| # | Company | Amount |
|---|---|---|
| 1 | ₹2.2 Cr |
Tender Value
₹3.6 Cr
EMD Value
₹7.1 L
Closing Date
10 Mar 2026, 3:00 pmClosed
SANTOSH KUMAR PRABHAKAR
EE
FLOOD CONTROL DIVISION MUZAFFARPUR
BINOD KUMAR
SE
A.E. WORK AT BARA BHARATI WARD NO.-1 LEFT BANK OF RIVER IN FRONT OF K.M. 24.00 TO 25.00 K.M. OF R.B.G.E. U/S OF A-GHAT (AGENDA NO-242/68/2026)
126689
NIT 03 SBD/2025-26/FCD MUZAFFARPUR/GR2
Open Tender
CIVIL
Muzaffarpur
• EMD Amount (Rs 713000)
• Legal Status of Bidder.
• Place of Registration.
• Principal place of Business
• Power of attorney of signatory Bid (Attached or Not)
• Total value of civil engineering construction work performed in 2020-21
• Total value of civil engineering construction work performed in 2021-22
• Total value of civil engineering construction work performed in 2022-23
• Total value of civil engineering construction work performed in 2023-24
• Total value of civil engineering construction work performed in 2024-25
• Satisfactory completed atleast one similar work of value not less than 10% (35.65) of estimated value of contract (Rs in Lakhs)
• Work Exp. Quantity Protection works (Pitching/ Crating/ Soling with Boulder/Brick/Geo bag/E.C.bag/Nylon crates/Gabians etc. Ft combined quantities in M3) 4740.00 M3
• Bid capacity (356.47 Lakhs)
• Existing commitments and ongoing works
• Work for which Bid already submitted
• Availability of key items of Contractor's Equipment Poclain/ Excavator / Front End Loader Max. Age 8/8/8 Years 2/2/2Nos., Tractor / Tipper / Dumper Age 5/6/6 Years 10/5/5 Nos.
• Key Personal Site Engineer (Site Engineer / B.E. Civil + 07 Years Exp. (3 years in Irrigation works) or retired A.E. ) No.1 Site Supervisor (Site Supervisor / Fresh Graduate in Civil or Diploma Civil + 03 Years Exp. Or retired I.T.I. Holder.) Nos. 1
• Evidence of accesses to Financial Resources 10% ( 35.65 Lakhs) of estimated cost
• PROGRAMME Of CONSTRUCTION
• Litigation History
• Affidavit-- Regarding statements made in the required attachments are true and correct.
• Undertaking
• Time of Completion As per tender document.
• Registration No
• I.T. & G.S.T. Registration & clearance Certificate
• Character Certificate (As per Direction of W.R.D Letter No 124 dated 04-02-2021)
• Noc for debar
• If Any Other Document Required As per NIT
CIVIL
PERCENTAGE
L1
1
28 documents required · 28 mandatory
₹10,000
Processing Fee: 5900
₹7.1 L
Office of Chief Engineer, Flood Control & Drainage, Water Resources Department, Muzaffarpur
18 May 2026
4 Mar 2026
12 Mar 2026
5 Mar 2026
10 Mar 2026
5 Mar 2026
7 Mar 2026
Technical Sheet
Name of Work A.E. WORK AT BARA BHARATI WARD NO.-1 LEFT BANK OF RIVER IN FRONT OF K.M. 24.00 TO 25.00 K.M. OF R.B.G.E. U/S OF A-GHAT (AGENDA NO-242/68/2026) Cost of Work as per BOQ(Rs in Lakhs) 0.49599 Time of Completion 15-05-2026 ALL COLOURED CELL TO BE FILLED ACCORDINGLY
Sactioned Amount Rs.3,56,47114.00 Date of Sanction 27-02-2026 Date of Tender 05-03-2026 TO 10-03-2026 3:00 PM
Sl No. Items Requirement Requirement Cl. No. Name of the contractor
Address of the contractor
1 Bid Validity Bids shall remain valid for a period not less than 120 days after the deadline date. A Bid valid for a shorter period shall be rejected by the Employer as non-responsive 120 Days Bid validity periods In days
2 Bid Security (A) Unconditional bank guarantee from any scheduled Indian bank issued within the state in the format given (If issued from any bank outside state will be converted to any bank within the state before executing the agreement. Amount To be entered (Rs in Lakhs)
(B) Earnest Money can be paid through Internet Payment Gateway (Credit/Debit Card), Net Banking, NEFT/RTGS in online mode. Amount To be entered (Rs in Lakhs)
Bid Security Amount - (Rs. In Lakhs) Bid Security Amount - Rs.
3 (i) Legal Status of Bidder.
(ii) Place of Registration.
(iii) Principal place of Business
(iv) Power of attorney of signatory Bid Attached (If any) or Not
4 Total value of civil engineering construction work performed in last five years. (All bidders shall include Reports on the financial standing of the Bidder, Such as profit and loss statements and auditor’s reports for the past five years) 1. Annual Financial Turn Over usually not less than 50% of the estimated annual payments under the contract (Rs in Lakhs)
2020 - 2021 Amount To be entered (Rs in Lakhs)
Escalation Factor= 1.17
2021 - 2022 Amount To be entered (Rs in Lakhs)
Escalation Factor= 1.26
2022 - 2023 Amount To be entered (Rs in Lakhs)
Escalation Factor= 1.36
2023- 2024 Amount To be entered (Rs in Lakhs)
2024-2025 Amount To be entered (Rs in Lakhs)
Escalation Factor= 1.47
5 Work Experience of Similar nature Satisfactory completed atleast one similar work of value not less than 10% of estimated value of contract (Rs in Lakhs) Amount To be entered (Rs in Lakhs)
6 Minimum Quantities of work done as prime contractor in any one year during last five years. Items Unit Quantity
Protection works (Pitching/ Crating/ Soling with Boulder/Brick/Geo bag/E.C.bag/Nylon crates/Gabians etc. Ft combined quantities in M3) M3 4740 Value to be entered in unit Cum.
Value to be entered in unit Cum.
Value to be entered in unit Cum.
7 Bidding Capacity: More than the total Bid value of present work = A*N*3-B=Rs. ____.Where A = Maxm. Value of work executed in any one yr during last 5 yrs. N= Nos of years for completion of works. B=Value of existing commitments & ongoing works to be completed in period
(a) Existing commitments and ongoing works Amount To be entered (Rs in Lakhs)
(b) Work for which Bid already submitted Amount To be entered (Rs in Lakhs)
8 Availability of key items of Contractor's Equipment Type of Equipment/Maximum age No. Required Max. Age in years Nos. Required Nos./ Max. Age
Poclain/ Excavator / Front End Loader or any other loading machine 8/8/8 2/2/2
Tractor/Tipper/Dumper 05/06/06 10//5/5
9 Key Personnel Personnel/Qualification/Contract Package Size Name of the Personnel and Experince in years
Site Engineer/ B.E. Civil+ 07 years exp. (3 years in Irrigation work) or retired A.E. 1
Site Supervisor / Fresh Graduate in Civil or Diploma Civil + 03 years Exp. Or retired ITI Holder 1
10 Evidence of accesses to Financial Resources Evidence of access to or availability of creadit facilities (10% of estimated cost), certified by bankers (Not more than 3 months old). (Rs in Lakhs). Amount To be entered (Rs in Lakhs)
11 Proposed methodology and programme of construction. Justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones. (Attached or not)
12 Litigation History Information regarding any litigation, current or during the last five years, in which the Bidder is involved, the parties concerned, and disputed amount. (Attached or not)
13 Affidavit Affidavit should be submitted in the format as per the Annexure-3 of the Water Resources Department letter no. 536 dated 13.06.2013 .
14 Undertaking Able to invest a minimum of cost upto 25% of contract value of work. During implementation of contract.
15 Time of Completion To be entered in months
16 Registration No.
17 Non assosiation with Departmental Officials
18 Proposal of sub-Contract
19 Joint Venture
20 Character Chertificate
21 I.T. & GST Registration & clearance Certificate
22 Labour License
23 NOC for Debar (If required)
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in the following pages will be used for purposes of post qualification as provided for in Clause 4 of the Instructions to Bidders. This information will not be incorporated in the Contract.
NAME OF THE CONTRACTOR
1 For Individual Bidders
1.1 Constitution or legal status of Bidder (Attach copy)
Place of registration :
Principal place of business :
Power of attorney of signatory of Bid (Attach)
1.2 Total value of Civil Engineering construction work performed in the last five years** (in Rs. Million)
1.3.1 Work performed as prime contractor, work performed in the past as a nominated sub- contractor will also be considered provided the sub-contract involved execution of all main items of work described in the bid document, provided further that all oth
NAME OF THE CONTRACTOR
Project Name Name of the Employer* Description of work Contract No. Value of Contract (Rs. In Crore) Date of issue of work order Stipulated period of completion Actual date of completion* Remarks explaining reasons for delay & work completed)
* Attach certificate(s) from the Engineer(s)-in-Charge
** Upto last day of the month Immediately preceding the last date of bids received. (PWD letter no. 2863(E) dt. 7.6.2017
Attach certificate from Chartered Accountant.
1.3.2 Quantities of work executed as prime contractor, work performed in the past as a nominated sub-contractor will also be considered provided the sub-contract involved execution of all main items of work described in the bid document, provided further
NAME OF THE CONTRACTOR
Year Name of the work Name of the Employer* Quantity of work performed (cum) @ Remarks
E.C. Bag filling/ Geobag filling E/W Remarks* (indicate contract Ref)
1.4 Information on Bid Capacity (works for which bids have been submitted and works which are yet to be completed) as on the date of this bid.
(A) Existing commitments and on-going works:
NAME OF THE CONTRACTOR
Description of works Place & State Contract No. Name & Address of Employer Value of Contract (Rs Cr) Stipulated Period of Completion Value of works* remaining to be completed (Rs Cr) Anticipated date of completion
* Attach certificate(s) from the Engineer(s)-in-Charge
The item of work for which data is requested should tally with that specified in ITB clause 4.5A ©
** Immediately preceding the financial year in which bids are received.
# Delete, if prequalification has been carried out.
(B) Works for which bids already submitted :
Description of works Place & State Name & Address of Employer Estimated value of works (Rs Cr) Stipulated period of completion Date when decision is expected Remarks, if any
1.5 Availability of key items of Contractor’s Equipment essential for carrying out the Works [Ref. Clause 4.5(B)(a)]. The Bidder should list all the information requested below. Refer also to Sub Clause 4.3 (d) of the Instruction to Bidders.
NAME OF THE CONTRACTOR
Description of works Requirement Availability proposals Remarks (from whom to be purchased)
No. Capacity Owned/Leased to be procured Nos./Capacity Age/ Condition
1.6 Qualifications and experience of key personnel required for administration and execution of the Contract [Ref. Clause 4.5(B)(b)]. Attach biographical data. Refer also to Sub Clause 4.3 (e) of instructions to Bidders and Sub Clause 9.1 of the Condition
NAME OF THE CONTRACTOR
Position Name Qualification Year of Experience (General) Years of experience in the proposed position
1.7 Proposed sub-contracts and firms involved. [Refer ITB Clause 4.3(k)]
NAME OF THE CONTRACTOR
Sanction of the works Value of Sub-contract Sub-contractor (Name & Address) Experience in similar work
Attach copies of certificates on possession of valid license for executing water supply/ sanitary work/ building electrification works [Reference Clause 4.5(d) & Clause 4.5(e)]
*1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors' reports (in case of companies/corporation), etc. List them below and attach copies.
1.9 Evidence of access to financial resources to meet the qualification requirements: cash in hand, lines of credit, etc. List them below and attach copies of support documents.
1.10 Name, address and telephone, telex and fax numbers of the Bidders' bankers who may provide references if contacted by the Employer.
1.11Information on litigation history in which the Bidder is involved.
NAME OF THE CONTRACTOR
Other Party(ies) Employer Cause of Dispute Amount involved Remarks showing Present Status
1.12 Statement of compliance under the requirements of Sub Clause 3.2 of the instructions to Bidders. (Name of Consultant engaged for project preparation is ** ........................ …………….............................)
Proposed work method and schedule. The Bidder should attach descriptions, drawings and charts as necessary to comply with the requirements of the Bidding documents. [Refer ITB Clause 4.1 & 4.3(1)]
1.15 Quality Assurance Programme
2 Additional Requirements
2.1 Bidders should provide any additional information required to fulfill the requirements of Clause 4 of the Instructions to the Bidders, if applicable.
(ii) Undertaking
*** (iii) Update of original prequalification application
*** (iv) Copy of original prequalification application
*** (v) Copy of prequalification letter
* Delete, if prequalification has been carried out.
** Fill the Name of Consultant.
*** Delete, if prequalification has not been carried out.
Check List for Submission Of Tender
Evaluation will be done as per the information provided in the document attached with tender. Bidder may disqualified, if documents are not attached properly.
Name of the Bidder
Sl. No. Checklist Items (Attach Documents in Link Name As Given in Adjacent coloumn in Edit Attachment Folder) Link Name in Edit Attachment Document attached
1 BIDSECURITY PHOTO COPY BID SECURITY PC
2 LAST 5 YEARS ANNUAL TURN OVER ANNUAL TURN OVER
3 EXPERIENCE Of SIMILAR NATURE Of W0RKS EXP SIM NAT
4 QUANTITY OF WORK (E/W, GSB, WMM, BITUMINOUS WORK, PCCetc) EXECUTED DURING LAST 5 YEARS) WORK EXE QTY
5 BALANCE VALUE OF ON GOING WORKS BAL VAL WORKS
6 EXISTING COMMITMENTS EXIST COMT
7 BANKER'S CERTIFICATE FOR ACCESS OF FINACIAL RESOURCES BANK CER
8 AFFIDAVIT AFFIDAVIT
9 UNDERTAKING FOR BID VALIDITY, INVESTMENT ABILITY, NON ASSOCIATION WITH OFFICIALS. UNDERTAKING
10 LITIGATION HISTORY LIT HIS
11 PLANT and MACHINARIES PT & MAC
12 KEY PERSONNEL KEY PER
13 Registration REGISTRATION
14 Power of Attoney POW AT
15 Legal Status Of Bidder LEGAL
16 PROGRAMME Of CONSTRUCTION PROG CONS
17 LABOUR LICENSE LAB LIC
18 IT & ST REGISTRATION and CLEARANCE CERTIFICATE IT ST CLEARANCE
19 NOC FOR DEBAR DEBAR
20 Proposal of sub-Contract SUB-CONTRACT
21 Joint Venture JV
22 Character Chertificate CC
IF YOU HAVE NOT BEEN DEBARED WRITE "NOT APPLICABLE" IN YOUR LETTER HEAD SCAN AND UPLOAD IN THE IN NOC FOR DEBAR LINK
Note:-Attachment should be self attested and should be attached as per above instruction, otherwise it may be rejected.
I, the undersigned, do hereby certify that all the statements made in the required attachments are true and correct.
Signature & Seal of the Bidder
aoc.json
Purchase Order
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
ALL LETTER OF SBD.pdf
NIT • 12.26 MB
Letter No 143.pdf
NIT • 3.13 MB
Letter No 0152.pdf
NIT • 0.09 MB
letter no. 642.pdf
NIT • 0.16 MB
LETTER NO 1964.pdf
NIT • 0.78 MB
Nit No.-3SBD-2025-26 (Hindi).pdf
NIT • 3.47 MB
Nit No.-03SBD-2025-26(Eng).pdf
NIT • 3.96 MB
BOQ BARA BHARTI.pdf
NIT • 0.46 MB
SBDDOCUMENT BARA BHARATI.doc
NIT • 15.96 MB
TECHNICAL SHEET BARA BHARATI.xls
NIT • 0.15 MB
BOQ BARA BHARTI.pdf
NIT • 0.46 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .