Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹56.7 LAccepted-AOC KARAIKAL 609602 | KARAIKAL | PUDUCHERRY | 609602 | L1 | Accepted-AOC L1 lowest tendere awarded contractor | |
| 2 | L2₹61.9 L+₹5.2 L (9.17%)Rejected-Finance | L2 | Rejected-Finance L2 Rejected |
Tender Value
₹54.2 L
EMD Value
₹1.1 L
Closing Date
22 Jan 2024, 10:30 amClosed
The Executive Engineer
The Executive Engineer PADSTDC
Improvements to the approach road to the kaliamman kovil pet, internal streets and cremation yard road at Subrayapuram in Thirunallar Constituency, Karaikal.
2024_PADCO_14716_1
104/PADSTDC/EW/23-24
Open Tender
Civil Works
Item Rate
180 days
PADSTDC Thattanchavady
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,050
Yes
₹1.1 L
Yes
20 Jun 2024
9 Jan 2024
22 Jan 2024
9 Jan 2024
22 Jan 2024
9 Jan 2024
Amount
Code No.3.15:- Scarifying the existing bituminous surfaceto a depth of 50mm and disposal of scarified material within all lifts and lead upto 1000 metres - by mechanical means.
Code No2.27A.1 :- Supplying and filling with gravel (excluding rock) in trenches , plinth, sides of foundations etc . In layers not exceeding 20 cm in depth consolidating each deposited layers by ramming and watering etc .complete including all lead and lift
Code No.4.12B.1:- Providing,laying ,spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site , laying in uniform layer by manual means in sub-base / base course on well prepared surface and compacting with smooth 3 wheeled steel roller to achieve the desired density
Code No.4.91B :- Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth three wheeled steel roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite Crushable type such as moorum / gravel for screening and gravel for binding to fill up the interstices of coarse aggregate, watering and compacting to the required density - by manual means - Water bound macadam Gr-I with Gravel screening. (As per MoRTH specification, 4th Revision)
Code No.4.92C: Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth 3 wheeld steel roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite Crushable type such as moorum or gravel for screening and gravel for binding to fill up the interstices of coarse aggregate, watering and compacting to the required density - by manual means - Water bound macadam Gr-II with moorum or gravel screening. (As per MoRTH specification, 4th Revision)
Code No.5.1 :- Providing and applying primer coat with bitumen emulsion on prepared surface of granular base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means. (As per MoRTH specification, 4th Revision)
Code No.5.2: Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg. per sqm. on the prepared bituminous / granular surface cleaned with mechanical broom. (As per MoRTH specification, 4th Revision)
Code No 5.3A:-Providing and laying bituminous macadam with hot mix plant of capacity not less than 40 to 60 TPH using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade,level and alignment and rolled as per clauses 501.6 and 507.7 of MoRTH specification, 4th Revision, to achieve the desired compaction.- Using grade I metal and bitumen 60/70 grade.
Code No.5.7A: Providing and laying semi-dense bituminous concrete with HMP of capacity not less than 40 - 60 TPH using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment,rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per clause 508 of MoRTH specification, 4th Revision, complete in all respects - Using grade-I material and bitumen 60/70 grade.
Code No.2.8.1 :-Earthwork in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed , within a lead of 50m - all kinds of soil.
Code No.4.1.8:- Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
Code No.4.1.3:- Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Code No.4.3.1 :- Centring and shuttering including strutting , propping etc. and removal of form work for - foundations, footings, bases for columns.
SAKTHI ENGINEERING CONSTRUCTION
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .