| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.5 LAccepted-AOC | ₹7.5 L | L1 | Accepted-AOC LER |
| 2 | L2₹7.7 LRejected-Finance | ₹7.7 L | L2 | Rejected-Finance Above Estimate Rate |
| Sl No | Description | Qty | Unit | DESABANDHU ANBUDASAN L2 | R.SAMMANDHAM CONTRACTOR L1 |
|---|---|---|---|---|---|
| 1.00Part-01-Renovation of PUES West Facing Three Class Room at Nadur Panchayat | |||||
| 2.00 | Clean removal of Cement Plaster from Walls | 48.83 | Sq.m | 8.2 ₹400.41 | 8 ₹390.64 |
| 3.00 | Plastering the surface of walls with Cement Mortar 1:3 (One cement and Three M.Sand), 10mm thick in all floors including curing etc., complete complying with standard specification and as directed by the departmental officers. | 7.5 | Sq.m | 320.83 ₹2,406.23 | 313 ₹2,347.50 |
| 4.00 | Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers. | 41.33 | Sq.m | 280.85 ₹11,607.53 | 274 ₹11,324.42 |
| 5.00 | Finishing the top of roof with One Course of Machine Pressed Tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers | 28.13 | Cu.m | 1,304.83 ₹36,704.87 | 1,273 ₹35,809.49 |
| 6.00 | White washing two coats with freshly burnt white shell lime in all floors including cost of lime, blue powder fevicol type gum, brushes, scaffolding charges, etc., complete complying with standard specification and as directed. | 101.38 | Sq.m | 36.9 ₹3,740.92 | 36 ₹3,649.68 |
| 7.00 | Re Painting the Walls with Two Coats with First Class Quality Plastic Emulsion Paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358 | 149.8 | Sq.m | 259.33 ₹38,847.63 | 253 ₹37,899.40 |
| 8.00 | Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) | 28.24 | Sq.m | 154.78 ₹4,370.99 | 151 ₹4,264.24 |
| 9.00 | Painting two coats with approved Black Board Painting including all labour charges etc. | 5.28 | Sq.m | 153.75 ₹811.80 | 150 ₹792 |
| 10.00Electrical Arrangements | |||||
Tender Value
₹11,300
EMD Value
₹11,300
Closing Date
18 Jul 2025, 6:00 pmClosed
Block Development officer(BP), Orathanadu,Thanjavu
Block Development officer(BP), Orathanadu,Thanjavur
Pck.IVA.Nadur Pt 1.Renovation of PUES West Facing 3 Cl.room 2.Reno of PUES North side 2 Cl.room 3.Repairs to PUES Girls Toilet at Nadur 4.Repairs to PUES Boys Toilet at Nadur Pt in Orathanadu Block of Thanjavur District under SIUS Scheme 2025-26
2025_RDTN_579915_1
Rc.No.877/2025/A2 dated.07.07.2025
Open Tender
Civil Works - Buildings
120 days
Orathanadu
As per Tender document
9 documents required · 9 mandatory
₹0
₹11,300
21 Jan 2026
9 Jul 2025
18 Jul 2025
9 Jul 2025
18 Jul 2025
9 Jul 2025
Amount
Part-01-Renovation of PUES West Facing Three Class Room at Nadur Panchayat
Clean removal of Cement Plaster from Walls
Plastering the surface of walls with Cement Mortar 1:3 (One cement and Three M.Sand), 10mm thick in all floors including curing etc., complete complying with standard specification and as directed by the departmental officers.
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Finishing the top of roof with One Course of Machine Pressed Tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers
White washing two coats with freshly burnt white shell lime in all floors including cost of lime, blue powder fevicol type gum, brushes, scaffolding charges, etc., complete complying with standard specification and as directed.
Re Painting the Walls with Two Coats with First Class Quality Plastic Emulsion Paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358
Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use)
Painting two coats with approved Black Board Painting including all labour charges etc.
Electrical Arrangements
Wiring with 2 x 1.50 sqm (22/0.30) PVC insulated Sc unsheathed copper conductor of 1100 V grade insutable PVC Rigid pipe on wall and ceiling with PVC accessories and with TW switch box and 5 A FT switch with painting of suitable colour for open PVC Light point / Fan point (SD 17)
Wiring with 2 x 1.50 sqm (22/0.30) PVC insulated Sc unsheathed copper conductor of 1100 V grade insutable PVC Rigid pipe on wall and ceiling with PVC accessories in flush with wall with 150 mm x 100 mm x 113 mm TW switch box with 3mm thick hylem sheet cover for 5 A 3 pin non interlocking wall socket with 5A flush type switch with continious conceld PVC Plun point (SD 38)
Supply and Run of 2 of 6 sqmm (84/0.30) PVC Insulated SC unsheathed copper conductor of 100 V on 7/20 GI bearer wire for service connection mains (SD 66)
Supply and fixing of WT Bulk head fittings with guard (philips/bajaj/Crompton/K lite) suitable for 11 W CFL Lamp (SD 83)
Supply and fixing of Tube light fittings with guard (philips/bajaj/Crompton/K lite) suitable for 11 W CFL Lamp (SD 89)
Supply and fixing of 1200 mm 48" AC Ceiling fan complete with stepped electronic 300 W regulator with 300 mm down rod on the existing clamp (SD 110)
Teachers Cupboard
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Supply & Fixing of 35mm thk.single leaf high density interior grade marine plywood shutters pasted both sides 1.5mm thk.laminate approved design with 35x12mm T.W.lipping on all edges with necessary adhesives and CP screws complying with standard specification.The cost is inclusive of 1 no cylindrical Lock,handel,tower bolt ,approved equivalent make SS ball bearing hinges of quivalent make of aproved make,2 no floor mounted SS door stoper ect.complete as per drawing. Make: Kutty,Sharon, Trojan. Accesseorice Make: Dorma, Godrej.1.5mm thk Laminate Basic Cost:810/M2 .
