Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.5 LAccepted-AOC | ₹20.5 L | L1 | Accepted-AOC L1 |
| 2 | L2₹20.5 LRejected-Finance DOOR NO 7 121 SURVEY NO 7 121 K PUDUR | TIRUNELVELI | TAMIL NADU | 627001 | ₹20.5 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | S.Ramasubramanian L1 | Lakshmanan L2 |
|---|---|---|---|---|---|
| 1.001.Construction of 60000 litre OHT(12m Staging Height) at Periyatheru Keela Colony in Pappankulam Panchayat in Kadayam Panchayat Union. | |||||
| 2.00Earthwork excavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth | |||||
| 3.00 | First depth of 2m | 59.47 | Cum | 263 ₹15,640.61 | 264 ₹15,700.08 |
| 4.00 | 2 nd Depth | 10.21 | Cum | 276 ₹2,817.96 | 277 ₹2,828.17 |
| 5.00 | Sand filling for foundation with clear M sand including cost of sand watering, ramming and consolidation etc complete as directed by TWAD Board officers. | 2.92 | Cum | 1,630 ₹4,759.60 | 1,631 ₹4,762.52 |
| 6.00 | Cement concrete 1:4:8 (one cement four sand and eight aggregates) using 40mm HBGS for levelling course for foundation including the cost of mixing concrete, ramming, curing etc., complete as directed by TWAD Board officers. | 4.37 | Cum | 5,414 ₹23,659.18 | 5,415 ₹23,663.55 |
| 7.00Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum. | |||||
| 8.00 | For footing below G.L. ( 1,50 to 4,50 below GL ) | 10.53 | Cum | 9,025 ₹95,033.25 | 9,026 ₹95,043.78 |
| 9.00 | For Column and Brace upto G.L ( 0 to1,50 below GL ) | 2.33 | Cum | 8,886 ₹20,704.38 | 8,887 ₹20,706.71 |
| 10.00 | For column and brace I 0 to 4.5m from GL | 4.11 | Cum | 9,027 ₹37,100.97 | 9,028 ₹37,105.08 |
Tender Value
₹23.1 L
EMD Value
₹23,100
Closing Date
18 Feb 2026, 4:00 pmClosed
Block Development officer,V.Pt
Block Development officer,V.Pt,Kadayam
Construction of 60000 litre Capacity OHT(12m staging height) at Periya theru colony in Pappankulam Panchayat.
2026_RDTN_655973_1
COLRD/299/2026-A5
Open Tender
Civil Works
180 days
Kadayam
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹23,100
28 Mar 2026
12 Feb 2026
18 Feb 2026
12 Feb 2026
18 Feb 2026
12 Feb 2026
1.Construction of 60000 litre OHT(12m Staging Height) at Periyatheru Keela Colony in Pappankulam Panchayat in Kadayam Panchayat Union.
Earthwork excavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth
First depth of 2m
2 nd Depth
Sand filling for foundation with clear M sand including cost of sand watering, ramming and consolidation etc complete as directed by TWAD Board officers.
Cement concrete 1:4:8 (one cement four sand and eight aggregates) using 40mm HBGS for levelling course for foundation including the cost of mixing concrete, ramming, curing etc., complete as directed by TWAD Board officers.
Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum.
For footing below G.L. ( 1,50 to 4,50 below GL )
For Column and Brace upto G.L ( 0 to1,50 below GL )
For column and brace I 0 to 4.5m from GL
For column and brace II 4.5m to 7.32m from GL
For column and brace III 7.32 to 10.98m from GL
For column beam floor slab side wall from 10.98m to 14.64 m from GL
For side wall, hance and Roof slab from 14.64 m to 18.30 m from GL
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding
PLANE SURFACES
Below GL
For column footing and GL Brace
GL 0 to 3.30 M
For Brace I
For Brace II
For Brace III
For Brace III
Roof slab
For Floor Beam and Bottm of Floor slab
CURVED SURFACE
For Side Wall, & Floor slab sides and Haunch
For Side Wall, Roof Slab sides
SQUARE COLUMN
For column Below GL
For column GL 0 to 3.30M
For column ( 3.31m to 4.30m ).
For column ( 4.31m to 5.30m).
For Column (5.31m to 6.30m )
For Column (6.31m to 7.30m )
For Column (7.31m to 8.30m )
For Column (8.31m to 9.30m )
For Column (9.31m to 10.30m )
For Column (10.31m to 11.30m )
Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete.
Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete and as directed by Deparment officers.
Refilling the foundation with excavated earth including consolidation as directed by the TWAD Board officers.
Providing MS Ladder & Hand rails arrangements in 60,000 Lits. Capacity OHT With 12.00m Staging Height.
Providing and fixing of RCC inner access ladder in RCC 1:1.5:3 (one cement, one and half sane! and three aggregates) using 20mm HBG stone for OHT including cost of reinforcement, placing grill in position, centering shuttering charges, mixing concrete cur
Providing GI ventilating arrangements mosquito proof nylon net with 50 mm GI pipes and cowl and as directed by Deparment officers
Providing manhole cover of size 1x1 0.75 X 0.75 M in RCC 1: 1.5:3 with suitable reinforcement and 5O x 5O x 6mm MS angle fixed along edges and as directed by Department officers. SFRC
Supply of Pipe connection arrangements for inlet, outlet, scour and Overflow for 60000 litres capacity OHT
65mm dia GI Pipe
65mm dia GI Nipple-0.30m
65mm dia GI Elbow
65mm dia GI Nipple-0.90m
65mm dia GI Nipple-0.45m
65mm dia GI Nipple-1.50m
65mm dia Gatevalue
65mm dia Flangeset
65mm dia GI Nipple-0.60m
75mm dia PVC Pipe
75mm dia PVC FTA
65mm dia GI Coupling
65mm dia GI Nipple-0.15m
65mm dia GI Tee
65mm dia GI Nipple-1.80m
65mm dia GI Nipple-1.20m
RWHS & Platform
Earth work excavation in all clauses of soils with initial lead and lift except hard rock requiring blasting etc., complete for foundation as per SS 20B.
For first depth of 2m
For Core wall
Cement concrete 1:4:8 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete
Brick work in CM 1:5 mix using third class country bricks of size 8 3/4 x 4 1/4 x 2 3/4 including all cost and conveyance of materials and labour charges etc., complete
Plastering with CM 1:5 mix using to 12mm thick including all cost and conveyance of all materials and all labour charges etc., complete.
Collection and supply of 40mm HBG metal and filling in to the recharge pits including cost and conveyance to the site and all labour charges for filling as per standard specifications.
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete
GST Amount for providing Service to Government Contract Works for the above RENEWAL Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_786603.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.31 MB
BOQ_786603.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid