| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹67.9 CrAccepted-AOC | ₹67.9 Cr | L1 | Accepted-AOC Being Lowest Bidder |
| 2 | L2₹103 CrRejected-Finance K 99 LGF KALKAJI NEW DELHI 110 019 | NEW DELHI | SOUTH EAST DELHI | DELHI | 110019 | ₹103 Cr | L2 | Rejected-Finance Being other than lowest bidder |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not approved for opening of financial bid since firm has not submitted MOU with eligible consultant |
| 4 | Rejected-Technical | - | - | Rejected-Technical Not approved for opening of financial bid since firm has not execute G plus 5 multistorey building of RCC framed construction of minimum cost of Rs 28 Crore |
Tender Value
₹73.5 Cr
EMD Value
₹15 L
Closing Date
15 Jan 2022, 6:00 pmClosed
HQ CEJZ JODHPUR
HQ CEJZ JODHPUR
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF MARRIED ACCOMMODATION (PHASE ONE (350 DUs) OF FOUR PHASES) AT JAISALMER MILITARY STATION (JOB NO S/2969)
2021_MES_466222_1
800524/JSLR/E8
Open Tender
Civil Works
912 days
JAISALMER
AS PER NOTICE OF TENDER
12 documents required · 12 mandatory
₹3,000
GE (A) (P) NO 01 JAISALMER
₹15 L
Yes
HQ CEJZ JODHPUR
14 Feb 2022
7 Aug 2021
17 Jan 2022
7 Aug 2021
15 Jan 2022
25 Dec 2021
23 Aug 2021
Amount
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF MARRIED ACCOMMODATION OF OFFICERS, JCOs & ORs, PUMP HOUSE, SUB STATIONS, UG SUMP ETC INCLUDING ALL INTERNAL AND EXTERNAL SERVICES COMPLETE AS DETAILED IN SCOPE OF WORK AND OTHER DOCUMENTS OF THE TENDER. (Phase-I to Phase-III Work)
PHASE-IV Outsourcing of services for operation and periodical maintanance during defects liability period in three shift per day including Sunday & holidays of Sewage treatment plant of capacity 270 cum per day-1 No. complete and all related equipmentS including keeping, the installation fully operational and in healthy condition by employing of 2 No. operators ( 1 x skilled Operator and 1 x semi skilled helper) per shift of 8 hours having knowledge of operation of Sewage treatment plant including their connected equipments and carrying out all daily maintanance all as directed by Engineer-in-charge and as per indian electricity rules/Engineering practice & maintaining properly the protective instruments complete in good condition and all maintanance records , break down records for JCO & ORs Qtrs all as specified in perticular specification and as directed to the entire satisfection of Engineer-in-charge.
The shift will be maintained as under:- (a) 02 operators (1 skilled and 1 semi skilled ) to be employed in each shifty of 08 hours. (i) First shift - 1400 hrs to 2200 hrs (ii) Second shift - 2200 hrs to 0600 hrs (iii)Third shift - 0600 to 1400 hrs Notes- (i)During defect liability period of 24 months , cost of rectification of defects including replacement of defective parts / spares / accessories etc shall be deemed included in the lump sump cost quoted by the contractor against item No. 1.00 of BOQ and no separate payment shall be made on this account. (ii)Cost of consumable materials, spares chemicals etc required for treatment of sewage shall also be deemed included in unit rate of this item (iii)Treated sludge shall be removed by the contractor free of cost out side the defence land and without any extra cost to Govt. No credit shall be taken for treated sludge from the contractor and contractor shall quote their rates accordingly
Outsourcing of services for operation and periodical maintanance duirng defects liability period of fully automatic electricaly operated passanger lifts 19 Nos, installed at different places of carrying various capacities as maintioned here in after including their connected equipments in two shifts per days including Sunday & holidays by deployment of 07 (seven) operators (skilled) for each shift of 8 hrs having knowldege of operaton of lift including oiling and cleaning of controller, motor, machine, oiling and greasing of guide rails and bearings, replacements of oil and minor spares like nuts , bolts, control wires and thimbals as required installed at 1 block of (Stilt+5) , 5 block of (Stilt+6) & 1 block of (Stilt+7) of JCO & ORs Qtrs
The details of passanger lifts are appended below (i) Passanger lift with Automatic Rescue device Suitable to S+6 Floors to carry 8 Passangers (544 kg)-10 Each (ii) Passanger lift with Automatic Rescue device Suitable to S+7 Floors to carry 8 Passangers (544 kg)-2 Each (iii) Passanger lift with Automatic Rescue device Suitable to S+6 Floors to carry 8 Passangers (884 kg)-5 Each (iv) Passanger lift with Automatic Rescue device Suitable to S+7 Floors to carry 8 (v) Passanger lift with Automatic Rescue device Suitable to S+5 Floors to carry 8 Passangers (884 kg)-1 EachPassangers (884 kg)-1 Each The shift will be maintained as under- (i) First shift - 0600 hrs to 1400 hrs (ii) Second shift - 1400 hrs to 2200 hrs Notes- (i)During defect liability period of 24 months , cost of rectification of defects including replacement of defective parts / spares / accessories shall be deemed included in the lump sump cost quoted by the contractor against item no. 1 of BOQ and no separate payment shall be made on this account. (ii)Cost of consumable material/Spairs etc required for operation and maintanance of lifts shall be deemed included in unit rate of this item.
PHASE-V Outsourcing of services for operation and periodical maintenance after defects liability period in three shift per day including Sunday & holidays of Sewage treatment plant capacity 270 cum per day-1 No complete and all related equipments including keeping, the installation fully operational and in healthy condition by employing of 2 No Operators (1 x skilled Operator and 1 x semi skilled helper) per shift of 8 hours having knowledge of operation of Sewage treatment plant including their connected equipments and carrying out including carried out all daily maintanance all as directed by Engineer-in-charge and as per indian electricity rules/Engineering practice & maintaining properly the protective instruments complete in good condition and all maintenance records , break down records for JCO & ORs Qtrs all as specified in particular specification and as directed to the entire satisfection of Engineer-in-charge.
The shift will be maintained as under- (a) 02 operators (1 skilled and 1 semi skilled ) to be employed in each shift of 08 hours (i) First shift - 1400 hrs to 2200 hrs (ii) Second shift - 2200 hrs to 0600 hrs (iii)Third shift - 0600 to 1400 hrs Notes- (i) This item is applicable for three year period after expiry of 24 months of defect liability period (ii)After expiry of defect liability period of 24 months , cost of rectification of defects including replacement of defective parts / spares/ accesseries shall be deemed included in the unit rate quoted for this item and no separate payment shall be made. (iii)Cost of consumable materials, spares, chemicals etc required for treatment of sewage shall also be deemed included in unit rate of this item. (iv)Treated sludge shall be removed by the contractor free of cost out side the defence land and without any extra cost to Govt. No credit shall be taken for treated sludge from the contractor and contractor shall quote their rates accordingly
Outsourcing of services for operation and periodical maintanance after defects liability period of fully automatic electricaly operated passanger lifts 19 Nos installed at different places of carrYing various capacity as mentioned here in after including their connected equipments in two shift per day including Sunday & holidays by deployment of 07 (seven) operators (skilled) for each shift of 8 hrs having knowldege of lift including oiling and cleaning of controller, motor, machine, oiling and greasing of guide rails and bearings, replacements of oil and minor spares like nuts , bolts, control wires and thimbals as required installed at 1 block of (Stilt+5) , 5 block of (Stilt+6) & 1 block of (Stilt+7) of JCO & ORs Qtrs The details of passanger lifts are appended below (i) Passanger lift with Automatic Rescue device Suitable to S+6 Floors to carry 8 Passangers (544 kg)-10 Each (ii) Passanger lift with Automatic Rescue device Suitable to S+7 Floors to carry 8 Passangers (544 kg)-2 Each (iii) Passanger lift with Automatic Rescue device Suitable to S+6 Floors to carry 8
Passangers (884 kg)-5 Each (iv) Passanger lift with Automatic Rescue device Suitable to S+7 Floors to carry 8 Passangers (884 kg)-1 Each (v) Passanger lift with Automatic Rescue device Suitable to S+5 Floors to carry 8 Passangers (884 kg)-1 Each The shift will be maintained as under- (i) First shift - 0600 hrs to 1400 hrs (ii) Second shift - 1400 hrs to 2200 hrs Notes-(i)After expiry of defect liability period of 24 months , cost of rectification of defects including replacement of defective parts / spairs accessories etc shall be deemed included in the unit rate quoted for this item and no separate payment shall be made. (ii)Cost of consumable materials/Spares etc required for operation and maintanance of lifts shall be deemed included in unit rate quoted for this item.
Common Notes for Srl item No. 2 to 5 1. Wages paid by the contractor to the persons employed shall not be less than the minimum wages fixed by State/Central Government from time to time which ever is higher (Issued by GOI from time to time). The payment shall be made to the workers through online banking and the bank statement of wages as per minimum labour wages as mentioned above shall be submitted along with the RARs/FB for payments. 2. The contractors shall be responsible for the EPF, ESI, bonus,LWS, Safety of operator etc. and insurance of all tradesman employed by him as per existing Labour Rules /Act/Regulations. 3. Contractor's special attention is invited that payment of operators / lobours shall be made only online banking and same shall be deposited in Aadhar linked bank account of operators / labours and documentry evidence for the same shall be submitted to the Engineer-in-charge at the time of claimiming payment of RARS/Final bill. 4. Contractor and his personals detailed for management and operation of entire installation shall be responsible for serviceability of plants, lifts and all equipments. In case of any major fault occurs in above equipments/installations, he will report directly to concerned JE E/M / AGE E/M. Person deputed for operation will also responsible for minor maintenance such as checking of STP, lift room and cleaning of plant room, equipments and surrounding areas complete. However for major defects contractor shall arrange the mechanical of OEM for rectifications of defects occured in the STP/Lifts and cost thereof shall be paid by the contractors at his own end. 5. Necessary weekely off will be given to each manpower employed as per existing rules and regulation of state/central govt and necessary replacement will be provided by the contractor. Rates quoted shall deemed to be included this provision.
6. In case of absence of operator / workman from any shift shall br penalized with a panelty of Rs 2000 per operator per shift for absent period however leave will get it sanctioned before proceeding on leave along with the name of indivisuals who will be performed his duty in his absence. No replacement of operator / workmen without the knowledge of department will be allowed. No operator/labour will be employed for more than 11 month continuous period. 7. Safety equipment's, tools first aid kit and uniform will be provided by the contractor to all tradesman without any extra cost to government. 8. Log book (sheet), Muster roll, duty roster,fuel consumption register, daily breakdown register, attendance register and other requisite registers shall be maintained by operator and get it signed by concerned JE, Engineer-in-charge and contractor on daily basis and same shall be submitted monthly to GE for inspection and other details as specified in particular specification. The unit rate quoted by the contractor for these items shall be deemed included this provisioned. 9. Operator's having minimum 02 years experience for running of STP/Lifts and well conversant with the equipments shall be engaged. The attested experience certificate shall be submitted to GE at the time of commencement of work. Contractor has to provide proper uniform and safety shoes with proper name of operator encrypted in his shirt of operator without any extra cost to the department. 10. The GST and other liabilities are deemed included in the rates quoted against all items.
11.It is sole responsibility of contractor if any mishappening occurs including accident/injury due to any reason, department shall not be held responsibe on this account. Nothing extra shall be admissible on this account from the department. 12. Electricity for operation of STP/Lifts shall be provided by the MES free of cost 13. Before deploying man power contractor has to provide the particular's of each indivisual for approval of GE and after approval, Police Verification of each man power shall be got carried out. Police Verification Certificate of all indivisual's / man power shall be submitted by the contractors for issuing security purposes by the station authority.
SOOD ASSOCIATES PVT LTD
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB