Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.0 LAccepted-AOC | L1 | Accepted-AOC Accept | |
| 2 | L2₹4.0 L+₹124.77 (0.03%)Rejected-AOC | L2 | Rejected-AOC Reject |
Tender Value
₹4 L
EMD Value
₹4,000
Closing Date
4 Mar 2025, 3:00 pmClosed
BLOCK DEVELOPMENT OFFICER(B.P),SIRKALI
BLOCK DEVELOPMENT OFFICER(B.P),SIRKALI
Construction of Cremation shed at Chinna Nemmelli Opposite Manmathankoil in Keelasattanathapuram Panchayat IN SIRKALI BLOCK MPLADS 2024-2025
2025_RDTN_526945_1
240/2025/a4 21.02.2025
Open Tender
Civil Works
Item Rate
BLOCK DEVELOPMENT OFFICER(B.P), SIRKALI
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹4,000
Yes
BLOCK DEVELOPMENT OFFICER(B.P),SIRKALI
11 Mar 2025
22 Feb 2025
4 Mar 2025
22 Feb 2025
4 Mar 2025
23 Feb 2025
22 Feb 2025 - 23 Feb 2025
22 Feb 2025
Amount
1.Construction of Cremation Shed at Chinna Nimmelli Opposite Manmadhan koil in Keelasattanathapuram Panchayat
Earth work excavation in classes all clasess of soils and depositing on bank with initial lead and lift soils such as, sand, or other loose soil, wet sand not under water silt and ordinary soil, sandy loom, and hard stiff, block cotton soil, red earth, earth mixed width 50% fair sized boulders etc., except hard rock which requires blasting as per SS20B, including all labour for balling out water if necessary and all labour and other incidental charges etc. complete for FOUNDATION.
Filling with river sand into foundation and basement including cost and conveyance of sand to worksite including labour for filling, watering within 200m lead for good water, including tamping if necessary, and all labour and all other incidental charges etc., complete for FOUNDATION / BASEMENT.
Cement Concrete 1: 4 : 8 mix using 40mm ISS Size HBG metal from approved quarry, including cost and conveyance of all materials to worksite, including labour for mixing, laying the concrete the concrete watering within 200m lead for good water, and compacting the concrete including labour and all other incidental charges etc., complete for FOUNDATION / BASEMENT.
Cement Concrete 1: 2 : 4 mix using 20mm ISS Size HBG metal from approved quarry, including cost and conveyance of all materials to worksite, including labour for mixing, laying the concrete the concrete watering within 200m lead for good water, and compacting the concrete including labour and all other incidental charges etc., complete.
Reinforced Cement Concrete 1:1.5:3 mix using 20mm ISS size HBG metal from approved quarry, including cost and conveyance all materials to worksite including labour for mixing, laying, watering with in 200m lead for good water, compacting the concrete including all labour for forming formwork and centering charges etc., (but excluding const and conveyance steel reinforcement ) and all labour and all other incidental charges etc., complete for UP TO BASEMENT
Brick work in C.M 1:5 mix using country bricks of size 83/4” x 41/4 " x 21/4" , including cost and conveyance of all materials to worksite, including labour for watering with good water within 200m Lead for good water, including all labour and all other incidental charges etc. complete for ABOVE BASEMENT.
Brick work in C.M 1:5 mix using country bricks of size 83/4” x 41/4 " x 21/4" , including cost and conveyance of all materials to worksite, including labour for watering with good water within 200m Lead for good water, including all labour and all other incidental charges etc. complete for ABOVE BASEMENT.
Reinforced Cement Concrete 1:1.5:3 mix using 20mm ISS size HBG metal from approved quarry, including cost and conveyance all materials to worksite including labour for mixing, laying, watering with in 200m lead for good water, compacting the concrete including all labour for forming formwork and centering charges etc., (but excluding const and conveyance steel reinforcement ) and all labour and all other incidental charges etc., complete for ABOVE BASEMENT
Supply and fabrication of steel including cost and conveyance of steels from godown to worksite including labour for cutting, jointing and welding is necessary including labour for dying with binding wire and labour for placing in position as directed by departmental officers, including all labour and all other incidental charges etc., complete for all R.C.C items.
Plastering with Cement Mortar 1:3, 10mm thick including cost and conveyance of all materials to worksite, and all labour for watering, curing and all leads for good water including cost of form work, and all labour and all other incidental charges etc. complete.
Providing pressed Tiles of size 20x20x2cm including cost and conveyance all materials to worksite, including labour for watering, curing with 200m lead for good water, including cost of formwork , and all labour and all other incidental charges etc. complete
Celing Plastering with Cement Mortar 1:3, 10mm thick including cost and conveyance of all materials to worksite, and all labour for watering, curing and all leads for good water including cost of form work, and all labour and all other incidental charges etc. complete.
Centring and shttering including cost and conveyance of all materials to worksite and all labour and all other incidental charges etc., complete
Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the walls smooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification. (The colour and shade of the distemper shall be got approved by the Executive Engineer before use of work).
Provision for Name Baord
Provision for photo Charges
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Kumar Kaliyamoorthy (BID ID -1262840)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .