| # | Company | Rank | Status |
|---|---|---|---|
| 1 | 1Accepted-AOC | 1 | Accepted-AOC QUOTED BIDDER |
| 2 | 2Accepted-AOC | 2 | Accepted-AOC QUOTED BIDDER |
| 3 | 3Rejected-AOC | 3 | Rejected-AOC REJECTED |
| 4 | 4Rejected-AOC | 4 | Rejected-AOC REJECTED |
| 5 | Rejected-Technical | - | Rejected-Technical REJECTED |
Tender Value
₹15 Cr
EMD Value
₹7.5 L
Closing Date
13 Jun 2022, 3:00 pmClosed
M.G.GIRGAONKAR
VVCMC
Providing and fixing foothpaths,dividers and kerb stones on Panel basis for the year 2022-23,2023-24 and 2024-25 in vvcmc area.
2022_VVCMC_800281_1
VVCMC/CE/PWD/YEARLY TENDERS/N.T.NO.18/2022
Open Tender
Civil Works
1095 days
VVCMC
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,900
₹7.5 L
VVCMC
12 May 2023
20 May 2022
15 Jun 2022
20 May 2022
13 Jun 2022
20 May 2022
30 May 2022
Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum including dressing section to the required grade, camber and side slopes and conveying the excavated materials with all lifts upto a lead of 50m. and spreading for embankment or stacking as directed.
Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm thick including hand packing and compacting etc. complete.
Providing and laying in situ / ready mix cement concrete of M10 proportion with trap/ granite/ quartzite/ gneiss metal in foundation including necessary form work, compacting and curing etc. complete. (with reversible drum type mixer/ concrete batch mix plant (pan mixer)) with SCADA with Natural / VSI standard Artificial Sand)
Providing and fixing heavy duty inter locking concrete Coloured paving blocks of 60 mm thickness of having a strength of 300 kg/Sq.cm. of approved quality and shape on a bed of crushed sand of 25 to 30 mm thick including skirting joints and cleaning etc. complete
Providing PCC Precast factory made kerb stone of 500 x 400 x 150 mm size for in M20 grade of concrete using design mix with minimum cement content as per IS 456 for moderate exposure condition including fixing in pcc1.2.4 250mm thick filling in joint with CM 1.3 pointing in CM on exposed faces etc. complete including painting in two coats of oil paint to exposed surfaces one coat of primer & excavation and disposal of excavated material, making good the road etc. complete.
Providing and casting in situ or precast tapering R.C.C.M-20 Barrier type Kerb without gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C. M-20 Semi Barrier type Kerb without gutter ( as per IRC 86 1983) embedded 125mm below ground level lover M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C M-20 Mountable type Kerb without gutter ( as per IRC86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C.M-20 Barrier type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C.M-20 Semi Barrier type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the (same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete
Batching and Mixing PlantProviding and casting in situ or precast tapering R.C.C. M-20 Mountable type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing sand faced plaster externally in cement mortar using approved screened sand, in all positions including base coat of 15 mm thick in cement mortar 1:4 using waterproofing compound at 1 Kilogramper cement bag curing the same for not less than 2 days and keeping the surface of the base coat rough to receive the sand faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing the surface by taking out grains and curing for fourteen days scaffolding etc.complete
Providing and fixing of precast parabolic RCC Diveder of 1.20x1.0x0.2 meter ect. complete
Providing and fixing of precast parabolic RCC Divederof 0.75x0.60x0.15 meter ect. complete
Providing and fixing of precast parabolic RCC Diveder of 0.45x0.30x0.10 meter ect. Complete
Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface-Proving and laying of hot applied Thermoplastic Compound 2.5 mm thick including Reflectorizing Glass Beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes. complete.
Providing and laying chequered tiles of approved quality of size 30 cm x 30 cm, confirming to corresponding I.S. for flooring in required position laid on a bed of 1:4 cement mortar including cement float, filling joint with cement slurry cleaning curing etc. complete.
Providing sand faced plaster externally in cement mortar using approved screened sand, in all positions including base coat of 15 mm thick in cement mortar 1:4 using waterproofing compound at 1 kg per cement bag curing the same for not less than 2 days and keeping the surface of the base coat rough to receive the sand faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing the surface by taking out grains and curing for fourteen days scaffolding etc. complete.
Supplying and stacking/ spreading of red hill earth( as per specification)
Providing and laying in situ / ready mix M20 controlled cement concrete of trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc. including ramming, vibrating, curing, formwork, centering and finishing in cement plaster excluding reinforcement etc. complete. (height up to 4 meter with fully automatic micro processor based PLC with SCADA enabled reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand)
Providing, cutting, bending, hooking, tying and laying in position TMT FE 500 steel bars for reinforcement for all RCC works as per detailed drawings etc. complete.