Student Cupboard
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Painting the walls with two coats Exterior Emulsion Paint over one coat of primer as instructed including cost of materils and all labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Cheppal Rack
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Painting the walls with two coats Exterior Emulsion Paint over one coat of primer as instructed including cost of materils and all labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Rain water Harvesting
Earth work excavation in all class of Soil except hard rock requiring blasting with intial lead and lift etc. Complete for foundation as per SS 20A
Cost and supply of 40mm HBG metal including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of 20mm HBG metal including cost & conveyance & Labour charges etc, Complete.,.
Supply and filling of good river sand including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of RCC Ring including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of RCC cover slab including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of 110 mm dia PVC Rain water down fall pipe including cost & conveyance & Labour charges etc, Complete.,.
Labour charges for soak pit and filling metal including cost & conveyance & Labour charges etc, Complete.,.
Provision for Name Board charges
Provision for photo charges
Part-02-Renovation of PUES West side North Facing Two Class Room at Nadur Panchayat
Clean removal of Cement Plaster from Walls
Plastering the surface of walls with Cement Mortar 1:3 (One cement and Three M.Sand), 10mm thick in all floors including curing etc., complete complying with standard specification and as directed by the departmental officers.
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Finishing the top of roof with One Course of Machine Pressed Tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers
White washing two coats with freshly burnt white shell lime in all floors including cost of lime, blue powder fevicol type gum, brushes, scaffolding charges, etc., complete complying with standard specification and as directed.
Re Painting the Walls with Two Coats with First Class Quality Plastic Emulsion Paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358
Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use)
Painting two coats with approved Black Board Painting including all labour charges etc.
Electrical Arrangements
Wiring with 2 x 1.50 sqm (22/0.30) PVC insulated Sc unsheathed copper conductor of 1100 V grade insutable PVC Rigid pipe on wall and ceiling with PVC accessories and with TW switch box and 5 A FT switch with painting of suitable colour for open PVC Light point / Fan point (SD 17)
Wiring with 2 x 1.50 sqm (22/0.30) PVC insulated Sc unsheathed copper conductor of 1100 V grade insutable PVC Rigid pipe on wall and ceiling with PVC accessories in flush with wall with 150 mm x 100 mm x 113 mm TW switch box with 3mm thick hylem sheet cover for 5 A 3 pin non interlocking wall socket with 5A flush type switch with continious conceld PVC Plun point (SD 38)
Supply and Run of 2 of 6 sqmm (84/0.30) PVC Insulated SC unsheathed copper conductor of 100 V on 7/20 GI bearer wire for service connection mains (SD 66)
Supply and fixing of WT Bulk head fittings with guard (philips/bajaj/Crompton/K lite) suitable for 11 W CFL Lamp (SD 83)
Supply and fixing of Tube light fittings with guard (philips/bajaj/Crompton/K lite) suitable for 11 W CFL Lamp (SD 89)
Supply and fixing of 1200 mm 48" AC Ceiling fan complete with stepped electronic 300 W regulator with 300 mm down rod on the existing clamp (SD 110)
Teachers Cupboard
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Supply & Fixing of 35mm thk.single leaf high density interior grade marine plywood shutters pasted both sides 1.5mm thk.laminate approved design with 35x12mm T.W.lipping on all edges with necessary adhesives and CP screws complying with standard specification.The cost is inclusive of 1 no cylindrical Lock,handel,tower bolt ,approved equivalent make SS ball bearing hinges of quivalent make of aproved make,2 no floor mounted SS door stoper ect.complete as per drawing. Make: Kutty,Sharon, Trojan. Accesseorice Make: Dorma, Godrej.1.5mm thk Laminate Basic Cost:810/M2 .
Student Cupboard
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Painting the walls with two coats Exterior Emulsion Paint over one coat of primer as instructed including cost of materils and all labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Cheppal Rack
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Painting the walls with two coats Exterior Emulsion Paint over one coat of primer as instructed including cost of materils and all labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Rain water Harvesting
Earth work excavation in all class of Soil except hard rock requiring blasting with intial lead and lift etc. Complete for foundation as per SS 20A
Cost and supply of 40mm HBG metal including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of 20mm HBG metal including cost & conveyance & Labour charges etc, Complete.,.
Supply and filling of good river sand including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of 110 mm dia PVC Rain water down fall pipe including cost & conveyance & Labour charges etc, Complete.,.
Provision for Name Board charges
Provision for photo charges
Part-03-Renovation of PUES East side North Facing Two Class Room at Nadur Panchayat
Clean removal of Cement Plaster from Walls
Plastering the surface of walls with Cement Mortar 1:3 (One cement and Three M.Sand), 10mm thick in all floors including curing etc., complete complying with standard specification and as directed by the departmental officers.
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Finishing the top of roof with One Course of Machine Pressed Tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers
White washing two coats with freshly burnt white shell lime in all floors including cost of lime, blue powder fevicol type gum, brushes, scaffolding charges, etc., complete complying with standard specification and as directed.
Re Painting the Walls with Two Coats with First Class Quality Plastic Emulsion Paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358
Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use)
Painting two coats with approved Black Board Painting including all labour charges etc.
Electrical Arrangements
Wiring with 2 x 1.50 sqm (22/0.30) PVC insulated Sc unsheathed copper conductor of 1100 V grade insutable PVC Rigid pipe on wall and ceiling with PVC accessories and with TW switch box and 5 A FT switch with painting of suitable colour for open PVC Light point / Fan point (SD 17)
Wiring with 2 x 1.50 sqm (22/0.30) PVC insulated Sc unsheathed copper conductor of 1100 V grade insutable PVC Rigid pipe on wall and ceiling with PVC accessories in flush with wall with 150 mm x 100 mm x 113 mm TW switch box with 3mm thick hylem sheet cover for 5 A 3 pin non interlocking wall socket with 5A flush type switch with continious conceld PVC Plun point (SD 38)
Supply and Run of 2 of 6 sqmm (84/0.30) PVC Insulated SC unsheathed copper conductor of 100 V on 7/20 GI bearer wire for service connection mains (SD 66)
Supply and fixing of WT Bulk head fittings with guard (philips/bajaj/Crompton/K lite) suitable for 11 W CFL Lamp (SD 83)
Supply and fixing of Tube light fittings with guard (philips/bajaj/Crompton/K lite) suitable for 11 W CFL Lamp (SD 89)
Supply and fixing of 1200 mm 48" AC Ceiling fan complete with stepped electronic 300 W regulator with 300 mm down rod on the existing clamp (SD 110)
Teachers Cupboard
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Supply & Fixing of 35mm thk.single leaf high density interior grade marine plywood shutters pasted both sides 1.5mm thk.laminate approved design with 35x12mm T.W.lipping on all edges with necessary adhesives and CP screws complying with standard specification.The cost is inclusive of 1 no cylindrical Lock,handel,tower bolt ,approved equivalent make SS ball bearing hinges of quivalent make of aproved make,2 no floor mounted SS door stoper ect.complete as per drawing. Make: Kutty,Sharon, Trojan. Accesseorice Make: Dorma, Godrej.1.5mm thk Laminate Basic Cost:810/M2 .
Student Cupboard
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Painting the walls with two coats Exterior Emulsion Paint over one coat of primer as instructed including cost of materils and all labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Cheppal Rack
Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed
Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed
Painting the walls with two coats Exterior Emulsion Paint over one coat of primer as instructed including cost of materils and all labour charges etc., completed
Supplying and fixing of Cuddappa Slab for CupBoard including cost and conveyance of
Rain water Harvesting
Earth work excavation in all class of Soil except hard rock requiring blasting with intial lead and lift etc. Complete for foundation as per SS 20A
Cost and supply of 40mm HBG metal including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of 20mm HBG metal including cost & conveyance & Labour charges etc, Complete.,.
Supply and filling of good river sand including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of RCC Ring including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of RCC cover slab including cost & conveyance & Labour charges etc, Complete.,.
Cost and supply of 110 mm dia PVC Rain water down fall pipe including cost & conveyance & Labour charges etc, Complete.,.
Labour charges for soak pit and filling metal including cost & conveyance & Labour charges etc, Complete.,.
Provision for Name Board charges
Provision for photo charges
Part-04-Repair of PUES Girls Toilet at Nadur Panchayat
Clean removal of Cement Plaster from Walls
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
White washing two coats with freshly burnt white shell lime in all floors including cost of lime, blue powder fevicol type gum, brushes, scaffolding charges, etc., complete complying with standard specification and as directed.
Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the walls smooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification. (The colour and shade of the distemper shall be got approved by the Executive Engineer before use of work).
Re Painting the Walls with Two Coats with First Class Quality Plastic Emulsion Paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358
Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use)
Part-05-Repair of PUES Boys Toilet at Nadur Panchayat
Clean removal of Cement Plaster from Walls
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
White washing two coats with freshly burnt white shell lime in all floors including cost of lime, blue powder fevicol type gum, brushes, scaffolding charges, etc., complete complying with standard specification and as directed.
Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the walls smooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification. (The colour and shade of the distemper shall be got approved by the Executive Engineer before use of work).
Re Painting the Walls with Two Coats with First Class Quality Plastic Emulsion Paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358
Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use)
GST Amount for providing Service to Government Contract Works for the above Construction Works. {GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
DESABANDHU ANBUDASAN (BID ID -1405833)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid