Loading…
Loading…
Tender Value
₹39.1 L
EMD Value
₹39,500
Closing Date
10 Aug 2026, 3:00 pm
Zonal office 9
Greater Chennai Corporation, Zone-9, Nungambakkam, Chennai -600034
Formation of New Park at Choolaimedu High Road SUBEDAR GARDEN (Housing Board) OSR Land in Dn-112, Unit-26, Zone-9
2026_CoC_687102_1
Z.O.IX.C.No.E1/1153/2026
Open Tender
Civil Works
Works
270 days
chennai
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹39,500
21 Jul 2026
21 Jul 2026
11 Aug 2026
21 Jul 2026
10 Aug 2026
21 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Installation of Vertical Bored cast in situ RCC piles of following diameter in all types of soils, using Standardised Concrete Mix of following grade, with sulphate resistant Cement or OPC/PPC, etc and Crushed Stone Sand and 20mm and down graded HBGS jelly coarse aggregate. The rate includes cost for placing of reinforcement cage in bore hole in correct position, cost of boring to the required depth with Bentonite solution with temprory casing of required length, conveyance of RMC to site and pouring concrete using Tremine pipes, conveyance of all materials to the site including all tools and plants, shifting the plants and equipments from one point to another, excavtion of mud pits for circulation of Bentonite soultion, closing the mud pits to original level and mud removal with initial lead and lift but including dismantling the concrete above the cut off level etc complete as directed by the departmental officers including socketing. The reinforcement cage should be welded properly for lifting. The concrete cubes to be tested as per IS 456- 2000. Acceptance criteria by clause
16.1. Frequency of testing as per 15.2.2. Testing to be conducted at both the ends at site as well as RMC plant. Pile driving depth should be decided by the departmental officers at site. The length of pile for payment shall be measured from top of shoe to the bottom of the pile cap.( Cost of Reinforcement provided for Pile and Welding charges shall be measured and Paid separately ) Grade of Concrete: M25
300 mm dia pile | - | R/M | 1,564.54 | - |
| 2 | Earth work excavation for foundation by Mechanical means for Isolated & Combined Footing etc in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sides and raming of bottoms etc., complete complying with standard specification and as directed by the departmental officers.- Upto 2.40m Footing Depth. (including Refilling charges) | - | CUM | 368.55 | - |
| 3 | Supplying and filling in foundation, basement, etc with filling crushed stone dust (Quarry dust) in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. | - | CUM | 391.95 | - |
| 4 | Plain Cement Concrete 1:2:4 (one cement, two crushed stone sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.-Mixing by mechanical means | - | CUM | 7,255.21 | - |
| 5 | Supplying, fabricating and placing in position Ribbed Tor Steel / TMT reinforcement grills of all variety like HYSD/CTD/TMTand all grade like Fe 500, Fe550D, Fe 500 D etc., for all RCC works as per design given including cost of steel reinforcement and G.I. binding wire, wastage etc. complete complying with standard specification and as directed by the departmental officers.(Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire) Above plinth / Basement level | - | KGS | 98.7 | - |
| 6 | Supplying and erecting centering for plane surfaces such as RCC Floor/Roof Beam, Lintels, Cantilever Beams, Bed Blocks etc.. with necessary supports and strutting upto 3.60m height in all floors with all cross bracings using MS Sheets made of 10 gauge thick welded with MS angle of Size 25mm x 25mm x 3mm for boarding laid over Steel adjustable Span of Size 2m x 2m(expandable upto 3.60m) and Silver Oak Joists of Size 10 x 5 cm spaced at 50cm to 60cm c/c and supported by Steel Adjustable Telescopic Props of Size 2m x 2m (expandable upto 3.60m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick) Spaced at not more than 50 to 60cm c/c , etc complete complying with standard specifications. Steel adjustable span and Steel Adjustable telescopic props shall be provided as directed by the departmental Officers. (Payment for centering shall be given after the concrete is laid).BEAM | - | SQM | 1,178.29 | - |
| 7 | Providing and laying in position, Standardised Concrete Mix M-25 Grade using In-situ Concrete batching plant/ Ready Mix Concrete (RMC) adopting weigh batch method in accordance with IS:456-2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement content of 350 kg/m3 and maximum water cement ratio of 0.50, including admixture (plasticiser / superplasticiser) in recommended proportions as per IS:9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability with about (5.0 Cu.m) 7730 kg. of 20mm machine crushed stone jelly and with about (3.3 Cu.m) 5156 kg. of 10-12mm machine crushed stone jelly and with about (4.79 cu.m’) 7670 kg. of crushed stone sand, but excluding cost of reinforcement grill and fabricating charges, centering and shuttering and also including Conveyance of concrete from batching plant to Work site, Electricity charges and other works & labour cost involved for concrete production, laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor/ roof slabs wherever necessary without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers. The coarse and fine aggregates to be used should comply with the requirements of IS Standards. (No separate payment will be made by the Department for the excess usage of materials). | - | CUM | 8,197.92 | - |
| 8 | Brick work in following Cement Mortar using best quality Burnt Clay Brick of size 9” x 4 3/8” x 2 3/4” with class designation of 10 conforming to IS 1077-1992 for foundation and basement including Cost of Mortar Plasticizer curing, etc.,complete complying with standard specification and as directed by the departmental officers.
Brickwork shall be done as per IS 2212-1991 adopting English Bond generally.other type of bond shall be done as directed by the Executive Engineer in charge. In Cement Morter 1:3 | - | CUM | 8,192.9 | - |
| 9 | Plastering the surface of walls with Cement Mortar 1:4 (One cement and Four plastering sand), 12mm thick in all floors including mortar plasticizer at 200ml per 50Kg of cement used, curing etc., complete complying with standard specification and as directed by the departmental officers. (Wall) | - | SQM | 317.59 | - |
| 10 | Painting New Plastered Wall Surface with Two finishing coats of ready mixed (Emulsion) of approved quality and colour over one coat priming coat in all floors including the cost of primer etc., complete complying with standard specification and as directed by the departmental officers.(The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) | - | SQM | 201.05 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.48 MB
1153TBOOK.pdf
Tender Documents • 1.80 MB
BOQ_826161.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].