Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹91.9 LAdmitted-Finance | +0.00% | ₹91.9 L | L1 | Admitted-Finance |
| 2 | L1₹91.9 LAdmitted-Finance | +0.00% | ₹91.9 L | L1 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | - | Rejected-Technical Technically not qualified |
| 4 | Rejected-Technical AT GARAM P O GARAM P S TIRTOL JAGATSINGHPUR | - | - | - | Rejected-Technical Technically not qualified |
Tender Value
₹91.9 L
EMD Value
₹91,900
Closing Date
2 May 2026, 5:00 pmClosed
Executive Engineer (Central Tender Cell)
Central Tender Cell, BMC, ICOMC Tower, Pin-751022
Construction of Shed for Non-Veg Vending Zone at Tarini Market, Bharatpur in Ward No. 22
2026_ORULB_128186_1
BMC-EE-Tender Cell-04/2026-27 dt. 15.04.2026
Open Tender
Civil Works - Others
120 days
BMC AREA
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹91,900
Yes
UG Floor,Office Chamber of EE Central Tender Cell
12 Jun 2026
17 Apr 2026
4 May 2026
17 Apr 2026
2 May 2026
17 Apr 2026
17 Apr 2026 - 27 Apr 2026
27 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
Earthwork by using hydraulic excavator of 1 cum bucket and depositing the excavated materials within 5 km lead including loading and unloading with all cost conveyance T&P sundries etc. complete as per direction of Engineer in-Charge | - | cum | 209.95 | - | |
Providing and laying plain cement concrete of proportion (1:3:6) in foundation and floors using cement, 4 cm. size black hard crasher broken granite stone metal, screened and washed sharp sand for mortar of approved quality from approved quarry including hosting, lowering, laying concrete, ramming, watering and curing etc. complete to required levels laid in layers not exceeding 15 cm. thick in each layer including cost, conveyance, loading, unloading, dewatering, royalties and taxes all materials and cost all labours, sundries, T&P required for the work including shuttering, hire & running charges of concrete mover complete as per the direction of the Engineer -in charge. | - | cum | 5,196.54 | - | |
Providing, lifting, hoisting and laying Reinforced Cement Concrete of M-25 grade in Column base, Column Footings, Raft Foundation, Stem of the Columns, beams, chaulja, fin, lintel, stair case, jali, shelves and slab etc as per approved designs and drawings having a minimum compressive strength (in work test) 20N./Square mm. in 15 cm. cubes at 28 days after moong and test conducted in accordance with 1.5. 456 and 1.5. 516 using screened & washed sharp river sand for mortar and 10 mm. to 20 mm, size ators, watering and caning for 28 days induding, centering and shuttering then after dismantling and removing the debrises away from the work site and finishing the exposed surface smooth providing grooves or beads wherever necessary induding cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labours, scaffolding, sundries, T&P required for the work etc. complete in all respect but the excluding cost & conveyance of M.5. rods or Tor Steel and Binding wires and labour charges for straightening, cutting, bending etc. of M.5. rods or Tor steel and binding wires and tying the grills and placing in propor position as directed by the Engineer-in-charge.
Truss Foundation | 33.79 | cum | 7,008.45 | ₹2,36,829.54 | |
Truss Plinth Beam | - | cum | 7,880.36 | - | |
Truss Column | - | cum | 18,527.53 | - | |
Truss Roof Beam | 34.42 | cum | 18,527.53 | ₹6,37,643.47 | |
Cutting, Straightening coiled or bent up M.S plain HYSD/TMT reinforcement bars welding or jointing if necessary bending, biriding, tying the grills as required for R.C.C works, providing fan hooks where necessary and hoisting, lowering and placing in proper position according to approved designs and drawings including cost, conveyance, loading, unloading & taxes of M.S plain/HYSD/TMT reinforcement bars and binding wires of 18 to 20 gaugo required for the work and cost of all labour, sundries, TSP and scaffolding complete in all respect as directed by the Engineer in charge (payment will be made according to the actual weight of M.S plain/HYSD/TMT reinforcement bars consumed in the work only. | - | qntl | 8,718.45 | - | |
Providing 12mm thick cement plaster in cement mortar (1:6) in all floors finished smooth to out side smooth surface of brick wallt after racking out joints, scrapping & deaning the surface & finishing the plaster surface smooth using wooden float only to proper plumbs & level and making necessary grooves, beads & drip course to give required ornamental finish as per drawing, watering, curing, scaffolding, screening sand etc. complete with cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P, sundries required for the work etc. complete as per specification & direction of Engineer-in-charge. | 578.3 | sqm | 186.87 | ₹1,08,066.92 | |
Painting two coats with weather seal coat over a coat of water bound wall primer of approved make & shade manufactured by reputed manufacturer like NEROLAC/ASIAN/ BERGER/DULOX or equivalent as required for the work complete. | 578.3 | sqm | 182.85 | ₹1,05,742.15 | |
Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | - | kg | 152.75 | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.89 MB
BOQ_587989.xls
BOQ • 0.25 MB
DTCN.pdf
Tender Documents • 0.94 MB
Download all tender documents and submit your bid