| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.7 LAccepted-Finance 23 11 93 DUTTAPARA ROAD P O HALISAHAR NORTH 24 PARGANAS | HALISAHAR | NORTH 24 PARGANAS | WEST BENGAL | 743134 | ₹2.7 L | L1 | Accepted-Finance 1st lowest bidder |
| 2 | L2₹2.8 L+₹5,718 (2.12%)Rejected-Finance | ₹2.8 L+₹5,718 (2.12%) | L2 | Rejected-Finance 2nd lowest bidder |
| 3 | L3₹2.8 L+₹11,329 (4.20%)Rejected-Finance | ₹2.8 L+₹11,329 (4.20%) | L3 | Rejected-Finance 3rd lowest bidder |
Tender Value
₹2.7 L
EMD Value
₹5,400
Closing Date
19 Sept 2026, 11:00 amClosed
EE(BR V)
22 SURYA SEN STREET KOL-12
REPAIRING AND RESTORATION OF CONCRETE ROAD SURFACE AT 3 PORTUGUESE CHURCH ST, SURROUNDING AREAS AND OTHER DIFFERENT PLACES IN WARD NO- 042
2026_KMC_1041085_1
KMC/EE(C)/Br-V/042/01/26-27
Open Tender
CIVIL WORKS
Percentage
45 days
WARD-42
Please refer Tender documents.
7 documents required · 7 mandatory
₹0
₹5,400
21 Sept 2026
9 Sept 2026
21 Sept 2026
9 Sept 2026
19 Sept 2026
9 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. b) flat channel stone. | 100.5 | MTR | 8.17 | ₹821.09 |
| 2 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 2. Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m In ground floor including roof. (a) upto 150 mm. thick | 10.48 | M3 | 939 | ₹9,840.72 |
| 3 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. a) vertical kerb stone. | 55.5 | MTR | 8.17 | ₹453.44 |
| 4 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). b) flat channel stone. | 100.5 | MTR | 18.24 | ₹1,833.12 |
| 5 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). a) Vertical Kerb | 55.5 | MTR | 21.34 | ₹1,184.37 |
| 6 | Raising gully pit cover and frame with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster with neat cement after dismantiling the existing setting and taking out and refixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. ( Ref :Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6)and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13)) | 8 | EA | 1,856.28 | ₹14,850.24 |
| 7 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. | 16.08 | %M3 | 119.27 | ₹1,917.86 |
| 8 | Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation. (a) 1:3:6 proportion | 7.96 | M3 | 4,572 | ₹36,393.12 |
| 9 | MATERIALS AND LABOUR 1. Building (B) Labour Rates Per Diem : 3)Mazdoor (Male). Note: (I)The above rates of labour are exclusive of 10% contractors profit and 1% Labour welfare cess which would be admissible to the Contractors, but contractual percentage will not be applicable. (II) The workersemployed on high rise building or any structure over 30 ft in height and also workers engaged in Tunnel shall be paid 20% extra wages. | 26 | EA | 245 | ₹6,370 |
| 10 | BUILDING WORKS(D) Flooring..A. ORIGINAL WORKS..(3)Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. | 53.6 | SQM | 24 | ₹1,286.4 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.22 MB
Tendernotice_2.pdf
PDF • 0.21 MB
Tendernotice_3.pdf
PDF • 0.83 MB
Tendernotice_4.pdf
PDF • 0.82 MB
BOQ_2556525.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .