| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.4 CrAccepted-Finance | ₹8.4 Cr | L1 | Accepted-Finance Quoted Low |
| 2 | L2₹87.5 CrRejected-Finance | ₹87.5 Cr | L2 | Rejected-Finance Quoted very high |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not meeting the NIT criteria |
| Sl No | Description | Qty | Unit | SGB INFRA LTD L1 | AASTHA CONTRACTS INDIA PRIVATE LIMITED L2 |
|---|---|---|---|---|---|
| 1.00 | Engineering Procurement and Construction of extension of Terminal Building along with Kerb area for Kerb amenities etc. with Site development and offices as per drawing, site survey, Earth Work, RCC / Composite Steel Structure/Steel Structure, Roofing system and steel structure, Brick Work / AAC Block work, Aluminium / Glazed façade, Stainless Steel Railings, Cladding works with ACP or as approved by EIC, Flooring, False Ceiling, Partition, offices, polycarbonate canopy, Rain water harvesting, Portable container project office, Interior Works and Sanitary, Plumbing and Water Supply works, Drainage system, Utilities, Internal & External Electrification , Power Supply System including LT panel, etc. & UPS, HVAC with VRV/VRF system, split ACs, Sliding door, Air curtain, Fire Hydrant, Fire Alarm Detection System, Internal, External Illuminated and Non-Illuminated Way Finding Signages and Emergency escape signages, Building Signage, PA system etc. as per drawings including dismantling, shifting of the existing services as per Specifications, DBR, Scope, Codes and Practices and all other requirements as contained in tender document. The detailed design of facilities shall confirm to standard specified by ICAO, DGCA, AAI, MORTH, IRC, NBC, CPWD, IS, IEC etc. wherever required and in conformity with regulations regarding permissible heights, locations requirements etc. i/c all other works covered under Scope of work and meeting all relevant statutory requirements i/c optimization of energy efficiency complete as required. Scope of work shall also cover DLP of 02 years after actual completion of work thereafter
Note: (1) The bidder shall quote the offer excluding GST, ESI & PF (Employer’s Contribution).
(2) Bidder has to quote their actual cost of the project In INR not in percentage above/below. | 1 | job | 8,40,60,000 ₹8.4 Cr | 87,50,00,000 ₹87.5 Cr |
Tender Value
₹8.4 Cr
EMD Value
₹25.3 L
Closing Date
24 Nov 2025, 6:30 pmClosed
SM (E-c)
Hindon Airport Ghaziabad-201005
Extension of Terminal Building Towards City Side Including Provision of Canopy, Construction of Kerb Area and Associated Road Works at Civil Enclave, Hindon Airport, Ghaziabad UP Recall
2025_AAI_254194_1
AAI/RHQ-NR/Engg-C/Ext Tr Bldg/Hindon/02/2025
Open Tender
Civil Works
240 days
Hindon Airport
Please refer Tender documents.
20 documents required · 20 mandatory
₹1,770
AAI
₹25.3 L
Hindon Airport
27 Jan 2026
3 Nov 2025
28 Nov 2025
3 Nov 2025
24 Nov 2025
3 Nov 2025
3 Nov 2025 - 11 Nov 2025
7 Nov 2025
Engineering Procurement and Construction of extension of Terminal Building along with Kerb area for Kerb amenities etc. with Site development and offices as per drawing, site survey, Earth Work, RCC / Composite Steel Structure/Steel Structure, Roofing system and steel structure, Brick Work / AAC Block work, Aluminium / Glazed façade, Stainless Steel Railings, Cladding works with ACP or as approved by EIC, Flooring, False Ceiling, Partition, offices, polycarbonate canopy, Rain water harvesting, Portable container project office, Interior Works and Sanitary, Plumbing and Water Supply works, Drainage system, Utilities, Internal & External Electrification , Power Supply System including LT panel, etc. & UPS, HVAC with VRV/VRF system, split ACs, Sliding door, Air curtain, Fire Hydrant, Fire Alarm Detection System, Internal, External Illuminated and Non-Illuminated Way Finding Signages and Emergency escape signages, Building Signage, PA system etc. as per drawings including dismantling, shifting of the existing services as per Specifications, DBR, Scope, Codes and Practices and all other requirements as contained in tender document. The detailed design of facilities shall confirm to standard specified by ICAO, DGCA, AAI, MORTH, IRC, NBC, CPWD, IS, IEC etc. wherever required and in conformity with regulations regarding permissible heights, locations requirements etc. i/c all other works covered under Scope of work and meeting all relevant statutory requirements i/c optimization of energy efficiency complete as required. Scope of work shall also cover DLP of 02 years after actual completion of work thereafter Note: (1) The bidder shall quote the offer excluding GST, ESI & PF (Employer’s Contribution). (2) Bidder has to quote their actual cost of the project In INR not in percentage above/below.
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.52 MB
TenderdocumentTB.pdf
Tender Documents • 26.00 MB
BOQ_292670.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid