Tender Value
₹51.3 L
EMD Value
₹1.0 L
Closing Date
6 Oct 2026, 4:00 pm
Executive Engieer RnB Division Kulgam
Executive Engieer RnB Division Kulgam
Balance Work for construction of Road from Ziyarath Shareef Baba Dawood Khaki Brinal to Khargund.(NABARD RIDF XXVII )
2026_PWDJK_326165_1
71/2026-27/RnB/Kul/7085-95 Dtd 26-09-2026
Open Tender
Civil Works
Percentage
120 days
Kulgam
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,600
No 0470010200000099
₹1.0 L
26 Sept 2026
26 Sept 2026
7 Oct 2026
26 Sept 2026
6 Oct 2026
26 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Engagment of JCB and tractors for removal of earthen humps , construction material dumping at site by locals, animal waste etc complete job | 10 | Hr | 1,271.19 | ₹12,711.9 |
| 2 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil | 1,201.5 | CUM | 165.56 | ₹1,98,920.34 |
| 3 | Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunk and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material. | - | - | - | - |
| 4 | Beyond 30 cm girth upto and including 60 cm girth. | 20 | NO | 302.29 | ₹6,045.8 |
| 5 | Beyond 60 cm girth upto and including 120 cm girth. | 15 | NO | 1,342.06 | ₹20,130.9 |
| 6 | Providing and laying of Nallah MUCK/RBM including watering dressindg ramming and Consolidation with PRR 8-10 TON Capacity incl carriage of same from approved source upto site of work complete. | 742.5 | Cum | 677.97 | ₹5,03,392.73 |
| 7 | P/L WBM base course with stone aggregate of 63-45mm size, stone screening 13.2 mm size and binding material asper morth specifications i/c screening sorting and spreading to template and consolidation using PRR of 8-10 tonne capacity including all carriages upto the site with compacted thiockness 75mm | 123.19 | Cum | 1,753.39 | ₹2,15,995.73 |
| 8 | Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to 0.075 mm ) to wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant, carriage of mixed material by tipper to site, for all leads & lifts, laying in uniform layers with mechanical paver finisher in sub- base / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge i/c all carriages(in two layers) | 164.25 | Cum | 2,016.4 | ₹3,31,193.7 |
| 10 | Providing and laying 50 mm compacted thick bituminous macadam with bitumen of grade VG-10 @ 3.5% (percentage by weight of total mix) prepared in Drum Type Hot Mix Plant of 60-90 TPH capacity using crushed stone aggregates of specified grading premixed with bituminous binder, transported to site by tippers, laid over a previously prepared surface with paver finisher equipped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers as per specifications to achieve the desired compaction and density, complete as per specifications and directions of Engineer-in-Charge i/c all carriages complete including tack coat complete job. | 82.13 | Cum | 7,451.91 | ₹6,11,988.11 |
| 11 | Providing and laying semi- dense Bituminous concrete of 25 mm compacted thickness with bitumen of grade VG-10 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Drum Type Hot Mix Plant of 60-90 TPH capacity.using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equipped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. | 1,642.5 | Sqm | 227.77 | ₹3,74,112.23 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.06 MB
BOQ_1102820.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .