMENT CONCRETE ( MIX 1:2:4 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES
Sub Total
tech_bid_open.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.12 MB
TF1631282.pdf
Tender Documents • 0.58 MB
BOQ_2245950.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .