| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹86.3 LAdmitted-Finance | -32.99% | ₹86.3 L | L1 | Admitted-Finance |
| 2 | L2₹93.3 LAdmitted-Finance | -27.55% | ₹93.3 L | L2 | Admitted-Finance |
| 3 | L3₹94.0 LAdmitted-Finance | -27.00% | ₹94.0 L | L3 | Admitted-Finance |
| 4 | L4₹97.5 LAdmitted-Finance | -24.31% | ₹97.5 L | L4 | Admitted-Finance |
| 5 | L5₹97.8 LAdmitted-Finance | -24.05% | ₹97.8 L | L5 | Admitted-Finance |
Tender Value
₹1.3 Cr
EMD Value
₹2.6 L
Closing Date
27 Mar 2026, 3:00 pmClosed
EE,RMD-8,ROHINI ZONE,DDA
EE,RMD-8,ROHINI ZONE,DDA
Additional civil work at community Hall Block E Sector -16 Rohini.
2026_DDA_902784_1
13/EE/RMD-8/DDA/2026-27
Open Tender
Civil Works
60 days
Rohini
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹2.6 L
16 Apr 2026
19 Mar 2026
28 Mar 2026
19 Mar 2026
27 Mar 2026
19 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1Excavating holes more than 0.10 cum & up to 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto1.5 m. (a)All kinds of soil. | ||||||
| 2Centering and shuttering including strutting, propping etc. and removal of form for | ||||||
| 2.1 | (a)Suspended floors, roofs, landings, balconies and access platform | 1 | sqm | - | - | BI01010001010000000000000515BI0100001115 |
| 2.2 | (b)Lintels, beams, plinth beams, girders, bressumers and cantilevers | 1 | sqm | - | - | BI01010001010000000000000515BI0100001116 |
| 3Edges of slabs and breaks in floors and walls Under 20 cm wide | ||||||
| 4Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand(zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | ||||||
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-Ill) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). | 1 | cum | - | - | BI01010001010000000000000515BI0100001119 |
| 6Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level. (a)Thermo-Mechanically Treated bars of grade Fe-500D or more. | ||||||
| 7Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. (a)In cement mortar | ||||||
| 8Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : (A) Cement mortar 1:6 (1 cement : 6 coarse sand) | ||||||
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.93 MB
BOQ_948897.xls
BOQ • 0.38 MB
NIT13.pdf
Tender Documents • 2.44 MB
Download all tender documents and submit your bid