Loading…
Loading…
Tender Value
₹50.8 L
EMD Value
₹1.0 L
Closing Date
6 Mar 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
SR DEE G
15 conditions · 4 needing a document upload
The tenderer must have minimum average annual contractual turnover of'V/N' or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments'' in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
(a) The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work costing not less than the amount equal to 60% of advertised value of the tender.
Similar work for eligibility: Satisfactory execution of any electrical work related to HT/LT installation.
The Tenderer should have valid Electrical license issued by the appropriate authority otherwise his offer will be summarily rejected.
43 conditions · 9 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Please submit your bank details i.e.Name of the Bank along with Bank BranchCode, IFSC Code, Beneficiary name, Account Number, Type of account, PAN and GSTN Number.
Tender Form: Tender Forms shall embody the contents of the contract documents either directly or by reference and shall be as per specimen form, Annexure-I. e-Tender Forms shall be issued free of cost to all tenderers.
Care in Submission of Tenders: Before submitting a tender, the tenderer will be deemed to have satisfied himself by actual inspection of the site and locality of the works, that all conditions liable to be encountered during the execution of the works are taken into account and that the rates he enters in the tender forms are adequate and all inclusive to accord with the provisions in Clause-37 of the Standard General Conditions of Contract for the completion of works to the entire satisfaction of the Engineer.
Right of Railway to Deal with Tenders: The Railway reserves the right of not to invite tenders for any of Railway work or works or to invite open or limited tenders and when tenders are called to accept a tender in whole or in part or reject any tender or all tenders without assigning reasons for any such action. In case if tender is accepted in part by Railway administration, Letter of Acceptance shall be issued as counter offer to the Tenderer, which shall be subject to acceptance by the Tenderer
Provisions of Make in India Policy 2017 issued by Govt. of India, as amended from time to time, shall be followed for consideration of tenders.
Execution of Contract Document: The Tenderer whose tender is accepted shall be required to appear in person at the office of General Manager/General Manager (Construction), Chief Administrative Officer (Construction), Divisional Railway Manager or concerned Engineer, as the case may be, or if tenderer is a firm or corporation, a duly authorized representative shall appear and execute the contract agreement within seven days of notice from Railways that the Contract Agreement is ready. The Contract Agreement shall be entered into by Railway only after submission of valid Performance Guarantee by the Contractor. Failure to do so shall constitute a breach of the agreement affected by the acceptance of the tender. In such cases the Railway may determine that such tenderer has abandoned the contract and there upon his tender and acceptance thereof shall be treated as cancelled and the Railway shall be entitled to forfeit the full amount of the Earnest Money and other dues payable to the Contractor under this contract. The failed Contractor shall be debarred from participating in the re-tender for that work.
If the tenderer(s) deliberately gives / give wrong information in his / their tender or creates / create circumstances for the acceptance of his / their tender, the Railway reserves the right to reject such tender at any stage.
If any partner(s) of a partnership firm expires after the submission of its tender or after the acceptance of its tender, the Railway shall deem such tender as cancelled/contract as terminated under clause 61 of the Standard General Conditions of Contract, unless the firm retains its character as per partnership agreement. If a sole proprietor expires after the submission of tender or after the acceptance of tender, the Railway shall deem such tender as cancelled / contract as terminated under clause 61 of the Standard General Conditions of Contract.
After opening of the tender, any document pertaining to the constitution of Sole Proprietorship Firm / Partnership Firm / Registered Company/ Registered Trust / Registered Society / HUF etc. shall be neither asked nor considered, if submitted. Further, no suo moto cognizance of any document available in public domain (i.e., on internet etc.) or in Railway's record/office files etc. will be taken for consideration of the tender, if no such mention is available in tender offer submitted.
Employment/Partnership etc. of Retired Railway Employees: ((a) Should a tenderer i) be a retired Engineer of the gazetted rank or any other gazetted officer working before his retirement, whether in the executive or administrative capacity or whether holding a pensionable post or not, in the Engineering or any other department of any of the railways owned and administered by the President of India for the time being, OR ii) being partnership firm / joint venture (JV) / registered society / registered trust etc have as one of its partners/members a retired Engineer of the gazetted rank or any other gazetted officer working before his retirement, OR iii) being an incorporated company have any such retired Engineer of the gazetted rank or any other gazetted officer working before his retirement as one of its directors A N D in case where such Engineer or officer had not retired from government service at least 1 year prior to the date of submission of the tender THEN the tenderer will give full information as to the date of retirement of such Engineer or gazetted officer from the said service and as to whether permission for taking such contract, or if the Contractor be a partnership firm or an incorporated company, to become a partner or director as the case may be, has been obtained by the tenderer or the Engineer or officer, as the case may be from the President of India or any officer, duly authorized by him in this behalf, shall be clearly stated in writing at the time of submitting the tender.
b) In case, upon successful award of contract, should a tenderer depute for execution of the works under or to deal matters related with this contract, any retired Engineer of gazette rank or retired gazetted officer working before his retirement in the Engineering or any other department of any of the railways owned and administered by the President of India for the time being, and now in his employment, then the tenderer will ensure that retired Engineer or retired gazetted officer had retired from government service at least 1 yearprior to the date of his employment with tenderer and in case he had retired from service within a year then he possesses the requisite permission from the President of India or any officer, duly authorized by him in this behalf, to get associated with the tenderer. c) Should a tenderer or Contractor being an individual, have member(s) of his family or in the case of partnership firm/ company / joint venture (JV) / registered society / registered trust etc. one or more of his partner(s)/shareholder(s) or member(s) of the family of partner(s)/shareholder(s) having share of more than 1% in the tendering entity employed in gazetted capacity in the Engineering or any other department of the railway, then the tenderer at the time of submission of tender, will inform the authority inviting tenders the details of such persons. Note:-If information as required as per 16.a), b), c) above has not been furnished, contract is liable to be dealt in accordance with provision of clause 62 of Standard General Condition of contract.
Railway Passes: No free railway passes shall be issued by the Railway to the Contractor or any of his employee/worker
Security Deposit: The Security Deposit shall be 5% of the contract value. The Bid Security submitted by the Contractor with his tender will be retained/encashed by the Railways as part of security for the due and faithful fulfillment of the contract by the Contractor. Provided further that, if Contractor submits the Cash or Term Deposit Receipt issued from a Scheduled commercial bank of India or irrevocable Bank Guarantee Bond from a Scheduled commercial bank of India, either towards the Full Security Depositor the Part Security Deposit equal to or more than Bid Security, the Railway shall return the Bid Security, to the Contractor. Balance of Security Deposit may be deposited by the Contractor in cash or Term Deposit Receipt issued from Scheduled commercial bank of India or irrevocable Bank Guarantee bond issued from Scheduled commercial bank of India, or may be recovered at the rate of 6% of the bill amount till the full Security Deposit is recovered. Provided also that in case of defaulting Contractor, the Railway may retain any amount due for payment to the Contractor on the pending "on account bills" so that the amounts so retained (including amount guaranteed through Performance Guarantee) may not exceed 10% of the total value of the contract. The Irrevocable Bank Guarantee submitted towards Security deposit shall be initially valid up to the stipulated date of Maintenance period plus 60 days and shall be extended from time to time, depending upon extension of contract granted in terms of Clause 17A and 17B of the Standard General Conditions of Contract. Note: Security Deposit deposited in cash by the Contractor or recovered from the running bills of a Contractor or submitted by contractor as Term Deposit Receipt(s) can be refunded/returned to the contractor, in lieu of irrevocable Bank Guarantee bond issued from scheduled commercial bank of India, to be submitted by him, for an amount equal to or more than the already available Security Deposit, provided however that, in a contract of value less than Rs. 50 Crore, such refund/ return of the already available Security Deposit is permitted up to two times and in a contract of value equal to or more than Rs. 50 Crore, such refund / return of the already available Security Deposit is permitted up to three times.
16.(2) (i) Refund of Security Deposit: Security Deposit mentioned in sub clause (1) above shall be returned to the Contractor along with or after, the following: (a) Final Payment of the Contract as per clause 51.(1) and (b) Execution of Final Supplementary Agreement or Certification by Engineer that Railway has No Claim on Contractor and (c) Maintenance Certificate issued, on expiry of the maintenance period as per clause 50.(1), in case applicable. 16. (2) (ii) Forfeiture of Security Deposit: Whenever the contract is rescinded as a whole under clause 62 (1) of these conditions, the Security Deposit already with railways under the contract shall be forfeited. However, in case the contract is rescinded in part or parts under clause 62 (1) of these conditions, the Security Deposit shall not be forfeited. 16.(3) No interest shall be payable upon the Bid Security and Security Deposit or amounts payable to the Contractor under the Contract, but Government Securities deposited in terms of Sub-Clause 16.(4)(b) of this clause will be payable with interest accrued thereon.
Performance Guarantee The procedure for obtaining Performance Guarantee is outlined below: (a) The successful bidder shall have to submit a Performance Guarantee (PG) within 21 (Twenty one) days from the date of issue of Letter of Acceptance (LOA). Extension of time for submission of PG beyond 21 (Twenty one) days and upto 60 days from the date of issue of LOA may be given by the Authority who is competent to sign the contract agreement. However, a penal interest of 12% per annum shall be charged for the delay beyond 21(Twenty one) days, i.e. from 22ndday after the date of issue of LOA. Further, if the 60thday happens to be a declared holiday in the concerned office of the Railway, submission of PG can be accepted on the next working day. In all other cases, if the Contractor fails to submit the requisite PG even after 60 days from the date of issue of LOA, the contract is liable to be terminated. In case contract is terminated railway shall be entitled to forfeit Bid Security and other dues payable to the contractor against that particular contract, subject to maximum of PG amount. In case a tenderer has not submitted Bid Security on the strength of their registration as a Startup recognized by Department of Industrial Policy and Promotion (DIPP) under Ministry of Commerce and Industry, DIPP shall be informed to this effect. The failed Contractor shall be debarred from participating in re-tender for that work.
The successful bidder shall submit the Performance Guarantee (PG) in any of the following forms, amounting to 5% of the original contract value:-(i) A deposit of Cash;(ii) Irrevocable Bank Guarantee;GCC April 2022 49 (iii) Government Securities including State Loan Bonds at 5% below the market value; (iv) Pay Orders and Demand Drafts tendered by any Scheduled Commercial Bank of India;(v) Guarantee Bonds executed or Deposits Receipts tendered by any Scheduled Commercial Bank of India;(vi) Deposit in the Post Office Saving Bank;(vii) Deposit in the National Savings Certificates;(viii) Twelve years National Defence Certificates;(ix) Ten years Defence Deposits; (x) National Defence Bonds and(xi) Unit Trust Certificates at 5% below market value or at the face value whichever is less. Also,FDR in favour of FA&CAO (free from any encumbrance) may be accepted.
(c) The Performance Guarantee shall be submitted by the successful bidder after the Letter of Acceptance (LOA) has been issued, but before signing of the contract agreement. This P.G. shall be initially valid upto the stipulated date of completion plus 60 days beyond that. In case, the time for completion of work gets extended, the Contractor shall get the validity of P.G. extended to cover such extended time for completion of work plus 60 days. (d) The value of PG to be submitted by the Contractor is based on original contract value and shall not change due to subsequent variation(s) in the original contract value(e) The Performance Guarantee (PG) shall be released after physical completion of the work based on 'Completion Certificate' issued by the competent authority stating that the Contractor has completed the work in all respects satisfactorily. (f) Whenever the contract is rescinded, the Performance Guarantee already submitted for the contract shall be encashed. (g) The Engineer shall not make a claim under the Performance Guarantee except for amounts to which the President of India is entitled under the contract (not withstanding and/or without prejudice to any other provisions in the contract agreement) in the event of: (i) Failure by the Contractor to extend the validity of the Performance Guarantee as described herein above, in which event the Engineer may claim the full amount of the Performance Guarantee. (ii) Failure by the Contractor to pay President of India any amount due, either as agreed by the Contractor or determined under any of the Clauses/Conditions of the Agreement, within 30 days of the service of notice to this effect by Engineer. (iii) The Contract being determined or rescinded under clause 62 of these conditions.
Force Majeure Clause: If at any time, during the continuance of this contract, the performance in whole or in part by either party of any obligation under this contract shall be prevented or delayed by reason of any war, hostility, acts of public enemy, civil commotion, sabotage, serious loss or damage by fire, explosions, epidemics/pandemics, strikes, lockouts or acts of God (hereinafter, referred to events) provided, notice of the happening of any such event is given by either party to the other within 30 days from the date of occurrence thereof, neither party shall by reason of such event, be entitled to terminate this contract nor shall either party have any claim for damages against the other in respect of such non-performance or delay in performance, and works under the contract shall be resumed as soon as practicable after such event has come to an end or ceased to exist, and the decision of the Engineer as to whether the works have been so resumed or not shall be final and conclusive, PROVIDED FURTHER that if the performance in whole or in part of any obligation under this contract is prevented or delayed by reason of any such event for a period exceeding 120 days, either party may at its option terminate the contract by giving notice to the other party.
Extension for Delay not due to Railway or Contractor: If in the opinion of the Engineer, the progress of work has any time been delayed by any act or neglect of Railway's employees or by other Contractor employed by the Railway under Sub-Clause (4) of Clause 20 of these Conditions or in executing the work not forming part of the contract but on which Contractor's performance necessarily depends or by reason of proceeding taken or threatened by or dispute with adjoining or to neighbouring owners or public authority arising otherwise through the Contractor's own default etc. or by the delay authorized by the Engineer pending arbitration or in consequences of the Contractor not having received in due time necessary instructions from the Railway for which he shall have specially applied in writing to the Engineer or his authorized representative then upon happening of any such event causing delay, the Contractor shall immediately give notice thereof in writing to the Engineer within 15 days of such happening, but shall nevertheless make constantly his best endeavours to bring down or make good the delay and shall do all that may be reasonably required of him to the satisfaction of the Engineer to proceed with the works. The Contractor may also indicate the period for which the work is likely to be delayed and shall be bound to ask for necessary extension of time
17B Extension of Time with Liquidated Damages (LD) for delay due to Contractor: The time for the execution of the work or part of the works specified in the contract documents shall be deemed to be the essence of the contract and the works must be completed not later than the date(s) as specified in the contract. If the Contractor fails to complete the works within the time as specified in the contract for the reasons other than the reasons specified in Clause 17 and 17A, the Railway may, if satisfied that the works can be completed by the Contractor within reasonable short time thereafter, allow the Contractor for further extension of time (Proforma at Annexure-VII) as the Engineer may decide. On such extension the Railway will be entitled without prejudice to any other right and remedy available on that behalf, to recover from the Contractor as agreed damages and not by way of penalty for each week or part of the week, a sum calculated at the following rates of the contract value of the works. For the purpose of this Clause, the contract value of the works shall be taken as value of work as per contract agreement including any supplementary work order/contract agreement issued. Provided also, that the total amount of liquidated damages under this condition shall not exceed 5% of the contract value or of the total value of the item or groups of items of work for which a separate distinct completion period is specified in the contract. . S.No. Duration of extension of time under Clause 17-B Rate of Liquidated Damages (i) Up to Twenty Five percent of original period of completion including period of extension of time granted under Section 17A(i) As decided by Engineer, between 0.01% to 0.05% of contract value for each week or part of the week (ii) Above Twenty Five percent but upto Fifty percent of original period of completion including period of extension of time granted under Section 17A(i) (ii))0.10 % of contract value for each week or part of the week (iii) Above Fifty percent of original period of completion including period of extension of time granted under Section 17A(i) (iii) 0.30 % of contract value for each week or part of the week
VARIATIONS IN EXTENT OF CONTRACT: 42.(2) (i) Unless otherwise specified in the special conditions of the contract, the accepted variation in quantity of each individual item of the contract would be upto 25% of the quantity originally contracted, except in case of foundation work (in which no variation limit shall apply). However, the rates for the increased quantities shall be as per sub- para (iii) below. (ii) The Contractor shall be bound to carry out the work at the agreed rates and shall not be entitled to any claim of any compensation whatsoever upto the limit of 25% variation in quantity of individual item of works.(iii) In case an increase in quantity of an individual item by more than 25% of the agreement quantity is considered unavoidable, then same shall be executed at following rates a. Quantities operated in excess of 125% but upto 140% of the agreement quantity of the concerned item, shall be paid at 98% of the rate awarded for that item in that particular tender; b. Quantities operated in excess of 140% but upto 150% of the agreement quantity of the concerned item shall be paid at 96% of the rate awarded for that item in that particular tender; c. Variation in quantities of individual items beyond 150% will be avoided and would be permitted only in exceptional unavoidable circumstances and shall be paid at 96% of the rate awarded for that item in that particular tender. d. Variation to quantities of Minor Value Item: The limit for varying quantities for minor value items shall be 100% (as against 25% prescribed for other items). A minor value item for this purpose is defined as an item whose original agreement value is less than 1 % of the total original contract value. d.(i) Quantities operated upto and including 100% of the agreement quantity of t h e concerned minor value item, shall be paid at the rate awarded for that item in that particular tender; d.(ii) Quantities operated in excess of 100% but upto 200% of the agreement quantity of the concerned minor value item, shall be paid at 98% of the rate awarded for that item in that particular tender; d.(iii) Variation in quantities of individual minor value item beyond 200% will be avoided and would be permitted only in exceptional unavoidable circumstances and shall be paid at 96% of the rate awarded for that item in that particular tender. (iv) In case of earthwork items, the variation limit of 25% shall apply to the gross quantity of earthwork items and variation in the quantities of individual classifications of soil shall not be subject to this limit. (v) As far as Standard Schedule of Rates (SSOR) items are concerned, the variation limit of 25% would apply to the value of SSOR schedule(s) as a whole and not on individual SSOR items. However, in case of Non Standard Schedule of Rates (SSOR) items, the limit of 25% would apply on the individual items irrespective of the manner of quoting the rate (single percentage rate or individual item rate).
43.(2) Signing of "No Claim" Certificate : The Contractor shall not be entitled to make any claim whatsoever against the Railway under or by virtue of or arising out of this contract, nor shall the Railway entertain or consider any such claim, if made by the Contractor, after he shall have signed a "No Claim" Certificate in favour of the Railway in such form as shall be required by the Railway after the works are finally measured up. The Contactor shall be debarred from disputing the correctness of the items covered by "No Claim" Certificate or demanding a clearance to arbitration in respect thereof.
46.(1) "On-Account " Payments: The Contractor shall be entitled to be paid from time to time by way of "On-Account" payment only for such works as in the opinion of the Engineer he has executed in terms of the contract. All payments due on the Engineer's/Engineer's Representative's certificates of measurements or Engineer's certified "Contractor's authorized Engineer's measurements" shall be subject to any deductions which may be made under these presents and shall further be subject to, unless otherwise required by Clause 16 of these Conditions, a retention of six percent by way of Security Deposits, until the amount of Security Deposit by way of such retentions shall amount to 5% of the total value of the contract provided always that the Engineer may by any certificate make any correction or modification in any previous certificate which shall have been issued by him and that the Engineer may withhold any certificate, if the works or any part thereof are not being carried out to his satisfaction.
Price Variation Clause (PVC): As per General Condition Contract April 2022 Applicable, and As per Railway Board Letter No.2013/CE-I/CT/0/10/PVC/Pt.1 dt. 27-01-2015 Non-application of Price Variation clause (PVC) to Annual Maintenance Contracts (AMC) and Zonal Contracts.
54. Wages to Labour: The Contractor shall be responsible to ensure compliance with the provision of the Minimum Wages Act, 1948 (hereinafter referred to as the "said Act") and the Rules made thereunder in respect of any employees directly or through petty Contractors or sub-contractors employed by him for the purpose of carrying out this contract. If, in compliance with the terms of the contract, the Contractor supplied any labour to be used wholly or partly under the direct orders and control of the Railways whether in connection with any work being executed by the Contractor or otherwise for the purpose of the Railway such labour shall, for the purpose of this Clause, still be deemed to be persons employed by the Contractor. If any moneys shall, as a result of any claim or application made under the said Act be directed to be paid by the Railway, such money shall be deemed to be moneys payable to the Railway by the Contractor and on failure by the Contractor to repay the Railway any moneys paid by it as aforesaid within seven days after the same shall have been demanded, the Railways shall be entitled to recover the same from Contractor's bills/Security Deposit or any other dues of Contractor with the Government of India. & other labour condition applicable as per General Condition Contract April 2022
Tenderer are advised to refer Indian Railways Standard General Condition Contract w.e.f April -2022 before/After submission of tender according to which contract shall be governed.
Payment condition:- Payment of running bills/ on account p a y m e n t : (i) For supply, installation/ fixing, testing and commissioning of work- (A) 90% payment will be made to contractor against supply, installation, testing and Commissioning of material, inspection certificate, receipted challan, joint note with Sr. DEE (G)Agra or his Representative/ Authorized supervisor, test certificate of manufacturer, report of RITES etc. (b) The number (i.e. maximum/minimum) of on account payment will be decided by the Sr. DEE/G/AGC depending upon the performance of contractor or importance of work. (C) Balance 10% will be released/paid with the final bill after successful completion, testing & commissioning of the complete awarded/ approved varied work. . All Taxes will be deducted from the payment by the Railway as per extent rule.This being a work contract, rates should be inclusive of all tax/surcharge liabilities. Payment will be made through EFT/ECS of work accepted by the Railway.The rates shall remain unchanged throughout the contract period.No octroi is payable. However, a certificate may be issued to the effect that material is for Railway use.
Upgradation of illumination and fan arrangement inside sickline shed at coaching depot Agra Cantt.
T-10-N-2025-26~NCR
T-10-N-2025-26
Open
Works - General
8 Months
Agra, Uttar Pradesh
₹0
₹1.0 L
6 Mar 2026
4 Feb 2026
20 Feb 2026
61 items across 1 schedule
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 50,80,148.42 | ||
| — | 120.00 | — | — | ||
| Supply, Erection, testing and commissioning of wiring for light point/ fan point/ exhaust fan point/ call bell point with 1.5 sq.mm FRLS/HFFR PVC insulated copper conductor single core cable in surface/recessed medium class PVC conduit, with modular switch, modular plate, suitable GI box and earthing the point with 1.5 sq.mm FRLS/HFFR PVC insulated copper conductor single core cable etc. as required. Group A | — | — | — | 1,42,680 | |
| — | 1325.00 | — | — | ||
| Supply, Erection, testing and commissioning of Wiring for circuit/ submain wiring along with earth wire with the following sizes of FRLS/HFFR PVC insulated copper conductor, single core cable in surface/ recessed medium class PVC conduit as required. Size 2 X 6 sq. mm + 1 X 6 sq. mm earth wire & Conduit pipe ceiling rose with box at every 1 meter all acessories should be water proof. | — | — | — | 6,38,650 | |
| — | 900.00 | — | — | ||
| Supply, Erection, testing and commissioning of Wiring for circuit/ submain wiring along with earth wire with the following sizes of FRLS/HFFR PVC insulated copper conductor, single core cable in surface/ recessed medium class PVC conduit as required. Size 2 X 10 sq. mm + 1 X 6 sq. mm earth wire & Conduit pipe ceiling rose with box at every 1 meter all acessories should be water proof. | — | — | — | 5,58,900 | |
| — | 80.00 | — | — | ||
| Supply, Erection, testing and commissioning of following modular switch/ socket modular plate with inner or front plate, box, switch box including connections but excluding modular plate etc. as required. 5/6 amps switch | — | — | — | 9,680 | |
| — | 40.00 | — | — | ||
| Supply, Erection, testing and commissioning of following modular switch/ socket modular plate with inner or front plate, Box & switch box including connections but excluding modular plate etc. as required. 6 pin 15/16 A socket outlet | — | — | — | 8,760 | |
| — | 20.00 | — | — | ||
| Supply, Erection, testing and commissioning of 100 Watt LED Flood Light, powder coated pressure die cast aluminium (System lumen efficacy 120 and <135 lm/Watt). Supplying, Installation, Testing & Commissioning of Flood Light, powder coated pressure die cast aluminium body with built in or separate driver as per the requirement with Driver efficiency >85%, Input voltage: Input voltage: 140-270 Volt AC, frequency 50/60 hz, Operating temp range -5 0C to 50 0C, internal surge protection of 5 KV L,N,E as per IEC 61000-4-5, Driver efficiency >85%,THD < 10% as per IEC 61000-3-2, P. F.0.95, IP-66,IK-10, CRI >70, under voltage and over voltage protection, EMI- EMC as per CISPR-15, lenses for beam angle 30 deg-120deg as per the application and the project requirement, suitable tilt able fitting, life time (LED, Driver & electrical circuitry) of minimum 50000 Burning Hours with 70% of initial Lumen maintained till life ends as per LM80 extrapolation IES TM- 21-11 report, CCT 3000°K / 4000°K / 5700°K /6500°K (As per ANSI Bin), SDCM(Standard Deviation Colour Matching) <5, Maximum power consumption should not more than the specified rating and Fixture shall be of relevant BIS standard complete in all respect i/c external connections with 1.5 sq.mm FRLS/HFFR, PVC insulated copper conductor single core cable and earthing etc. as required with Minimum 5 year OEM warranty. System lumen efficacy 120 and <135 lm/Watt output . LM79 & LM80 Test report and all testing required for LED fixtures as per BIS shall be submitted.. Shape size and CCT shall be as approved by Engineer-in-Charge as per requirement. (Thermal management: heat sink of aluminium housing such that LED junction temperature shall not rise above 90°C). | — | — | — | 49,340 | |
| — | 50.00 | — | — | ||
| Supply, Erection, testing and commissioning of 50 Watt AC LED Flood Light, powder coated pressure die cast aluminium (System lumen efficacy 120 and <135 lm/Watt). Supplying, Installation, Testing & Commissioning of Flood Light, powder coated pressure die cast aluminium body with built in or separate driver as per the requirement with Driver efficiency >85%, Input voltage: Input voltage: 140-270 Volt AC, frequency 50/60 hz, Operating temp range -5 0C to 50 0C, internal surge protection of 5 KV L,N,E as per IEC 61000-4-5, Driver efficiency >85%,THD < 10% as per IEC 61000-3-2, P. F.0.95, IP-66,IK-10, CRI >70, under voltage and over voltage protection, EMI- EMC as per CISPR-15, lenses for beam angle 30 deg-120deg as per the application and the project requirement, suitable tilt able fitting, life time (LED, Driver & electrical circuitry) of minimum 50000 Burning Hours with 70% of initial Lumen maintained till life ends as per LM80 extrapolation IES TM- 21-11 report, CCT 3000°K /4000°K / 5700°K /6500°K (As per ANSI Bin), SDCM(Standard Deviation Colour Matching) <5, Maximum power consumption should not more than the specified rating and Fixture shall be of relevant BIS standard complete in all respect i/c external connections with 1.5 sq.mm FRLS/HFFR, PVC insulated copper conductor single core cable and earthing etc. as required with Minimum 5 year OEM warranty. System lumen efficacy 120 and <135 lm/Watt output . LM79 & LM80 Test report and all testing required for LED fixtures as per BIS shall be submitted.. Shape size and CCT shall be as approved by Engineer-in-Charge as per requirement. (Thermal management: heat sink of aluminium housing such that LED junction temperature shall not rise above 90°C). | — | — | — | 1,00,450 | |
| — | 15.00 | — | — | ||
| Supply, Erection, testing and commissioning of Earthing with G.I. earth pipe 4.5 Meter long, 40 mm dia including accessories, and providing masonry enclosure with cover plate having locking arrangement and watering pipe etc. with charcoal/ coke and salt as required. | — | — | — | 1,14,870 | |
| — | 10.00 | — | — | ||
| Supply, Erection, testing and commissioning of 20 A, 240 V, SPN Industrial type socket outlet, modular with 2 pole and earth, metal enclosed plug top along with modular 20 A "C" curve, SP, MCB, in sheet steel enclosure, on surface or in recess, with chained metal cover for the socket out let and complete with connections, testing and commissioning etc. as required and conforming to CPWD General Specifications for Electrical Works CPWD DSR (E&M) 2025 Item No. 2.18 | — | — | — | 18,060 | |
| — | 12.00 | — | — | ||
| Supply, Erection, testing and commissioning of 250W. LED Flood Light, powder coated pressure die cast aluminium (System lumen efficacy >135 lm/Watt) Supplying, Installation, Testing & Commissioning of Flood Light, powder coated pressure die cast aluminium body with built in or separate driver as per the requirement with Driver efficiency >85%, Input voltage: Input voltage: 140-270 Volt AC, frequency 50/60 hz, Operating temp range -5 0C to 50 0C, internal surge protection of 5 KV L,N,E as per IEC 61000-4-5, Driver efficiency >85%,THD < 10% as per IEC 61000- 3-2, P. F.0.95, IP-66,IK-10, CRI >70, under voltage and over voltage protection, EMI-EMC as per CISPR-15, lenses for beam angle 30 deg-120deg as per the application and the project requirement., suitable tilt able fitting, life time (LED, Driver & electrical circuitry) of minimum 50000 Burning Hours with 70% of initial Lumen maintained till life ends as per LM80 extrapolation IES TM-21-11 report, CCT 3000°K /4000°K / 5700°K /6500°K (As per ANSI Bin) ,SDCM(Standard Deviation Colour Matching) <5, Maximum power consumption should not more than the specified rating and Fixture shall be of relevant BIS standard complete in all respect i/c external connections with 1.5 sq.mm FRLS/HFFR, PVC insulated copper conductor single core cable and earthing etc. as required with Minimum 5 year OEM warranty. System lumen efficacy >135 lm/Watt output. LM79 & LM80 Test report and all testing required for LED fixtures as per BIS shall be submitted. Shape size and CCT shall be as approved by Engineer-in-Charge as per requirement. (Thermal management: heat sink of aluminium housing such that LED junction temperature shall not rise above 90°C). | — | — | — | 74,748 | |
| — | 2.00 | — | — | ||
| Supply, fixing, testing and commissioning of wall mounted LT distribution board made up of steel sheet, phosphatized powder painted complete with neutral link, earth point, Din rail and prewired confirming to IS:13032& 8623:1991 with following itemsof matching make to be fixed indistribution board, confirming toIS:8828 :1996 or latest, IE rulesand site requirement. TPN MCB63 Amps. 10 kA 'C' series= 01No. (Incoming) SP MCB 6-32Amps. 10 kA 'C' series = 18 Nos.(Outgoing) | — | — | — | 9,350.32 | |
| — | 15.00 | — | — | ||
| Supply, fixing, testing & commissioning of MCB DB single phase with RCBO, m.s. enclosure, I/C -DP RCBO of 40Amp - 1No, O/G: SP MCB of 6A - 32A - 8Nos, as per specifications. 30 mA | — | — | — | 57,750 | |
| — | 20.00 | — | — | ||
| Supplying, testing & commissioning of heavyduty bracket type 750 mmsweep air circulator fansingle phase RPM 2800three blades suitable for230 V 50 Hz without regulator AC supply havingair replacement 370 cm perminutes. The propellershould be cast aluminiumYellow &conforming to IS:2997/64 with amendment 1to 5 air- circulating fanshould be wall mounting.The air circulating fan willbe mounted/fixed on MSpillar (in shed) with MS flats50x6 mm size clamps bolts&nuts complete in allrespect. | — | — | — | 98,642 | |
| — | 1.00 | — | — | ||
| Supply, erection, testing andcommissioning of 3 phaseoutdoor & double door type LTdistribution panel comprising2 nos. 400 Amps FP MCCB asincoming with 1 no. 400 Ampsautomatic transfer switch(with auto, manual andbypass arrangements) and 6nos. 125 Amps FP MCCB, 4nos. 63 Amps FP MCCB, 04nos. 32 Amps DP MCB and 4nos. 16 Amps DP MCB asoutgoing with 4 nos. copperbus-bars of size 50 x 5 mm,RYB indicator, digitalmultifunctioning Energy meter(KWH, Volt, Amp), selectorswitches, indicator lamps(LED type) with cable alleychamber and other associatedaccessories complete withcable termination by cablegland, lug, nut bolt etc. Allinternal wiring in the panelsshall be carried out usingFRLSH wires. The MCCB shallbe adjustable type having ground fault module with (Ics= 100% Icu) and breakingcapacity of MCCBs shall be 50KA for 400 A & 250 A MCCBs,35 KA for 125 A & 63 A MCCBand 10 KA for MCB. Theenclosure of LT panel shall befabricated of 12 SWG CRCAsheet, weatherproof powdercoated type with otheraccessories. The panel boardshall be wall mounted / CCflooring with MS stand madeof MS angle of size 50 mm x50 mm x 6 mm and skeletontype angle structures withholes for cable entry & exit asper site condition. The anglestructure of panel should becovered with M.S. Sheet andduly painted. The panel boardshall be properly earthed asper IS. The successfultenderer shall be required tosubmit circuit diagram andblock diagram for the panelboard and start fabricationafter approval of the same bySr.DEE (G)'s office. The LTpanel shall be designedmanufactured and all typetested in accordance with thelatest relevant IEC (viz. IEC61439 1-6, 60947-2, 60898-12002 or latest) standards. Thecontractor shall submitoriginal test report from CPRI/ ERDA / Any other equivalentGovt. Testing Agencies. | — | — | — | 2,87,981.68 | |
| — | 40.00 | — | — | ||
| Supply,Erection,,Testing andCommissioning of MCB SP-6A to 32A for individual octagonal pole for operating street light | — | — | — | 7,060 | |
| — | 40.00 | — | — | ||
| Supply, Erection, Testing and commissioning of 300 W LED Highbay light in fixturecomplete withnecessary mounting accessories, clamps and hardware etc as per specification. | — | — | — | 8,42,268.8 | |
| — | 1500.00 | — | — | ||
| Excavation of cable trench:-This item shall be operated in conformity with IS:1255(latest version) i.e. code of practice for installation and maintenance of HT/LT cables.The price shall cover cost of excavation of cable trench inall type of soil for laying LTcables and back filling thesame with sieved earth and finishing the surface in its original condition after providing sand, & bricks in cross position. For LT/HTcables the trench shall be 600mm wide x 1000mmdeep. In trench the cable shall be covered with riversand at a depth of 100mm below the cable and 100mm above the cable than placing well-burned bricks continuously in cross position through out the cable route inthe ground. The bottom ofthe trench should level freefrom stones and sharp edgeof rocks etc. At the termination a loop of 5 meter(approx) cable shall be keptas allowance and loops ringsbe formed as per the site condition, in the ground, The cost shall include the cost ofall materials i.e. sand, bricks,cable route markers (groutedin the earth firmly with cement concrete so that itcan not be uprooted by miscreants) etc at 25m.interval and each turn of the cable. | — | — | — | 89,295 | |
| — | 1800.00 | — | — | ||
| Laying/Cleating erection,Testing & Commissioning of HT/LT Cable 03/04 Core on wall with all accessories & refilling of cable trench (asper IE rule) after laying of cable (Cable will be suppliedby Rly free of cost at Cosignee Depot) | — | — | — | 60,912 | |
| — | 150.00 | — | — | ||
| Excavation of Cable trench1000mm deep and back filling in all type of soil under the track/roadfor laying of the cable including thework of supply and placeing of RCChume pipe 150m dia with necessary RCC collars etc fordrawing the cable in trench underthe track/road | — | — | — | 17,400 | |
| — | 80.00 | — | — | ||
| Horizontal boring of cableduct at 1.4 to 2.1 mtr.depth from the bottom of sleeper/ground lable and laying of120 mm dia HDPE DWC pipesfor cable crossing under track/ road .The work shall bedone as per extant practiceand instruction of site engineer.It includes supply of DWC/HDPE pipes conforming to IS14930(Part:2:2001) | — | — | — | 1,10,200.8 | |
| — | 40.00 | — | — | ||
| supply, erection, Testing & Commissioning of energy efficient LED street light fitting 60 Watt outdoor complete street light fitting pressure die cast aluminium (PDC) body with make embosed on PDC body and complete with all accessories/ components and connection with PVC copper wire 2.5sq.mm size multicore and fixing arrangement as persite requirement.The technical parameters will generally conform to relevant Railway specification attached Annexure-II | — | — | — | 1,67,704.4 | |
| — | 20.00 | — | — | ||
| Supply, Erection, Testing and commissioning of hot dip galvanized octagonal pole 5 Mtr. long confirming to IS 2629/BSEN ISO 1461 or equivalent including casting, muffing with cement concrete foundation (1:2:4) painting, earthing etc. the pole shall be complete with holes, Anchor bolts, bottom plate etc. As per Tech. Specification/site requirement, IS/IE rules of Double Arm type with 1.5 feet to 2 feet long type | — | — | — | 1,27,601.2 | |
| — | 20.00 | — | — | ||
| Supply, Erection, testing and commissioning of 10W Dragon Light for night ranger Hand Held Search Light , Type - LED 10 Watt IP 65 , Dia of search light (mm) 101 to 125 | — | — | — | 37,000 | |
| — | 100.00 | — | — | ||
| Supply, erection, testing and commissioning of 30W. Led Luminaire Light LED Luminaire IP-65 s per IS 10322, IS 16107, IS 16108, IS 16103, IS 10322 (Q3) | — | — | — | 1,97,900 | |
| — | 70.00 | — | — | ||
| Supply, Erection, Testing and commissioning of Rechargeble tubelight 20W. ASCORAJ Copper Led batten with battery/ Invertor (Q3), Power 20 Watt | — | — | — | 69,160 | |
| — | 14.00 | — | — | ||
| Supply, Installation, Testing and commissining of out door type 415 Volts pre-cooling cum 110 V battery charging box as per IS:8623/ Part I to III / 1993 (Latest Version). | — | — | — | 3,85,230.72 | |
| — | Breakup | for details. | — | ||
| Supply and Erection of Supply and erection of Under gear examination luminaire with hAvey duty IP67,IK 09 Operating Temperature -20 C To 50 C , Life50000 hrs, 110 V LED lamps 30 W with lamps complete work on AC/DC and the same shall be fitted with proper/hard pvc clamp for mounting of fitting thickness 10mm, width 25mm, length as per sample /flats, screws etc. Power suply Connection make from Juncrtion box 4 sqmm copper wire which iscovered by Flexible pipe. Fitting should be robust, water proof shock proof, rust free, corrosion free, acid and chemical resistant, fire retardant made ofhalogen and silica free recyclable low toxicity material , Fiitting will be approved by cosignee before supply make-jaquar, Luzion, Goldwyn, or equivalent, | — | — | — | 5,19,469.5 | |
| — | 50.00 | — | — | ||
| Supply, Installation, Testing and Commissioning of ceiling fan with Brush Less Direct Current (BLDC) Motor, class of insulation: B, 3 nos. metal(Aluminium alloy) blades, 30 cm long down rod, 2 nos. canopies, shackle kit, safety rope, copper winding, steel/Al body. Power Factor not less than 0.9, Service Value (CM/M/W) minimum as below, 350 RPM (tolerance as per IS : 374-2019), THD (Total Harmonic Distortion) less than 10%, remote (preferably mobile app based) for speed control and all remaining accessories including safety pin, nut bolts, washers, temperature rise=75 0C (max.), insulation resistance more than 2 mega ohm, suitable for 230 V, 50 Hz, single phase AC supply Ceiling Fan compliant to IS 374:2019 fan i/c external connections with 1.5 sq.mm FRLS/HFFR, PVC insulated copper conductor single core cable and earthing etc. as required. (1400mm, service value 6.0 CM/Min/Watt, air delivery 245 CM/Min (Minimum)) | — | — | — | 1,45,650 | |
| — | 45.00 | — | — | ||
| Supply, Erection, testing and commissioning of outdoor end termination with cast resin compound including aluminium lugs and other jointing materials for following size of PVC insulated and PVC sheathed / XLPE aluminium conductor cable of 1.1 KV grade as required. (4X 25 Sqmm) | — | — | — | 71,190 | |
| — | 28.00 | — | — | ||
| Supplying, Erection, Testing and commissioning of end termination of LT cable 4 Core X 120 Sqmm | — | — | — | 62,244 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .