Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.4 LAccepted-AOC H NO 3 1 197 P58 MYTINAGAR COLONY LB NAGAR HYDERABAD 500 074 | HYDERABAD | HYDERABAD | TELANGANA | 500074 | L1 | Accepted-AOC L1 bidder | |
| 2 | L2₹20.0 L+₹99,582.28 (5.24%)Rejected-Finance | L2 | Rejected-Finance other than L1 bidder | |
| 3 | L3₹20.1 L+₹1.1 L (5.87%)Rejected-Finance | L3 | Rejected-Finance other than L1 bidder | |
| 4 | L4₹20.3 L+₹1.3 L (6.85%)Rejected-Finance DOOR NO 43 2 BESIDES VIZAG DEFENCE ACADEMY 104 AREA KAPPARADA VISAKHAPATNAM 530013 | VISAKHAPATNAM | VISAKHAPATNAM | ANDHRA PRADESH | 530013 | L4 | Rejected-Finance other than L1 bidder | |
| 5 | L5₹20.6 L+₹1.6 L (8.66%)Rejected-Finance | L5 | Rejected-Finance other than L1 bidder |
Tender Value
₹25 L
EMD Value
₹50,000
Closing Date
17 Oct 2023, 6:00 pmClosed
CWE (ARMY) Secunderabad
Commander Works Engineers Mudfort, MES Office Complex Secunderabad-500 003
REPAIR REPLACEMENT AND MAINTENANCE OF HT CABLE TRANSFORMER VCBS AND CONNECTED ALLIED WORKS AT CDM AREA UNDER AGE EM NO 1 OF GE (U) SECUNDERABAD
2023_MES_619059_1
86260
Open Tender
Electrical and Maintenance Works
Item Rate
180 days
Secunderabad
As per NIT
7 documents required · 7 mandatory
₹500
GE (Utility) Secunderabad
₹50,000
Yes
27 Dec 2023
15 Sept 2023
24 Oct 2023
15 Sept 2023
17 Oct 2023
3 Oct 2023
Amount
Supply & Fixing in replacement of Disc insulator single disc 11 KV grade porcelain vitreous brown or green 145mm high and 255 mm dia incl taking down complete all as directed by Engr-in-Charge.
Supply & Fixing in replacement of pin type insulator 11 KV grade porcelain vitreous brown or green insulator including one galvanised iron washer and one nut 150mm high and 150 mm dia including taking out old unserviceable one complete all as directed by Engr-in-Charge.
S&Fin replacement of post top porcelain insulator vitrous brown with GI clamp nuts bolts etc suitable for 11000 Volts grade working pressure incl taking down old unsv one after disconnecting of electric supply connections and restore the supply complete all as directed by Engr-in-Charge.
M&L for Cable jointing kit for 11 KV (earthed) grade cable for outdoor end termination heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 50 to 95 Sqmm including taking out old u/s one complete all as directed
All as per item No 4.00 here- in- before but size 120 to 185 Sqmm complete all as directed.
M&L for Cable jointing kit for 11 KV (earthed) grade cable for straight through heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 50 to 95 Sqmm including taking out old u/s one complete all as directed by Engr-in-charge .
All as per item No 6 here- in- before but size 120 to 185 Sqmm complete all as directed. Note for item no 6 & 7 : Earth work shall be measured and paid separately.
M&L for Cable jointing kit for 11 KV (earthed) grade cable for indoor termination heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 50 to 95 Sqmm including taking out old u/s one complete all as directed
All as per item No 8 here- in- before but size 120 to 185 Sqmm complete all as directed. Note for item no 8 & 9 : Earth work shall be measured and paid separately.
Excavation in trenches not exceeding 1.5m wide and not exceeding 1.5m in depth and getting out in hard/ dense soil for foundation of poles, structures, stay rods, laying of underground cable etc complete all as specified & directed.
Excavation in trenches not exc. 1.5M wide and exc.1.5M & upto 3.0M tin depth for foundation of stay/ pole and etc and getting out in hard/dense soil complete all as specified and as directed by Engr-in-Charge.
Returning, filling in soils including spreading, leveling, watering and well ramming in layers each not exceeding 25cm thick complete all as directed.
Removing excavated soil to a distance not exceeding 50m and depositing where directed at a level not exceeding 1.5m above the starting point complete all as specified & directed.
Spreading earths ( after preparation of excavated earth) in Cable duct for cushioning of cable laid in trenches complete all as directed by Engineer-in-Charge Note:- Punned thickness 18 CM( 6.25 Cm below cale and 11.75 cm above cale) will be measured for payment purpose. The earth removed during excavation to be used as rddled earth after crushing and sieving. Quoted rate inclusive of all arrangement as mentioned.
M&L for laying un-reinforced precast concrete cable cover, class HV , type 1 with , size 300 mmX180mmX 40mm complete all as directed
M/L for cement concrete in foundation (1:4;8) type D2 using 40 mm graded broken stone aggregate for base of foundation complete as specified
M/L for cement concrete in foundation (1:3;6) type C2 using 40 mm graded broken stone aggregate including form work complete as specified
PCC (1:2:4) type B1 (using 20mm graded stone aggregate) as in coping including necessary formwork complete all as specified and as directed.
Supply and lay in replacement of GI tubing 100 mm dia, light grade for cable protection at road crossing / on poles and tubing sealed at both ends after laying the cables complete all as directed. Make: Tata/Jindal
Supply and lay in replacement of GI tubing 80 mm dia, light grade for cable protection at road crossing / on poles and tubing sealed at both ends after laying the cables complete all as directed. Make: Tata/Jindal
M&L for boring of horizontally holes under the road below 1.0 mtr from the road/hard surface by trenchless techonology using ultra sound technique and inclduing necessary machine without damaging the existing road and getting out in any type of soil and disposal of soil to a distance not exceeding 50m from the site of work including supply & laying HDPE pipe up to 150 mm dia suitable for 0.4 MPA work pressure . NOTE: AVERAGE WIDTH OF THE ROAD IS 20 RM. Necessary permissions required from state Govt and other Civil bodies for doing the job is the responsibility of contractor.
Supply, laying in replacement, in trenches /ducts/fixing on pole/STR with suitable size of GI clamps made out of GI strip 32 mm x 6 mm, XLPE insulated, screened, earthed, PVC bedded, galvanised steel strip, electric power cable (heavy duty) of size 3 x 95 sqmm with aluminium conductor suitable for 11 KV (E) grade as per relevent IS including latest amendment for IS (ISI marked cable) testing, commissionong along with suitable foundation complete all as specified and directed including taking out of old burnt out cable alongwith cable covers. Note:- (a) Earth work, EHV cable cover, sand coushioning & GI pipe will be measured and paid seperately. (b) High voltage test to be conducted at site with suitable voltage before and after laying of HT cable and reading shall be recorded jointly and test report to be submitted in triplicate to the Engineer-in-Charge. The cost of the same shall be deemed to be included in the unit rate quoted above.
All as item no 22.00 above but size 3 X120 Sqmm
M&L in replacement of Advance Maintenance Free G.I. SAFE EARTHING Electrode with PIPE of not less than 50 mm outer dia( THICKNESS NOT LESS THAN -2.5MM) and two meter length, The electrode should be of galvinised (80 -100 micron) along with earth lead as Galvanised steel strip of size 32 X6 mm 7.5 m . The GI Electrode shall be pre-filled with Cristaline Conductive Material (CCM) . The GI electrode shall be surrounded with 25 kg BackFill compound to provide maximum contact between the electrode and Back Fill Compound. GI Electrode Shall be tested from CPRI.The earting pit should be cover with pcc(1:2:4 , B1) cover ,of 450 x 450 mm complete incl taking down old unsv one all as specified and directed.Note: Test certificate to be submitted after completion of earthing work .
M&L for Supply, test, erection & commissioning in replacement of Steel tubalar swaged poles staying in a truely vertical position till the foundations are properly set with the help crane complete with cast iron base plate, finial taper plug, bolts, nuts & screws including drilling of holes to poles for clamps & hooks for running of earth wire/Strip complete all as specified type 410 SP-55,11 mtrs HT poles complete incl taking down old unsv one all as directed by Engr-in-Charge. Note:-(i)Crane charges for erection shall be deemed to be including in quoted rate. (ii) Earth work,PCC,coping shall be measured and paid separately. (iii) The rates include staying the poles in atruely vertical position till the foundations are properly set. (iv)The rates include cast iron base plate,nuts,bolts,screws,painting of steel tubular poles,drilling of holes in steel tubular poles for fixing of clamps,hooks for continuous earth wire/strip.
Supply, test, install & commissioning in replacement of HT 11 KV outdoor type gang operated air break switch triple pole mechanically operated suitable for horizontal or vertical mounting(suitable for existing one) on insulator and steel frame with operating mechanism worked from ground level for current rating up to 400 Amps and connecting up with jumpers, testing and commissioning including dismantling/disconnecting & taking down the old unserviceable one complete all as directed by Engr-in-Charge. Make :- VJV / SMC / ATLAS/JAIPURIA
M & L for servicing, greasing, cleaning of GOD, adjustment of its operation, cleaning and checking (for any type of damage) of insulators and lightening arresters incl. tightening of all loose nuts & bolts on the HT structure at site complete all as specified and directed by Engineer-in-Charge. NOTE :- 1. All the necessary tools, tackles and ladder shall be arranged by the contractor for the subject work. 2. Contractor has to arrange for necessary cleaning agent (petrol, diesel, CRC 2-26 etc.) and lubricating material like grease, oil and lubricating sprays if any, as required for subject work. 3. Major spares required to be replace during servicing will be measured and paid under relevant item as specified in the schedule hereforth.
M&L in replacement of fixed type top contact for DO fuse units 11 kV in replacement complete all as specified and directed.
S&F , testing and commissioning in replacement of Male contact (gunmetal) suitable for Horizontal/vertical operating type GOD 11 KV grade, 200 Amps rating in position as in replacement complete, all as specified and directed.
All as per srl item No. 29 but Female gunmetal contact.
All as per srl item No. 29 but Tinned copper flexible jumper.
All as per srl item No. 29 but MS Jumper carrier.
All as per srl item No. 29 but Back connector plate.
M&L in replacement of GI pipe of size not less 25mm dia, medium grade, as down rod levers coupling & operating handle of the existing GOD cut to suitable length including fixing up the same and commissioning of the respective GOD complete incl taking down unsv one. NOTE - The quoted rate is deemed to be inclusive of cost of threading, cutting of pipe incld. cost of nut, bolts, washers, etc. minor items required for the efficient operation of GOD.
M&L in replacement of cross arms i.e bracing supporting clamps back plates, nuts, bolts and washers complete including one under coat and one finishing coat with synthetic enamel paint over a coat of red oxide primer & including taking down old unserviceable complete all as directed.
Supplying, fixing, connecting and testing in repair/replacement of , single pole zinc oxide (gap less surge type), heavy duty, station class, self supporting outdoor type lighting arresters having rated voltage 09 KV (RMS), discharge current 10 KA insulation level 28/75 KV/KVp (peak) suitable for rated system voltage of 12 KV supply system with maximum continuous operating voltage (MCOV) not less than 7.65 KV (RMS) with highly non linear ceramic resister made of zinc oxide in dermetically sealed container, complete, with metal base, base insulator and suitable terminals for ground connections and pressure relieving arrangement complete incl taking down old unsv one all as specified and directed.
M&L in replacement of ACSR jumpers in HT/LT over head line upto 10 mm dia as that of existing size including binding wire, nuts & bolts washers complete incl taking down old unsv one all as directed.
M&L of danger notice plate of 1.6mm thick mild steel sheet vitreous enameled white, with letters, figures and convention skull and bones in signal red colour and fixed with MS clamps bolts and nuts of approved size for HT 11 KV of size 25 x 20 cm complete all as specified and conforming to IS : 2551-1982
Supplying and fixing in replacement of Tinned Copper fuse wire of 16SWG to 22 SWG or 10 Amps to 100 Amps capacity suitable for 11kV supply
M&L in replacement of ACSR conductor, steel reinforced for LT / HT over head lines on poles including streching tightining of poles insulator with binding wire of suitable size with insulator/streching of ACSR conductor including disconnecting/taking out old existing unsv ACSR conductors complete all as specified and directed.
M&L for Disconnection of all Primary/Secondary connections of the defective transformer rating up to 200kVA out door / indoor type, any make, taking down / out from plinth / pole / platform with the help of suitable crane and transporting the same carefully to workshop for repair and bringing back and test, install & commissioning in its original existing position by making all neccessary connections complete all as directed by Engr-in-Charge. Note :- Crane and Transporting Charges including in the Job.
M&L for Disconnection of all Primary/Secondary connections of the defective transformer rating above 200KVA and up to 400kVA out door / indoor type, any make, taking down / out from plinth / pole / platform with the help of suitable crane and transporting the same carefully to workshop for repair and bringing back and test,install &commissioning in its original existing position by making all neccessary connections complete all as directed by Engr-in-Charge. Note :- Crane and Transporting Charges including in the Job.
M&L for Opening top cover of transformer taking out complete oil and keeping in clean and dry container, taking out core & winding from the body,remove the sludge from tank complete and segregation of HT/LT coil from transformer including job assembling of jointing the connections pf HT/LT coil in core assembling complete insulation works, setting of core, making new connections (as per existing connections), proper alignment of job including keeping in oven chamber of as per IS Specification of respective transformer capacity for remove the moisture as well as fixing of upper yoke lamination, checking, tightening, nuts, bolts, washers and all types of gasket ( Bushing and tank) etc and welding if any leakage found in body or fins, making good dificient item if any, testing the jobs with megger for proper results including two coats of anti corrosive paint aftre cleaning inside transformer tanks and two coats of outside painting including writing KVA Capacity, repairs of body by means of welding, jointing if required complete for capacity up to 200 KVA with complete Testing and Commissioning all as directed by Engr-in-Charge.
M&L for Opening top cover of transformer taking out complete oil and keeping in clean and dry container, taking out core & winding from the body,remove the sludge from tank complete and segregation of HT/LT coil from transformer including job assembling of jointing the connections pf HT/LT coil in core assembling complete insulation works, setting of core, making new connections (as per existing connections), proper alignment of job including keeping in oven chamber of as per IS Specification of respective transformer capacity for remove the moisture as well as fixing of upper yoke lamination, checking, tightening, nuts, bolts, washers and all types of gasket ( Bushing and tank) etc and welding if any leakage found in body or fins, making good dificient item if any, testing the jobs with megger for proper results including two coats of anti corrosive paint aftre cleaning inside transformer tanks and two coats of outside painting including writing KVA Capacity, repairs of body by means of welding, jointing if required complete for capacity above 200 KVA and upto 400 KVA with complete Testing and Commissioning all as directed.
M&L in replacement of Making Primery/Secondary coil with insulating copper wire of required gauge craft paper cotton tape HT/LT insulation as per specification of old existing transformer including making of coil as required of various capacity of transformer complete all as directed
M&L for Reconditioning of over heated HT/ LT coil of transformer up to 400 KVA after removing all old insulation any type and re-insulation with insulated craft paper cotton tape Class'F' insulation as required complete all as directed
M&L for Opening of the 11 KV / 0.433 KV Distribution transformer rating up to 500 KVA by removing the inspection cover / top cover, decanning of the transformer oil up to the required level,check leaked cork seal(if any), check the un sericeable insulators & LT/HT bush (if any) complete from the shell and making connections of LT/HT bush,insulators & cork seals to avoid leakage and refilling oil back to existing postion into the transformer complete testing & commissioning complete all as directed by Engr-in-Charge. Note: Spares shall be measured and paid separately under relevant items.Necessary arrangement for repairs on timely basis at site to be madebt contractor and minor items like cork seal, insulators,bolts,nuts and washers required for arresting leakages are deemed to be included in quoted rate.
S&F in replacement of renewal of transformer/Servo Transformer bushing LT side including brass set stems conical bush/gasket for indoor/outdoor transformer incl taking down old unsv one for the following capacity :- Note : The rates quoted is deemed to be included the cost of necessary labour charges for draining out transforer oil, opening of top cover by unscrewing nut, bolts washers and and suitable size pad type bus bar almuminium and nut pach washers etc
Upto 160 KVA
200 KVA to 400 KVA
S&F following accessories of transformer in replacement of unserviceable, incl taking down old unsv one complete all as directed :-
Top cover gasket of FOR DISTRIBUTION TRANSFORMER OF 50-500 KVA any capacity as per site requirement.
Temp gauge 0-100 degree Celcius suitable for distribution transformer 11/0. 433 KVA of Capacity upto 400 kva
Porcelain transformer bushing HT 11 KV including brass set stems conical bush/ gasket for indoor/outdoor transformer upto 500 KVA as per IS-3347 complete all as specified and as directed.
LT rod / studs for any make of transformer rating up to 160KVA mounted on pole/plinth, made of brass with nut and washers, Insulator and fittings etc as per size and shape of original complete including taking down old u/s one complete all as directed.
LT rod / studs for any make of transformer rating up to 200KVA to 400 KVA mounted on pole/plinth, made of brass with nut and washers, Insulator and fittings etc as per size and shape of original complete including taking down old u/s one complete all as directed
S&F in replacement of renewal silca jel breather assembly with vent pipe for indoor/outdoor transformer incl taking down old unsv one of the follolwing capacity :-
Upto 160 KVA of Cap 250g
200 KVA to 400 KVA of Cap 500g
Replacment / Renewal of Silica gel for filling in existing air breather by removing old one
Arresting leakage of transformer fins by brazing / welding etc, after removing of oil from inside of transformer and refilling of oil by opening top cover of transformer of capacity upto 500KVA
Supply and filling in replacement of transformer oil in transformer plinth / pole mounted including testing insulation and vescocity of oil incl taking down old unsv one all as specified and directed
M&L for Dehydration including filtration cleaning of transformer oil in transformer indoor/ outdoor type by centrifusion / machine having minimum capacity 1000 to 30000 ltrs/ hrs including testing insulation and vescocity of oil before and after dehydration complete all as directed
M&L for Shifting of the any make of transformer rating up to 500 KVA mounted onplinth/pole from existing location to new location and existing transformer vice versa, including removing and reconnections of HT/LT side, jumper / cable connection, control cable connection of both transformers including testing and commission complete all as directed by Engr-in-Charge. Note:- (i) The rate quoted is deemed to be inclusive of necessary crane / vehicle charges for shifting and installation of the transformer.
Dismantling HT/LT pole of any height by taking out from PCC foundation complete and shifting to other location as directed including fixing the pole in true vertical position including excavation and earth work, PCC 1:4:8 type D2 (using 40mm graded stone aggregate) as base concrete and PCC 1:3:6 type C2 (using 20mm graded stone aggregate) in both foundation and coping of poles all as specified in SSR Part I-2009 and applying two coats of aluminium paint to pole surface complete all as directed
Inspection of defective 11kv HT cable(laid in UG/trench/tunnel/wall/surface) to locate the fault using cable fault Locator machine(by surge generators mounted on Van) (fault either by Short/Moisture/earth fault or any type) including complete all as directed
M&L for cleaning/Painting the HT poles of OH lines and HT Four poles/two poles and single pole structure complete with cross arms any height and any description thoroughly with necessary cleaning agent including scrapping up of old corroded paint dirt/dust/rust carefully and applying two coats of synthetic aluminum paint including marking and colour washing of pole coping details as are under :-
Two poles with cross Arms
Four pole with cross Arms
Single HT 11mtr Pole with cross Arms
M&L for Spray painting of upto 400 KVA transformer pole mounted / plinth mounted at site and applying two coat of synthetic enameled Smoke grey paint after removing all dust & rust and paint shall confirm to IS 2032 including marking or transformer capacity with stencil letter with black or white paint and Font and Size of letter shall be directed by Engr-in-Charge, complete all as specified and directed
Cutting anxious green growth / vegetation growth for cleaning out the area around transformer installations and four pole structure yards at ground level by cutting out roots, un wanted plants bushes and removal of the same by surface excavation not exceeding 30 cm deep average 15 cm complete.
Maintenance of earthings of installations like cleaning of earth pits, treatment of earthing by pauring salt water, replacement of perished wire mesh, unserviceable funnel and repair works like patch works to the PCC chambers and RCC cover with cement mortar 1 : 4 all as directed.
Restreching/Restringing, tightening and repair to overhead line ACSR conductor of any size on HT poles including necessary Aluminium binding wire connectors PVC sleeves for jumper, fixing of insulators and prunning of tree complete all as specified and directed. Note: 3 run of ACSR conductor is deemed to one unit.
Dismantling and taking out existing Expulsion fuse unit single pole 11 KV channel mounted complete including supply and fix for new Expulsion fuse unit single pole 11 KV, above 50 & 100 amp channel mounted complete
Cutting and trimming trees branches any girth and any size touching to overhead lines and cleaning the distance 1.5 mtr length both side of OH line with in a span of upto 50 mtrs each disposing the same, clearing the site all as directed
Cutting the existing road straight by manual, depth and width not less than 1 mtr below ground level for passing of underground cable and filling back with excavated soil upto 75% road portion and 25% shall be made with cement concrete 1:2:4 (using 20 mm graded aggregate stone complete all as specified and directed. Note: Necessary work permissions for the works to be carried in Civil/Public ares/Defence areas to be taken by the contractor prior to starting the work. Laision with concerned departments is the responsibility of contractor. Department will do the necessary authorised correspondence for the said approvals. No extra payment will be entertained on this account.
S&F cable route indicator for HT11KV UG Cable shall be made of cast iron of size 150 mm dia 8 mm thick and embossed 5mm thick arrow mark and HT 11 KV with cast iron on route indicator including angle iron of sixe 75x75x6mm thick 90 cm long shall be fix PCC 1 : 3 : 6with 20 mm aggregate concrete block below ground level of size 400x300x500 mm. The route indicator shall be welded on MS angle including Red paint over on red oxide paint and including excavation / removal and return filling and complete all as specified and directed.
Surface excavation not exc 30 cm deep and averaging 15cm deep and getting out HARD / DENSE soil
M&Lfor shingle filling in floors or pavings of Gauge 20 mm to 40mm, deposited, spread and levelled in layers not exc. 150mm thick, watered and rammed to a True Surface, complete all as specified and as directed.
Supply & Laying in replacement of Insulating mats 2.5mm thick made of Elastomer (a generic term that includes rubbers, latex and elastomeric compounds that may be natural or synthetic or a mixture or a combination of both) for use as floor covering for the protection of workers on ac and dc installations with the system voltages up to 11 kV ac and 240 V dc and as per Cl 5 of IS15652 latest Class B Cat II of Size 1m X 2m complete with Relevant Test Reports and fixing on floor with suitable adhesives complete incl taking down old unsv one all as specified and as directed Note:- The mat should be permanently pasted with the help of suitable adhesive/resin. All joints and comers shall be filled/covered wit,hinsulating material of matching colour. Matching colour and matching designed tapes should be used to maintain an aesthetic look of the installation.
Supply of Hand Glouves 11 KV ISI marked
Taking down HT switch gear (Vacuum circuit breaker ) of capacity 400 to 800 Amps, 11 KV 250 to 450 MVA comprising of following repairs, overhauling, servicing and refixing the same after repairs/ overhauling: (a) Tripping off the breaker, lowering the breaker with raising/lowering handle and pulling out the breaker complete from the panel along with the trolley for servicing/inspection/overhauling. (b) Servicing/Inspecting/checking of automatic safety shutter operation for serviceability and replacement of spares if required. (b) Servicing/Inspecting/checking of circuit spout and cicuit spout connections for RYB phases and replacement of spares if required. (c) Dismantling and checking of cross bar assembly, fixed contacts and current carrying parts of the breaker, trolley, insulated assembly and checking lamination with clamps, epoxy spout, isolator assembly etc. (d) Setting, reassembling, cleaning, adjustment of fixed contacts, main contact, arcing contacts and chamber baffle pot assembly, moving contact for proper setting of auxiliary contacts operating mechanism. (e) Servicing/Inspecting/checking of secondary sockets/busbar earthing plugs/earthing sockets and replacement of spares if required. (f) Checking, setting and adjustment of lowering and raising operation of the breaker trolley. (g) Lubrication and greasing of all moving parts of the trolley, stopper bolt for proper operating and closing of shutter gear, isolation resistance of trolley of with vacuum interrupter assembly. h) The inspection of HT switch gear shall involve:- (i) Inspection of truck & hoist assembly. (ii) Inspection of tank assembly & barriers. (iii) Inspection of assembly & components of solenoid assembly. (iv) Inspection of assembly & components of dependent mechanism. (v) Inspection of assembly & components of spring box mechanism. (vi) Inspection of motor mechanism spring charge assembly (vii) Inspection of assembly of trip unit & related components. Notes: (i) The rate quoted shall be deemed to include for necessary T&P, nuts, bolts, washers, gasket, insulation tape, compound etc. to put in to the VCBs and panels in serviceable condition, testing and commissioning all as specified and as directed by the Engineer-in-Charge. (ii) Major spares like Breaker bushings, vaccum interrupture assly, busbar spout, busbar spout connections, circuit spout/circuit spout connections/buffer fixed contacts, moving contacts, tank assly/barriers, solenoid spares, dependent/spring mechainsm/ motor mechanism, trip unit etc will be measured and paid separately under relevant items of Schedule 'A' item No.75. However the rate quoted shall be deemed to include of fixing/ replacement and taking down old unsv one of item no 75 materials
Supply only spare parts for VCB
Opening/Closing push button Assly
Spring charging motor and Gear Assly.
Limit Switch Assly including connected control wiring etc
TNC Switch
Closing Coil
Auxiliary Switch with link
Tripping Coil
Thermostat
pring return latch Assy
Vacuum interrupter Assy
Shrounds for spout Insulator
Strip heater 230V, 80 Watt
Indicating Lamps LED Type
Support insulator
Fixed contact block 400 Amp
Moving contact block 400Amp
Healthiness test of whole HT 11 KV installation such as VCB by injecting artifical HT supply complete all as directed
Supply, install, testing and commissioning in replacement of 11KV HT Voltage tranformer(PT) from existing VCB, ratio 11000/110 , HT PT Ratio 11000/110 Volts. V.F. 1.2 CONT/1.5 FOR 30 SEC STAR/STAR ,H.S.V. 12 KV RATED FREQUENCY 50HZ, RATED VOLTAGE 11 KV Class 5P 10 for protection, metering Class 1.0 Complete incl taking down old unsv one Make : Crompton Greaves or as approved by GE. Note : Contractor are advise to visit the site before quoting the rate. Ant additional/alteration required for replacement of PT is deemed to be included.
M Shyam Sunder
sree venkateswara enterprises
Mavee Syndicate
vvcenterprises
LEO ENTERPRISES
L and S ENTERPRISES
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .