Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹21.7 CrAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹21.7 Cr+₹2.9 L (0.13%)Admitted-Finance E 108 LGF GREATER KAILASH ENCLAVE I GREATER KAILASH ENCLAVE PART 1 NEW DELHI SOUTH DELHI DELHI 110048 | SOUTH DELHI | DELHI | 110048 | L2 | Admitted-Finance | ||
| 3 | Not Admitted-Fee/PreQual/Technical Z 79 SHYAM ENCLAVE GOPAL NAGAR EXTN NAJAFGARH NEW DELHI 110043 DELHI INDIA | NEW DELHI | SOUTH WEST DELHI | DELHI | 110043 | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹26.5 Cr
EMD Value
₹36.5 L
Closing Date
21 Mar 2023, 4:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Er. Rajesh Kumar Tanwar
OFFICE OF THE EXECUTIVE ENGINEER SPECIAL PROJECT CIVIL ENGINEERING DEPARTMENT NEW DELHI MUNICIPAL COUNCIL 3rd FLOOR, PRAGATI BHAWAN, JAI SINGH ROAD, NEW DELHI - 110001
Conservation and restoration of main Gole Market building as a museum and redevelopment of surrounding area including construction of Service Block and Subway(Composite Work) .
2023_NDMC_237072_1
02/EE (Special Project)/AB/2022-23
Open Tender
Composite Works
Percentage
730 days
Gole Market
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹36.5 L
PALIKA KENDRA, NEW DELHI
19 Apr 2023
23 Feb 2023
21 Mar 2023
23 Feb 2023
21 Mar 2023
23 Feb 2023
6 Mar 2023
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | CIVIL WORK Phase 1 Restoration Work Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge. The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding.
Note: - This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done. | 2,106.28 | Square Metre | 303.04 | ₹6,38,287.09 |
| 2 | Providing, Erecting double scaffolding using bamboo male of 1" to 11/2" dia. Vertical and horizontal at 1.2 mtr and necessary cross bamboos and short bamboos for supports from building and providing and fixing planks by taking necessary holes in wall and remaking good the damages after completion of work, including coir and all necessary material including conveying loading unloading including removing the same after completion of work by taking necessary precautions and safety measures of labour etc., (irrespective of duration of the scaffold, the item will be paid only once) | 903 | Square Metre | 139.06 | ₹1,25,571.18 |
| 3 | Providing and erecting internal scaffolding up to ceiling soffit using two legged metal tubular arrangement and any steel framework required as described in detailed drawings in rows spaced at a distance not exceeding 2.5 Metre, including suitable cross and horizontal bracing in both planes to make the entire scaffolding erected over the floor as self supporting ,space frame arrangement without anchorage from the building components. The rate includes for providing planks below base plates of tubular scaffolding pipes. Minimum of one third of the quantity of the total measured area in elevation shall be deployed at site.Where scaffolding is taken over upper floors or terrace these shall be adequately shored and supported from below. The rate to also include all cross bracings, vertical and horizontal steel props, acro and all necessary jacking and pipes and should have rubber pads at the base as to safeguard the flooring from being damaged. Item to include providing full plaftorm/ boarding in 19 mm ply or MS Sheets to cover the entire area of the verandah areas where the scaffolding is erected. the item to also include covering the platform completely with high density plastic sheet with necessary fixing wherever required. The plaftorm should be properly anchored to the tubular sections and well supported that personnel can easily work on the platform without any nuisance and entire area to be covered such that no material falls on the floor. Access routes to be made for entry and exit to the various courtrooms on each floor and for passage of people below to use the corridor with minimum 1800 mm clear safe walkway below for pedestrian. The measurements will be calculated by multiplying the lengths of the two legged units at the centre line of the 1200-1500mm scaffold unit widths x heights of the individual rows. The rates will include for the cross bracings between the rows of the scaffold units and plaftorms to be laid horizontally | 1,878.15 | Square Metre | 314.04 | ₹5,89,814.23 |
| 4 | Providing and erecting for strengthening the distressed structure by using steel adjustable props of required length with connecting pipes and couplers with wooden load distributors at top and bottom etc., complete. | 668.76 | Square Metre | 607.96 | ₹4,06,579.33 |
| 5 | Providing and fixing mechanical jacks with hydraulic mechanism of appropriate pressure in required length to reach specified height and lift the distressed load bearing wooden members like trusses, beams, supports etc. for consolidation including strutting , propping, flitching to bring the distressed member in line to show zero deflection and in line and level etc. complete, all as specified by the Consultants and the Architect and as approved by the Engineer in charge. | 72 | Per One Number | 22,144.76 | ₹15,94,422.72 |
| 6 | Providing and laying high density plastic sheet on the roof and other areas for monsoon protection and over temporary plaforms during roof restoration works. Item to include nails, nylon rope etc, required to fix the plastic sheet to the required areas. The plastic sheet to be of the best and approved quality available in market and as approved by the Engineer incharge. | 903 | Square Metre | 224.42 | ₹2,02,651.26 |
| 7 | Careful Packing of sculpture details/ decorative grill work/ delicate tracery and statuary in bubble wrap plastic sheeting with masking tape and duck tape to ensure absolutely no damage to the details during the site works | 25 | Square Metre | 260.34 | ₹6,508.5 |
| 8 | Providing and erecting a temporary vertical partitions using 6 mm thick commercial plywood of approved quality and make and with adequate supporting framework to make it largely free standing to provide protection from other works in progress. The partitions shall be such that they can be removed and reused at different locations without damaging the property. Item to include printed duck tape with safety signage and words “Site Works in Progress” and “Caution” printed to cordon off areas of work. Adequate site signage in bold printed signs should be placed as per Architect’s instructions for safety instructions. | 50 | Square Metre | 1,455.02 | ₹72,751 |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form for all heights : Foundations, footings, bases of columns, etc. for mass concrete | 986.56 | Square Metre | 327.44 | ₹3,23,039.21 |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls
Above 20 cm wide | 364.94 | Square Metre | 820.97 | ₹2,99,604.79 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.47 MB
Tendernotice_2.pdf
PDF • 2.46 MB
BOQ_308874.xls
BOQ • 1.56 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .