| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.3 CrAccepted-AOC 11 OLD POST OFFICE STREET IST FLOOR LEFT SIDE KOLKATA 700001 STATE WEST BENGAL | KOLKATA | WEST BENGAL | 700001 | ₹3.3 Cr | L1 | Accepted-AOC L1 Bidder |
| 2 | L2₹4.3 Cr+₹1.1 Cr (33.0%)Rejected-Finance | ₹4.3 Cr+₹1.1 Cr (33.0%) | L2 | Rejected-Finance L2 Bidder |
| 3 | L3₹4.5 Cr+₹1.3 Cr (38.7%)Rejected-Finance | ₹4.5 Cr+₹1.3 Cr (38.7%) | L3 | Rejected-Finance L3 Bidder |
| 4 | Rejected-Technical | - | - | Rejected-Technical Technically non-responsive |
Tender Value
₹5.6 Cr
EMD Value
₹11.3 L
Closing Date
2 Apr 2026, 4:00 pmClosed
Ashok Kumar Saha
NHIDCL, RO-Gangtok
Short Term Maintenance Contract (STMC) on NH-10 for the section from km 64 Singtam Bridge to km 80 Indian Oil Fuel Station Ranipool under the jurisdiction of PMU-Ranipool, NHIDCL on Percentage Rate Contract Basis for FY 2026-27 in the state of Sikkim
2026_NHIDC_902259_1
NHIDCL/NH-10/MR/PKG-II/2026-27
Open Tender
Civil Works
Percentage
365 days
Singtam to Ranipool
Please refer Tender documents.
4 documents required · 4 mandatory
₹11,800
NHIDCL
₹11.3 L
NHIDCL, RO-Gangtok
9 Jun 2026
12 Mar 2026
4 Apr 2026
12 Mar 2026
2 Apr 2026
23 Mar 2026
13 Mar 2026 - 19 Mar 2026
20 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1VEGETATION CLEARANCE | |||||
| 1.01 | Clearing road side vegetation
(brush wood mooli bamboos, overgrown grass including removal etc. along existing road side, and disposal of the cut bushes down hill side of the road formation. This jungle clearance should include minimum height of clearance of 4.5m from top of pavement on uphill side of the road including road shoulder and all the bushes on the shoulder and down hillside of the road
C.) MDRs, SHs, NHs, etc | - | KM | 8,089 | - |
| 2DRAIN CLEARANCE | |||||
| 2.01 | Hill side Drain Clearance
(Removal of earth from the choked hill side drain and disposing it on the valley side manually) | - | RM | 57 | - |
| 2.02 | Mazdoor
Considering 5 Labours per Day during Monsoon i.e., in the month of May, June, July & August in the year 2025-26 for clearance of Choked Drains, Channelising Storm Water and other Ancillary Works.
Considering 3 Labours during Dry Season in the month of March, April, September, October, November & December in the year 2025 and January, February in the year 2026 for keeping the carriageway dust free, clearance of Choked Drains and other Ancillary Work. | - | Man Day | 436 | - |
| 3LANDSLIDE CLEARANCE Providing and supplying followings equipments including driver, labour, loading/unloading arrangements, fuel lubricants and attachment for maintenance work when required as per the instruction of the Engineer. | |||||
| 3.01 | Hydraulic Excavator of 1 Cum bucket and rock breaker attachment | - | Hour | 1,438.31 | - |
| 3.02 | Front End Loader 1 Cum bucket Capacity | - | Hour | 931.22 | - |
| 3.03 | Tipper-5Cum | - | Hour | 478.38 | - |
| 4GABIAN WORKS (Length = 220m ; Height = 5m) | |||||
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.43 MB
BOQ_948353.xls
BOQ • 0.37 MB
RFP.pdf
Tender Documents • 1.01 MB
corrigendum_1.pdf
PDF • 0.08 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .