| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.5 LAccepted-AOC | ₹12.5 L | L1 | Accepted-AOC Bid Accepted as the Bidder Quoted Lowest Value (L1 Bidder) |
| 2 | L2₹12.6 LRejected-AOC | ₹12.6 L | L2 | Rejected-AOC Bid Rejected as the Bidder Quoted Higher Value (L2 Bidder) |
| Sl No | Description | Qty | Unit | MIRUTHI CONSTRUCTION L1 | KSS BUILDERS L2 |
|---|---|---|---|---|---|
| 1.00 | Providing Cement Concrete Pavement from Eshwaramoorthi house to Public well at Karaipudur H/O Karaipudur | 1 | nos | - | - |
| 2.00 | EARTHWORK EXCAVATION for foundation in all soils and sub soils and to full depth as may be directed except in rock requiring blasting but inclusive of shoring, strutting and baling out water wherever necessary and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc.,including levelling the sites complete complying with standard specifications and as directed. (Hard Soil ) | 41.9 | Cum | 263.5 ₹11,040.65 | 265 ₹11,103.50 |
| 3.00 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete | 63.27 | Cum | 5,308.5 ₹3.4 L | 5,310 ₹3.4 L |
| 4.00 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc | 25.65 | Cum | 6,611.5 ₹1.7 L | 6,615 ₹1.7 L |
| 5.00 | Supplying and erecting centering shuttering including necessary supports for plane etc., complete.BGL | 230.85 | Sqm | 547 ₹1.3 L | 550 ₹1.3 L |
| 6.00 | cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum. | 44.89 | Cum | 9,050 ₹4.1 L | 9,100 ₹4.1 L |
| 7.00 | Provision for tar pad for expansion joint | 14.96 | Sqm | 475 ₹7,106 | 500 ₹7,480 |
| 8.00 | Nameboard | 1 | Nos | 2,000 ₹2,000 | 4,500 ₹4,500 |
| 9.00 | Photocharges | 1 | Nos | 400 ₹400 | 500 ₹500 |
| 10.00 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | 1 | nos | 1,90,535 ₹1.9 L | 1,91,644 ₹1.9 L |
Tender Value
₹12.6 L
EMD Value
₹12,600
Closing Date
24 Feb 2026, 3:00 pmClosed
Block Develpoment officer(BP)
Panchayat Union office,Palladam
Providing Cement Concrete Pavement from Eshwaramoorthi house to Public well at Karaipudur H/O Karaipudur
2026_RDTN_661184_1
105/2026/A6
Open Tender
Civil Works
Panchayat Union office, Palladam
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹12,600
Panchayat Union office,Palladam
25 Feb 2026
20 Feb 2026
24 Feb 2026
20 Feb 2026
24 Feb 2026
20 Feb 2026
21 Feb 2026
Providing Cement Concrete Pavement from Eshwaramoorthi house to Public well at Karaipudur H/O Karaipudur
EARTHWORK EXCAVATION for foundation in all soils and sub soils and to full depth as may be directed except in rock requiring blasting but inclusive of shoring, strutting and baling out water wherever necessary and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc.,including levelling the sites complete complying with standard specifications and as directed. (Hard Soil )
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc
Supplying and erecting centering shuttering including necessary supports for plane etc., complete.BGL
cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum.
Provision for tar pad for expansion joint
Nameboard
Photocharges
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.35 MB
TBpkg1.pdf
Tender Documents • 1.13 MB
BOQ_793556.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid