| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.3 CrAccepted-AOC 1095 ELDECO 2 UPHAAR SECTOR 3 RAIBAREILLY ROAD LUCKNOW UP PIN 226002 | LUCKNOW | LUCKNOW | UTTAR PRADESH | 226002 | ₹18.3 Cr | L1 | Accepted-AOC Being L1 |
| 2 | L2₹18.8 Cr+₹51.7 L (2.83%)Rejected-Finance | ₹18.8 Cr+₹51.7 L (2.83%) | L2 | Rejected-Finance Being other than L1 |
| 3 | L3₹19.7 Cr+₹1.4 Cr (7.65%)Rejected-Finance 193 1 CIVIL LINES BAREILLY 243001 | BAREILLY | UTTAR PRADESH | 243001 | ₹19.7 Cr+₹1.4 Cr (7.65%) | L3 | Rejected-Finance Being other than L1 |
| 4 | L4₹21.2 Cr+₹3.0 Cr (16.2%)Rejected-Finance | ₹21.2 Cr+₹3.0 Cr (16.2%) | L4 | Rejected-Finance Being other than L1 |
| 5 | L5₹22.2 Cr+₹4.0 Cr (21.8%)Rejected-Finance | ₹22.2 Cr+₹4.0 Cr (21.8%) | L5 | Rejected-Finance Being other than L1 |
| Sl No | Description | Qty | Unit | PAHELWAN TRADERS L1 | LUMOS INFRA PVT LTD L2 | Sudhir Sharma Associates L3 | D.M.BROTHERS L4 | M/s Matadeen Ramchandra Agarwal L5 | AMIT ASSOCIATES L6 |
|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Sch 'A' Part-I (Building Work)
Note : This schedule is pre-priced by MES and the pre-priced rate indicated are under Col. 5. | 1 | Lump Sum | 15,16,28,485 ₹15,16,28,485 | 14,91,57,000 ₹14,91,57,000 Lowest | 16,70,00,000 ₹16,70,00,000 | 16,37,66,115 ₹16,37,66,115 | 18,00,00,000 ₹18,00,00,000 | 17,95,60,000 ₹17,95,60,000 |
| 2.00 | Total amount of Sch 'A' Part II (Site clearance, excavation and earth work) | 1 | Lump Sum | 9,42,003 ₹9,42,003 | 9,00,000 ₹9,00,000 Lowest | 12,00,592.07 ₹12,00,592.07 | 15,16,500 ₹15,16,500 | 10,60,000 ₹10,60,000 | 16,32,000 ₹16,32,000 |
| 3.00 | Total amount of Sch 'A' Part III (Internal Water Supply ) | 1 | Lump Sum | 11,14,466.15 ₹11,14,466.15 | 9,00,000 ₹9,00,000 Lowest | 9,69,101.76 ₹9,69,101.76 | 16,21,500 ₹16,21,500 | 9,32,000 ₹9,32,000 | 9,69,101.76 ₹9,69,101.76 |
| 4.00 | Total amount of Sch 'A' Part IV (Internal Electrification) | 1 | Lump Sum | 19,63,678.5 ₹19,63,678.5 Lowest | 26,10,000 ₹26,10,000 | 26,49,408.23 ₹26,49,408.23 | 24,88,000 ₹24,88,000 | 26,35,000 ₹26,35,000 | 28,35,800 ₹28,35,800 |
| 5.00 | Total amount of Sch 'A' Part V (Road, Path, Culvert & Hard Standing) | 1 | Lump Sum | 20,16,884.61 ₹20,16,884.61 Lowest | 27,00,000 ₹27,00,000 | 27,62,855.63 ₹27,62,855.63 | 33,82,000 ₹33,82,000 | 27,00,000 ₹27,00,000 | 28,55,000 ₹28,55,000 |
| 6.00 | Total amount of Sch 'A' Part VI (Area Drainage) | 1 | Lump Sum | 6,65,338.53 ₹6,65,338.53 Lowest | 8,19,000 ₹8,19,000 | 8,87,118.04 ₹8,87,118.04 | 9,43,000 ₹9,43,000 | 7,95,000 ₹7,95,000 | 8,50,000 ₹8,50,000 |
| 7.00 | Total amount of Sch 'A' Part VII (Sewage Disposal) | 1 | Lump Sum | 1,92,951.21 ₹1,92,951.21 Lowest | 2,07,000 ₹2,07,000 | 1,99,605.52 ₹1,99,605.52 | 2,23,500 ₹2,23,500 | 2,16,000 ₹2,16,000 | 2,50,000 ₹2,50,000 |
| 8.00 | Total amount of Sch 'A' Part VIII (External Water Supply ) | 1 | Lump Sum | 8,70,914.39 ₹8,70,914.39 | 7,38,000 ₹7,38,000 Lowest | 9,50,088.5 ₹9,50,088.5 | 13,56,000 ₹13,56,000 | 7,70,000 ₹7,70,000 | 8,05,000 ₹8,05,000 |
| 9.00 | Total amount of Sch 'A' Part IX (External Electrification and DG set) | 1 | Lump Sum | 12,78,936.66 ₹12,78,936.66 Lowest | 17,01,000 ₹17,01,000 | 20,99,746.78 ₹20,99,746.78 | 23,95,000 ₹23,95,000 | 18,70,000 ₹18,70,000 | 20,35,000 ₹20,35,000 |
| 10.00 | Total amount of Sch 'A' Part X (Refrigerator & Water Cooler) | 1 | Lump Sum | 3,74,354.04 ₹3,74,354.04 Lowest | 4,50,000 ₹4,50,000 | 4,11,378.07 ₹4,11,378.07 | 4,20,000 ₹4,20,000 | 4,56,000 ₹4,56,000 | 4,38,000 ₹4,38,000 |
Tender Value
₹17.1 Cr
EMD Value
₹11.8 L
Closing Date
9 Apr 2026, 6:00 pmClosed
Cheif Engineer Lucknow Zone
Headquarters Chief Engineers Lucknow Zone, Lucknow-226002
PROVISION OF SINGLE MEN BARRACK INCLUDING COOK HOUSE AND DINING HALL FOR RECRUITS AT LUCKNOW
2026_MES_747733_2
CELZ/LKO/T-10 OF 2025-26
Open Tender
Civil Works
Lump-sum
540 days
Lucknow
AS per NIT
8 documents required · 8 mandatory
₹3,000
GE(P) Lucknow
₹11.8 L
29 May 2026
14 Mar 2026
15 Apr 2026
14 Mar 2026
9 Apr 2026
4 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Sch 'A' Part-I (Building Work)
Note : This schedule is pre-priced by MES and the pre-priced rate indicated are under Col. 5. | 1 | Lump Sum | 14,57,44,836 | ₹14,57,44,836 |
| 2 | Total amount of Sch 'A' Part II (Site clearance, excavation and earth work) | 1 | Lump Sum | 14,57,935.91 | ₹14,57,935.91 |
| 3 | Total amount of Sch 'A' Part III (Internal Water Supply ) | 1 | Lump Sum | 9,32,045.16 | ₹9,32,045.16 |
| 4 | Total amount of Sch 'A' Part IV (Internal Electrification) | 1 | Lump Sum | 25,29,022.36 | ₹25,29,022.36 |
| 5 | Total amount of Sch 'A' Part V (Road, Path, Culvert & Hard Standing) | 1 | Lump Sum | 3,77,426.3 | ₹3,77,426.3 |
| 6 | Total amount of Sch 'A' Part VI (Area Drainage) | 1 | Lump Sum | 8,87,118.04 | ₹8,87,118.04 |
| 7 | Total amount of Sch 'A' Part VII (Sewage Disposal) | 1 | Lump Sum | 2,21,783.91 | ₹2,21,783.91 |
| 8 | Total amount of Sch 'A' Part VIII (External Water Supply ) | 1 | Lump Sum | 1,70,030.96 | ₹1,70,030.96 |
| 9 | Total amount of Sch 'A' Part IX (External Electrification and DG set) | 1 | Lump Sum | 17,07,466.9 | ₹17,07,466.9 |
| 10 | Total amount of Sch 'A' Part X (Refrigerator & Water Cooler) | 1 | Lump Sum | 4,11,378.07 | ₹4,11,378.07 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.46 MB
Tender.pdf
Tender Documents • 2.15 MB
BR_5.rar
Additional Documents • 1.22 MB
BOQ_847258.xls
BOQ • 2.15 MB
BR_1.rar
Additional Documents • 2.82 MB
BR_2.rar
Additional Documents • 2.62 MB
BR_3.rar
Additional Documents • 2.38 MB
BR_4.rar
Additional Documents • 1.70 MB
Revdrg_1.rar
PDF • 13.48 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .