| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.4 LAccepted-AOC | ₹12.4 L | L1 | Accepted-AOC L1 |
| 2 | L2₹12.9 LRejected-AOC | ₹12.9 L | L2 | Rejected-AOC L2 |
| 3 | L3₹14.1 LRejected-AOC | ₹14.1 L | L3 | Rejected-AOC L3 |
| 4 | L4₹14.1 LRejected-AOC FATEHPUR | ₹14.1 L | L4 | Rejected-AOC L4 |
| 5 | L5₹14.1 LRejected-AOC | ₹14.1 L | L5 | Rejected-AOC L5 |
Tender Value
₹14.1 L
EMD Value
₹1.4 L
Closing Date
4 May 2026, 3:00 pmClosed
chief Engineer nagar nigam saharanpur
chief Engineer nagar nigam saharanpur
Construction of CC road and drain from Ashu house to Naresh house via Poonam Chaudhary house in Ward No. 20 Dabki Junardar Paras Vihar Colony.
2026_NNSAH_1143846_1
6168 B
Open Tender
Civil Works
30 days
saharanpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,298
₹1.4 L
Yes
1 Jun 2026
30 Apr 2026
5 May 2026
30 Apr 2026
4 May 2026
30 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in filling with cartage 8.0 km from site i/c all comp of work. | 341.84 | m3 | 255 | ₹87,169.2 |
| 2 | Concrete with 4 cm gauge brick ballast fine sand and cement in proportion are 1:6:12 in foundation and under floors, including supply of all materials, labour. T&P etc. required for proper completion the work. | 10.44 | m3 | 2,985 | ₹31,163.4 |
| 3 | M-150 Brick work in 1:4 one cement and four course sand, mortar in foundation in plinth including suopply of all material labour, T&P etc. required for proper completion of the work. | 29.23 | m3 | 4,690 | ₹1,37,088.7 |
| 4 | Cement Concrete with 2 cm gauge approved graded stonee grit, coarse sand and cement in the proportion of 4:2:1, including supply of all materials, labour, tools & plants etc required for proper completion of the work As per direction of E/l. for nali | 1.48 | m3 | 5,750 | ₹8,510 |
| 5 | 12 mm thick plaster with cement and approved c sand mortar in 1:4 over brick work minium thickness not to be less than 1 Cm including supply of all material labour Tool & Plants etc. required for proper completion of the work. | 124.12 | m2 | 165 | ₹20,479.8 |
| 6 | Construction of Granular sub- base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in lace method with rotavator of OMC, and compacting with vibratory power roller to achive the desired density, complete (As per clause 401 RA) | 68.06 | m3 | 2,015 | ₹1,37,140.9 |
| 7 | Cement Concrete with 4cm gauge approved stone grit, coarse sand & cement in the proportion of 8:4:1 including supply of all materials ,labour, Tools & plants etc .required for proper completion of the work. | 45.37 | m3 | 4,850 | ₹2,20,044.5 |
| 8 | Cement concrete with 2cm gauge approved stone grit, coarse sand & cement in proportion of 1:1.50:3 in cc pavement (theckness as per design) cement coarse & fine aggregate confirming to IS standard mixed in concrete mixture /Plant of not less then 0.2 cum capacity & appropriate weight batcher using approved mix design, laid in approved fixed form work (steel) channel) laying and fixing of 125 micron thick polythene film, wedges, steel plates including leveling the form work spreading the concretewith shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including hassion cloth for curring of concrete pavements for not less then 14 days curring compound (where as specified) and water finishing to lines & grade including supply of all material, labour, tools & plants etc. required for proper completion of work and also including complete shifting of Recron 38 fibre reinforcement material etcl & concrete etc. | 68.06 | m3 | 7,300 | ₹4,96,838 |
| 9 | R.C.C. Work with cement, approved coarse sand & 2 cm gauge approved stone grit in proportions of 1:1.5:3 in slab/ nall with all comp of work. | 4.2 | m3 | 7,400 | ₹31,080 |
| 10 | M.S. (tor steel or plain) in Plain work such as R.C.C. or R.B. work including bending for proper shape and including supply of steel & its wastage, bend, hooks, and authorised overlapping shall be measured and including cost of binding wire. | 3.3 | qtl | 8,529 | ₹28,145.7 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.22 MB
BOQ_2136956.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid