Laying and Jointing of RCC UGPL Works, Fixing of ARV, AAV, GV, Construction of Haudies and all other allied works.
2026_DOA_172044_4
DSWC/SAN/2026-27/12
Open Tender
Pipe Laying Works
Percentage
180 days
Sangrur
Please refer tender documents.
3 documents required · 3 mandatory
₹1,500
₹45,000
20 Aug 2026
20 Aug 2026
27 Aug 2026
20 Aug 2026
27 Aug 2026
20 Aug 2026
FINANCIAL BID NO.: DSWC/SAN/2026-2027/12
Rates for Civil Works (Approved by CCS Punjab Chandigarh)
Name of the Firm/Bidder
Phone Number of Bidder Email id of Bidder
Total Estimated Amount of Work Rs.
Quoted by Contractor (As % less of Estimated Amount) Quote (+/-%)
Note: Please quote only figure (upto 2 decimal points) in above blue colour box in minus or plus. Do not put %age sign after this figure. Please check Quoted Rate in Next cell.
Name of Work :- Earth work for excavation of Trenches for laying of Underground pipeline , lowering and jointing of 400 mm Dia RCC Pipes, fixing of AVP , Risers, Construction of Haudies at Village - Hamidi (C/o 36100/L), Tehsil and District- Barnala.
Item of Work Quantity Unit Rate in (Rupees) Total in Rupees
Earth work in Excavation in trenches not exceeding 2 m depth including dressing Bottom & sides of trenches, stacking the excavated Soil Clear from the edge of excavation & subsequent filling around layed pipes in 15 cm layer with compaction including disposal of all surplus soil as directed within a lead of 30 meters. 10127.7 /Cum 93.78 Rupees Ninty Three and Seventy Eight Paise Only
Lowering of R.C.C. Class NP-2 Pipes in to trenches for all depths and laying out the same to correct alignment ,gradients level etc. /Mtrs 71 Rupee Seventy One Only
Jointing of class N.P.2 R.C.C pipes in trenches using collar joints jointed with 1:2 1/2 Cement sand mortar including facing trowelling and finishing the joints at the angle of 45 degree with faces of collars keeping joints w.e.f till cured, testing the drain lines or leakage and making good all leakage and defects to the satisfaction site incharge . 2728 /Joints 208.61 Rupees Two Hundred Thirty Four and Eighty One Paise Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (400 mm) 57 /Cut hole 105 Rupees One hundered Sixteen Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (150 mm) 24 /Cut hole 41 Rupees Fourty One Only
Fixing of Riser Pipe & Fixing of Alfa Alfa valves with C.C 1:2:4 (400 mm) /Riser & Valve 707.98 Rupees Seven Hundared Sixty and Two Paise Only
Fixing of Air vent Pipes with C.C 1:2:4 (150 mm) /Air pipe 288.21 Rupees Two Hundred Eighty Five and Seventy Only
Fixing of Gate valves with C.C 1:2:4 (400 mm) 19 /Gate Valve 2052.99 Rupees Two Thousand One Hundred Sixty Seven and Forty One Paise Only
Estimate of Charges for pump stand 1100mm
S&S Pump Stand 1000mm(3Mtr) 11 Nos
Material For Fixing of P.S:-
Cement 2 Nos 300 Rupess Three Hundred Only
Sand 9 Cft 38.01 Thirty Seven Rupees and Eight Paise Only
Aggrigate 15 Cft 38.13 Thirty Seven Rupees and Eight Paise Only
Labour for installation of P.S 1 No 2079 Thirty Seven Rupees and Eight Paise Only
Foundation Of Pump Stand (1:8:16) Dimension (2*2*0.15m)
Cement 1.08 Bags 300 Three Hundred
Sand 10.6 Cft Thirty Seven Rupees and Eight Paise Only
Aggrigate 21.18 Cft Thirty Seven Rupees and Eight Paise Only
1:8:16 Labour 0.6 Cft 1269.47 One Thousand Two Hundred Sixty Nine Rupees and Fourty Seven Paise Only
Excavation(2*2*2) 8 Cft 93.78 Ninety Three Rupees and Seventy Eight Paise Only
Total Cost for Eleven Pump Stand
Estimate of Charges for Haudi (1.20 X 1.20 X 3.00 m)
Earth work in Excavation 8 cum 93.78 Rupees Ninty Three and Seventy Eight Paise Only
B.B.C 1:8:16 0.6 cum 3879.26 Rupees Three Thousand Eight Hundred Seventy and Twenty Paise Only
Plain Cement Concrete 1:2:4 0.14 cum 5109.7 Rupees Five Thousand One Hundred Four Only
First Class burnt brick work laid in Cement sand mortar in 1:4 in foundation and plinth 4.75 cum 5625.28 Rupees Five Thousand Forty Five Only
12.5 mm thick cement plaster work 1:4 15.32 cum 202.27 Rupees Two Hundred Two and Ten Paise Only
RCC Slab 1:2:4 0.21 cum 8206.5 Rupees Eight Thousand Two Hundred Only
Foot rest (Item No. 29.37) 6 No 100 Rupees One Hundred Only
Total Cost for ONE Haudi
Total Cost for Seven Haudis 44805-L RATTAKHERA
Cost of Other Items
Providing and Fixing of jaal 1 each 4000 Rupees Four Thousand Only
Sign Board (5' X 3') 1 each 4000 Rupees Four Thousand Only
Nimar for jointing the pipe 376.464 KG 60 Rupees Sixty Only
Provision for Carriage of Pipe for lead upto 2 Km (Subjected to actual site condition, given as per actual measurements provided by the site incharge or the Santioned amount in tender whichever is less) as per CSR 5.2 (13 b,c,d) of 2020 672.708 Ton 172.94 Rupees One Hundred Seventy Two and Forty Paise Only
Credit of damaged lined water channel existing on site to be deducted from the bill of Agency 339960
Grand Total (A)
Total Credit of Damaged Lined Water Channel Existing on Site to be Deducted from the Bill of Agency
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.54 MB
NITUGPL262712.pdf
Tender Documents • 0.52 MB
DNITUGPL262712.pdf
Tender Documents • 1.18 MB
FBUGPL262712.xls
Additional Documents • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].