Providing and applying priming coat on concrete/masonary/ Asbestos Cement plastered surfaces including scaffolding if necessary, preparing the surface by thoroughly cleaning oil, grease, dirt and other foreign matter and sand papering as required etc. complete.
Providing and applying two coats (exterior quality) of flat oil paint of approved colour and shade to the plastered surface in buildings and workshops including scaffolding if necessary, cleaning the surface and preparing surface etc. complete. (excluding primer coat)
Disposing of excavated material upto 3km
Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum including dressing section to the required grade, camber and side slopes and conveying the excavated materials with all lifts upto a lead of 50m. and spreading for embankment or stacking as directed.
Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm thick including hand packing and compacting etc. complete.
Providing and laying in situ / ready mix cement concrete of M10 proportion with trap/ granite/ quartzite/ gneiss metal in foundation including necessary form work, compacting and curing etc. complete. (with reversible drum type mixer/ concrete batch mix plant (pan mixer)) with SCADA with Natural / VSI standard Artificial Sand)
Providing and fixing heavy duty inter locking concrete Coloured paving blocks of 60 mm thickness of having a strength of 300 kg/Sq.cm. of approved quality and shape on a bed of crushed sand of 25 to 30 mm thick including skirting joints and cleaning etc. complete
Providing PCC Precast factory made kerb stone of 500 x 400 x 150 mm size for in M20 grade of concrete using design mix with minimum cement content as per IS 456 for moderate exposure condition including fixing in pcc1.2.4 250mm thick filling in joint with CM 1.3 pointing in CM on exposed faces etc. complete including painting in two coats of oil paint to exposed surfaces one coat of primer & excavation and disposal of excavated material, making good the road etc. complete.
Providing and casting in situ or precast tapering R.C.C.M-20 Barrier type Kerb without gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C. M-20 Semi Barrier type Kerb without gutter ( as per IRC 86 1983) embedded 125mm below ground level lover M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C M-20 Mountable type Kerb without gutter ( as per IRC86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C.M-20 Barrier type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C.M-20 Semi Barrier type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the (same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete
Batching and Mixing PlantProviding and casting in situ or precast tapering R.C.C. M-20 Mountable type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing sand faced plaster externally in cement mortar using approved screened sand, in all positions including base coat of 15 mm thick in cement mortar 1:4 using waterproofing compound at 1 Kilogramper cement bag curing the same for not less than 2 days and keeping the surface of the base coat rough to receive the sand faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing the surface by taking out grains and curing for fourteen days scaffolding etc.complete
Providing and fixing of precast parabolic RCC Diveder of 1.20x1.0x0.2 meter ect. complete
Providing and fixing of precast parabolic RCC Divederof 0.75x0.60x0.15 meter ect. complete
Providing and fixing of precast parabolic RCC Diveder of 0.45x0.30x0.10 meter ect. Complete
Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface-Proving and laying of hot applied Thermoplastic Compound 2.5 mm thick including Reflectorizing Glass Beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes. complete.
Providing and laying chequered tiles of approved quality of size 30 cm x 30 cm, confirming to corresponding I.S. for flooring in required position laid on a bed of 1:4 cement mortar including cement float, filling joint with cement slurry cleaning curing etc. complete.
Providing sand faced plaster externally in cement mortar using approved screened sand, in all positions including base coat of 15 mm thick in cement mortar 1:4 using waterproofing compound at 1 kg per cement bag curing the same for not less than 2 days and keeping the surface of the base coat rough to receive the sand faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing the surface by taking out grains and curing for fourteen days scaffolding etc. complete.
Supplying and stacking/ spreading of red hill earth( as per specification)
Providing and laying in situ / ready mix M20 controlled cement concrete of trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc. including ramming, vibrating, curing, formwork, centering and finishing in cement plaster excluding reinforcement etc. complete. (height up to 4 meter with fully automatic micro processor based PLC with SCADA enabled reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand)
Providing, cutting, bending, hooking, tying and laying in position TMT FE 500 steel bars for reinforcement for all RCC works as per detailed drawings etc. complete.
Providing and applying priming coat on concrete/masonary/ Asbestos Cement plastered surfaces including scaffolding if necessary, preparing the surface by thoroughly cleaning oil, grease, dirt and other foreign matter and sand papering as required etc. complete.
Providing and applying two coats (exterior quality) of flat oil paint of approved colour and shade to the plastered surface in buildings and workshops including scaffolding if necessary, cleaning the surface and preparing surface etc. complete. (excluding primer coat)
Disposing of excavated material upto 3km
Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum including dressing section to the required grade, camber and side slopes and conveying the excavated materials with all lifts upto a lead of 50m. and spreading for embankment or stacking as directed.
Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm thick including hand packing and compacting etc. complete.
Providing and laying in situ / ready mix cement concrete of M10 proportion with trap/ granite/ quartzite/ gneiss metal in foundation including necessary form work, compacting and curing etc. complete. (with reversible drum type mixer/ concrete batch mix plant (pan mixer)) with SCADA with Natural / VSI standard Artificial Sand)
Providing and fixing heavy duty inter locking concrete Coloured paving blocks of 60 mm thickness of having a strength of 300 kg/Sq.cm. of approved quality and shape on a bed of crushed sand of 25 to 30 mm thick including skirting joints and cleaning etc. complete
Providing PCC Precast factory made kerb stone of 500 x 400 x 150 mm size for in M20 grade of concrete using design mix with minimum cement content as per IS 456 for moderate exposure condition including fixing in pcc1.2.4 250mm thick filling in joint with CM 1.3 pointing in CM on exposed faces etc. complete including painting in two coats of oil paint to exposed surfaces one coat of primer & excavation and disposal of excavated material, making good the road etc. complete.
Providing and casting in situ or precast tapering R.C.C.M-20 Barrier type Kerb without gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C. M-20 Semi Barrier type Kerb without gutter ( as per IRC 86 1983) embedded 125mm below ground level lover M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C M-20 Mountable type Kerb without gutter ( as per IRC86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C.M-20 Barrier type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing and casting in situ or precast tapering R.C.C.M-20 Semi Barrier type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the (same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete
Batching and Mixing PlantProviding and casting in situ or precast tapering R.C.C. M-20 Mountable type Kerb with gutter ( as per IRC 86 1983) embedded 125mm below ground level over M-10 PCC finished neatly with C.M. 1:2, setting the same in C.M. 1:2, including the required excavation in any strata and removing the excavated stuff any where in city and redoing the surface as specified and directed by Engineering In-charge. Using Concrete Batching and Mixing Plant
Providing sand faced plaster externally in cement mortar using approved screened sand, in all positions including base coat of 15 mm thick in cement mortar 1:4 using waterproofing compound at 1 Kilogramper cement bag curing the same for not less than 2 days and keeping the surface of the base coat rough to receive the sand faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing the surface by taking out grains and curing for fourteen days scaffolding etc.complete
Providing and fixing of precast parabolic RCC Diveder of 1.20x1.0x0.2 meter ect. complete
Providing and fixing of precast parabolic RCC Divederof 0.75x0.60x0.15 meter ect. complete
Providing and fixing of precast parabolic RCC Diveder of 0.45x0.30x0.10 meter ect. Complete
Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface-Proving and laying of hot applied Thermoplastic Compound 2.5 mm thick including Reflectorizing Glass Beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes. complete.
Providing and laying chequered tiles of approved quality of size 30 cm x 30 cm, confirming to corresponding I.S. for flooring in required position laid on a bed of 1:4 cement mortar including cement float, filling joint with cement slurry cleaning curing etc. complete.
Providing sand faced plaster externally in cement mortar using approved screened sand, in all positions including base coat of 15 mm thick in cement mortar 1:4 using waterproofing compound at 1 kg per cement bag curing the same for not less than 2 days and keeping the surface of the base coat rough to receive the sand faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing the surface by taking out grains and curing for fourteen days scaffolding etc. complete.
Supplying and stacking/ spreading of red hill earth( as per specification)
Providing and laying in situ / ready mix M20 controlled cement concrete of trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc. including ramming, vibrating, curing, formwork, centering and finishing in cement plaster excluding reinforcement etc. complete. (height up to 4 meter with fully automatic micro processor based PLC with SCADA enabled reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand)
Providing, cutting, bending, hooking, tying and laying in position TMT FE 500 steel bars for reinforcement for all RCC works as per detailed drawings etc. complete.
Providing and applying priming coat on concrete/masonary/ Asbestos Cement plastered surfaces including scaffolding if necessary, preparing the surface by thoroughly cleaning oil, grease, dirt and other foreign matter and sand papering as required etc. complete.
Providing and applying two coats (exterior quality) of flat oil paint of approved colour and shade to the plastered surface in buildings and workshops including scaffolding if necessary, cleaning the surface and preparing surface etc. complete. (excluding primer coat)
Disposing of excavated material upto 3km
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid