Tender Value
₹15.1 L
EMD Value
₹18,900
Closing Date
22 Sept 2026, 5:00 pm
GM CV AREA
OFFICE OF GENERAL MANAGER CV AREA-XII
Dismantling of Chimney, Fan House at Laikdih under C.V. Area
2026_BCCL_365113_1
BCCL/XII/ACE/ e-Tender-51/2026-27/51 Dated-07.09.2026
Open Tender
Civil Works - Buildings
Percentage
90 days
CV Area
Please refer to the tender documents.
4 documents required · 4 mandatory
₹18,900
11 Sept 2026
11 Sept 2026
23 Sept 2026
11 Sept 2026
22 Sept 2026
12 Sept 2026
11 Sept 2026 - 15 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | DISMANTLING AND DEMOLISHING Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | 28.72 | CUM | 2,126.1 | ₹61,059.47 |
| 2 | DISMANTLING AND DEMOLISHING Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 150 mm dia pipe | 21 | METRE | 48.05 | ₹1,009.05 |
| 3 | REPAIRS TO BUILDING Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. | 1,130.4 | SQM | 226.05 | ₹2,55,526.92 |
| 4 | 1.1.1 Carriage of materials by mechanical transport including loading, unloading and stacking Lime, Moorum, Building Rubbish | 259.88 | CUM | 261.35 | ₹67,918.33 |
| 5 | DISMANTLING AND DEMOLISHING Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar | 392.73 | CUM | 1,232.8 | ₹4,84,160.01 |
| 6 | DISMANTLING AND DEMOLISHING Extra for cutting reinforcement bars manually/ by mechanical means in R.C.C. or R.B. work (Payment shall be made on the cross sectional area of R.C.C. or R.B. work) as per direction of Engineer-in-charge. | 169 | SQM | 758.8 | ₹1,28,237.2 |
| 7 | DISMANTLING AND DEMOLISHING Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work. | 13,520 | KG | 5.8 | ₹78,416 |
| 8 | DISMANTLING AND DEMOLISHING Dismantling steel work manually/ by mechanical means in built up sections without dismembering and stacking within 50 metres lead as per direction of Engineer-in-charge. | 1,600 | KG | 2.35 | ₹3,760 |
| 9 | CLEARING OF JUNGLE | 4,506.1 | SQM | 7.75 | ₹34,922.28 |
| 10 | EARTH WORK Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m. All kinds of soil | 1,800.75 | SQM | 20.4 | ₹36,735.3 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 2.37 MB
BOQ_378098.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .