| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹45.4 LAccepted-AOC VILL TEHARI PO PARSWAR PS BHANDARIYA DIST GARHWAA JHARAKHAND | ₹45.4 L | L1 | Accepted-AOC Work has been allotted |
| 2 | L2₹49.9 L+₹4.6 L (10.0%)Rejected-Finance | ₹49.9 L+₹4.6 L (10.0%) | L2 | Rejected-Finance Financially Disqualified by Concern Committee |
| 3 | L3₹51.6 L+₹6.2 L (13.6%)Rejected-Finance | ₹51.6 L+₹6.2 L (13.6%) | L3 | Rejected-Finance Financially Disqualified by Concern Committee |
| 4 | L4₹55.3 L+₹10.0 L (22.0%)Rejected-Finance | ₹55.3 L+₹10.0 L (22.0%) | L4 | Rejected-Finance Financially Disqualified by Concern Committee |
| 5 | L5₹55.5 L+₹10.1 L (22.3%)Rejected-Finance | ₹55.5 L+₹10.1 L (22.3%) | L5 | Rejected-Finance Financially Disqualified by Concern Committee |
Tender Value
₹55.5 L
EMD Value
₹1.1 L
Closing Date
9 May 2026, 5:00 pmClosed
DISTRICT ENGINEER,ZILA PARISHAD GARHWA
Old Collecterate, Garhwa
CONSTRUCTION OF HSC AT PARASWAR, PANCHAYAT PARASWAR, BLOCK BARGARAH, DISTRICT GARHWA
2026_gzp_113529_2
ZP/GARHWA/04/2025-26/RE(2nd call)
Open Tender
Civil Works - Buildings
Percentage
180 days
GARHWA
Please refer to the required tender document
2 documents required · 2 mandatory
₹10,000
₹1.1 L
1 Jul 2026
2 May 2026
11 May 2026
2 May 2026
9 May 2026
2 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I. | 47.08 | Cum | 151.82 | ₹7,147.96 |
| 2 | Extra for earthwork in hard soil as per specification and direction of E/I. ( vide classification of soil item-B) | 23.54 | Cum | 15.51 | ₹365.11 |
| 3 | Earth Filling in foundation trenches and Plinth in layers not exceding 150 mm thick well watered, rammed, fully compacted and all complete as per approved design, building specification and direction of E/I. | 50.83 | Cum | 55.28 | ₹2,809.88 |
| 4 | Providing coarse clean sand in filling in in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including cost of all materials labour, royalty and taxes all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 10.54 | Cum | 589.51 | ₹6,213.44 |
| 5 | Providing designation 75B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/I. | 93.02 | Sqm | 330.34 | ₹30,728.23 |
| 6 | Hospital- Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 13.49 | Cum | 3,751.64 | ₹50,609.62 |
| 7 | Foundation- Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) | 14.28 | Cum | 5,218 | ₹74,513.04 |
| 8 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mmnominal size) | 20.32 | Cum | 6,082.45 | ₹1,23,595.38 |
| 9 | First floor Beams- Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). | 42.53 | Cum | 6,308.87 | ₹2,68,316.24 |
| 10 | providing Tor steel reinforcement of 8mm dia rods as per approved design and drawing exclusive carriage of M.S. bars to work site, cutting, bending and binding with annealed wire with cost of the wire, removal of rust, placing the rods in position all complete as per building specification and direction of E/I. TMT Fe 500 (only valid for SAIL & TATA STEEL) | 1.85 | MT | 83,314.02 | ₹1,54,139.27 |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.20 MB
BOQ_153378.xls
BOQ • 0.42 MB
CORRIGENDUM2.pdf
PDF • 0.57 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .