Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹26.0 L
EMD Value
₹52,000
Closing Date
19 Nov 2026, 4:30 pm5d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
DGM, Contract and Procurement
Admin Building, Indira Sagar Power Station, Narmada Nagar, Distt. Khandwa, Pin code 450119
Construction of parking shed at H-type residential quarters of Indira Sagar Power Station, Narmada Nagar, Distt. Khandwa (MP).
2026_NHDC_932223_1
NIT NO. 17/6118/2026-27 Dated 28/10/2026
Open Tender
Civil Works
Percentage
120 days
Indira Sagar Power Station, Narmada Nagar, Khandwa
As per tender documents
3 documents required · 3 mandatory
₹590
NHDC Limited
₹52,000
Yes
29 Oct 2026
29 Oct 2026
23 Nov 2026
29 Oct 2026
19 Nov 2026
29 Oct 2026
29 Oct 2026 - 12 Nov 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including dressing of sides and ramming of bottom disposal of excavated earth, lead up to 50m and lift up to 1.5m, disposed earth to be levelled and neatly dressed. (No extra lift is payable if work is done by mechanical means) All kinds of soil | 95.04 | Cum | 175.19 | ₹16,650.06 |
| - | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work upto plinth level : With 20mm nominal size graded stone aggregate. M-10 Nominal (Mix-1 Cement : 3 sand : 6 graded stone aggregate ) | 45.42 | Cum | 4,636.1 | ₹2,10,571.66 |
| - | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding including cost of binding wire all wastages and overlaps, couplers (overlaps shall be provided as per requirement of IS 13920 for ductile detaling IS-456 RCC Design & SP 34 Reinforcement detailing ) etc. complete .
(Note:-
1. Spacer bars (chairs) shall be paid separately as shown in the drawing and as per direction of engineer in charge.
2. No extra payment shall be done for overlaps and/or couplers.
3. Couplers shall be conforming to IS code on “Reinforcement Couplers for Mechanical Splices of Bars for Concrete Reinforcement - Specification”) Thermo-Mechanically Treated bars. FE 500 conforming to IS 1786 | 1,674.39 | Kg | 91.77 | ₹1,53,658.77 |
| - | Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns, etc. for concrete upto plinth level | 34.56 | Sqm | 227.16 | ₹7,850.65 |
| - | Centering and shuttering in cluding strutting, propping etc. and removal of form for: Columns, Pillars , Piers, Abutments, Posts and Struts. | 64 | Sqm | 561.57 | ₹35,940.48 |
| - | Providing and laying in position specified grade of reinforced cement concrete (with 20mm nominal size graded stone aggregate) excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : M-20 Grade Concrete | 27.95 | Cum | 7,333.15 | ₹2,04,961.54 |
| - | Filling available excavated earth (excluding hard rock/Ordinary rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 71.02 | Cum | 113.22 | ₹8,040.88 |
| - | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work upto plinth level : M-15 – Grade concrete | 50.4 | Cum | 5,328.54 | ₹2,68,558.42 |
| - | Structural steel work built up sections Structural steel work using M.S. flats, angles, channels I-section, H-section etc. riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 3,366.66 | kg | 122.76 | ₹4,13,291.18 |
| - | Steel work in built up M.S. tubular section (round, square or rectangular hollow tubes etc.) trusses/frame work etc. including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes | 5,552.02 | kg | 139.44 | ₹7,74,173.67 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.60 MB
BOQ_979640.xls
BOQ • 0.24 MB
17Tender6118.pdf
Tender Documents • 13.70 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .