| 1 | L1₹2.5 CrAccepted-AOC | ₹2.5 Cr | L1 | Accepted-AOC Quoted L1 rate |
| 2 | L2₹2.5 Cr+₹4.4 L (1.78%)Rejected-AOC | ₹2.5 Cr+₹4.4 L (1.78%) | L2 | Rejected-AOC Quoted L2 rate |
| Sl No | Description | Qty | Unit | RENGASAMY S L2 | AMMAN CONSTRUCTION L1 |
|---|---|---|---|---|---|
| 1.00 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25mm using 13.20mm IRC size HBG metal with 44 Kg of Bitumen-for 1cum of metal mixed in hot mix plant laying at site KM 6/0 - 7/0 | 0.04 | Cum | 4,520 ₹180.8 | 4,513 ₹180.52 Lowest |
| 2.00 | KM 7/0 - 8/0 | 0.06 | Cum | 4,530 ₹271.8 | 4,525 ₹271.5 Lowest |
| 3.00 | KM 8/0 - 9/0 | 0.08 | Cum | 4,545 ₹363.6 | 4,535 ₹362.8 Lowest |
| 4.00 | KM 9/0- 10/0 | 0.7 | Cum | 4,565 ₹3,195.5 | 4,545 ₹3,181.5 Lowest |
| 5.00 | KM 10/0 - 11/0 | 0.27 | Cum | 4,575 ₹1,235.25 | 4,555 ₹1,229.85 Lowest |
| 6.00 | KM 11/0 - 12/0 | 0.12 | Cum | 4,600 ₹552 | 4,565 ₹547.8 Lowest |
| 7.00 | KM 12/0 - 13/0 | 0.05 | Cum | 4,600 ₹230 | 4,575 ₹228.75 Lowest |
| 8.00 | KM 13/0 - 14/0 | 0.16 | Cum | 4,600 ₹736 | 4,585 ₹733.6 Lowest |
| 9.00 | KM 14/0 - 15/0 | 0.14 | Cum | 4,600 ₹644 | 4,595 ₹643.3 Lowest |
| 10.00 | KM 15/0 - 16/0 | 0.14 | Cum | 4,650 ₹651 | 4,605 ₹644.7 Lowest |
Tender Value
₹2.5 Cr
EMD Value
₹5.0 L
Closing Date
30 May 2025, 3:00 pmClosed
Project Director
DRDA Perambalur
Renewal of 1 road in Veppur Block in Perambalur District under Periodic Renewal of PMGSY Roads 2024-25 Package No.TN11-123
2025_RDTN_141332_1
DIPR/2253/Tender/2025 Dated 15.05.2025
Open Tender
Civil Works - Roads
Item Rate
120 days
Perambalur
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹5.0 L
DRDA Perambalur
7 Aug 2025
17 May 2025
30 May 2025
17 May 2025
30 May 2025
17 May 2025
23 May 2025
Amount
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25mm using 13.20mm IRC size HBG metal with 44 Kg of Bitumen-for 1cum of metal mixed in hot mix plant laying at site KM 6/0 - 7/0
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS KM 6/000 - 7/000
Applying TACK COAT over BT surface at 3 Kg of RS-1 Bitumen Emulsion/ 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. KM 6/000 - 16/520
Providing and laying Bituminous Concrete to 25mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of PMB Cubes for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as KM 6/000 - 16/520
Provision for Repainting Citizen Information Board
60cm Circular ( Mandatory Sign)
Road Marking with hot applied thermoplastic compound with reflectorising glass base on bituminouse surface
Towards the charges for routline maintenance of the road work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
RENGASAMY S (BID ID -618136)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .