Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | I₹1.0 CrAccepted-AOC | I | Accepted-AOC L1 | |
| 2 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | S.RANGANATHAN L1 |
|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum | 700 | M3 | 110 ₹77,000 Lowest |
| 2.00 | Providing Granular surface base to the required surface using murram, Granular soil of size varying from 4mm to 75mm including cost of material and cost of labour for stacking, spreading and consolidating layer by layer (Each layer not exceeding 100mm) including hire charges of Roller etc, complete as per the direction of Departmental officers. | 742 | M3 | 650 ₹4,82,300 Lowest |
| 3.00 | Providing of Granular Sub base using Grade I materials of table 400 -1 of Morth with minimum CBR 30 spreading in uniform layers with motor grader on prepared surface, mix in by palce method at OMC and compacting with Vibratory Roller to achieve the desired density including all labourcharges etc, complete as per technical specification and as directed by the departmental officers. Morth - Rev V No. 111,112,401,900 | 406 | M3 | 1,600 ₹6,49,600 Lowest |
| 4.00 | Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications. | 256 | M3 | 2,050 ₹5,24,800 Lowest |
| 5.00 | Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications | 1,705 | M2 | 85 ₹1,44,925 Lowest |
| 6.00 | Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications | 1,705 | M2 | 20 ₹34,100 Lowest |
| 7.00 | Providing and laying tack coat of 2kgs/10 sqm over the existing BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications | 848 | M2 | 25 ₹21,200 Lowest |
| 8.00 | Providing and laying 50 mm compacted thick dense bituminous macadam using 0.24 cum of 26.5-13.2 mm graded metal and 0.25 cum of 13.2-2.36 mm graded metal and 0.23 cum of 2.36 mm & below metal with 53.20 kgs of 60/70 bitumen for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site,spreading the mix in required temperature for uniform thickness of 50mm with Hydro static paver finisher with sensor controlled to the required gradient and alignment to the specified grades and cross sections and compaction by Vibratory roller to the required density etc.,including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, hydro static sensor controlled paver finisher, vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 505 of MORTH Rev-5 specifications. | 127.65 | M3 | 9,200 ₹11,74,380 Lowest |
| 9.00 | Providing and laying Bituminous concrete to 30mm thick using 0.13 cum of 19.00-9.50 mm graded metal and 0.17 cum of 9.50-2.36 mm graded metal and 0.26 cum of 2.36 mm & below metal with 45.27 kgs of 60/70 bitumen & 5.03Kg of Plastic waste (Total-50.30 kg) (as per IRC SB 098 ) and for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site, spreading the mix in required temperature for uniform thickness of 30mm with hydro static paver finisher with sensor controled to the required gradient and alignment to the specified grades and cross sections and compaction by Vibratory roller to the required density etc., including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, sensor conroled hydro static paver finisher, Vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 507 of MORTH Rev-5 specifications. | 76.6 | M3 | 9,200 ₹7,04,720 Lowest |
| 10.00 | Earth Work excavting and depositing on bank with initial lead of 10m & initial lift of 2m in Sand,Silt or other loose soil,wet sand or silt not under water,light black cotton soil sandy loam and ordinary soil including excavated earth etc completed as per the standard specifications | 464 | M3 | 137 ₹63,568 Lowest |
Tender Value
₹1.5 Cr
EMD Value
₹1.5 L
Closing Date
21 Jan 2026, 3:00 pmClosed
Commissioner Kancheepuram Corporation
Kancheepuram city municipal corporation, Annai Indira Gandhi Salai, Kancheepuram
FORMATION OF APPROACH ROAD AND CONSTRUCTION OF RCC RETAINING WALL AND STREET LIGHT ARRANGMENTS IN MINOR BIRDGE AT THATTITHOPPU IN KANCHEEPURAM CORPORATION
2026_MAWS_639595_3
6209/2025/E1
Open Tender
Civil Works
Item Rate
Kancheepuram Corporation
Please refer Tender documents.
9 documents required · 9 mandatory
₹0
₹1.5 L
8 Oct 2026
6 Jan 2026
21 Jan 2026
6 Jan 2026
21 Jan 2026
6 Jan 2026
6 Jan 2026 - 21 Jan 2026
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum
Providing Granular surface base to the required surface using murram, Granular soil of size varying from 4mm to 75mm including cost of material and cost of labour for stacking, spreading and consolidating layer by layer (Each layer not exceeding 100mm) including hire charges of Roller etc, complete as per the direction of Departmental officers.
Providing of Granular Sub base using Grade I materials of table 400 -1 of Morth with minimum CBR 30 spreading in uniform layers with motor grader on prepared surface, mix in by palce method at OMC and compacting with Vibratory Roller to achieve the desired density including all labourcharges etc, complete as per technical specification and as directed by the departmental officers. Morth - Rev V No. 111,112,401,900
Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications.
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications
Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications
Providing and laying tack coat of 2kgs/10 sqm over the existing BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Providing and laying 50 mm compacted thick dense bituminous macadam using 0.24 cum of 26.5-13.2 mm graded metal and 0.25 cum of 13.2-2.36 mm graded metal and 0.23 cum of 2.36 mm & below metal with 53.20 kgs of 60/70 bitumen for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site,spreading the mix in required temperature for uniform thickness of 50mm with Hydro static paver finisher with sensor controlled to the required gradient and alignment to the specified grades and cross sections and compaction by Vibratory roller to the required density etc.,including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, hydro static sensor controlled paver finisher, vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 505 of MORTH Rev-5 specifications.
Providing and laying Bituminous concrete to 30mm thick using 0.13 cum of 19.00-9.50 mm graded metal and 0.17 cum of 9.50-2.36 mm graded metal and 0.26 cum of 2.36 mm & below metal with 45.27 kgs of 60/70 bitumen & 5.03Kg of Plastic waste (Total-50.30 kg) (as per IRC SB 098 ) and for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site, spreading the mix in required temperature for uniform thickness of 30mm with hydro static paver finisher with sensor controled to the required gradient and alignment to the specified grades and cross sections and compaction by Vibratory roller to the required density etc., including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, sensor conroled hydro static paver finisher, Vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 507 of MORTH Rev-5 specifications.
Earth Work excavting and depositing on bank with initial lead of 10m & initial lift of 2m in Sand,Silt or other loose soil,wet sand or silt not under water,light black cotton soil sandy loam and ordinary soil including excavated earth etc completed as per the standard specifications
Supplying and filling in foundation, basement, etc with Dust filling in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Plain Cement Concrete 1:4:8 mix (One Cement, Four crushed stone sand and Eight Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28).
Vibrated reinforced cment concrete (Design mix)using 20 mm ISG HB4 graded metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but formwork and centering soft water labour charges for mixing, transportation, placing in position, vibrating and compacting, finishing and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges etc., complete as per standard specification for retaining wall.
Supply fabrication and placing of steel reinforcement using FE 415 and TMT rods including cost and conveyance of steel and all labour charges etc complete
supply and fixing of 65 mm dia. (2 -1/2") GI pipe (class B) of 6 metre length with 300mm x 300mm x 6mm MS base plate duly welded at the bottom with concreting with construction of masonary pedestal with suitable SMC box with door arrangement to house 6A SP MCB switch, 2/4 way connector on suitable hylem sheet and supply and fixing of 48W LED street light fitting with LED (Higher end) with 1 metre 32mm dia. GI pipe (class B) Complete with suitable MS clamps for LED steet light fitting and SMC box with PVC unsheathed copper leads from SMC box to fitting and with painting of suitable colour . SD 465
Supply and laying of 2 x 16 sq.mm PVC armoured LTUG cable in a trench to be excavated at a depth of 0.75 metre putting 0.15 metre layer of sand and covering the cable completely with bricks and sand and refilling the earth to make good SD 177
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.09 MB
BOQ_765764.xls
BOQ • 0.30 MB
thattithoppuuntied146L.pdf
Tender Documents • 0.84 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .