| 1 | L1₹2.6 CrAccepted-AOC AT TITIA P O P S KHUNTA DIST MAYURBHANJ 757019 | MAYURBHANJ | ODISHA | 757019 | ₹2.6 Cr | L1 | Accepted-AOC aoc |
| 2 | L2₹2.8 Cr+₹13.5 L (5.10%)Rejected-Finance | ₹2.8 Cr+₹13.5 L (5.10%) | L2 | Rejected-Finance Loss through opening of the Financial Bid (Cover-II) |
| 3 | Rejected-Technical | - | - | Rejected-Technical As per DTCN |
| 4 | Rejected-Technical AT NIWARAPUR PO DORANDA PS CHUTIA DIST RANCHI JHARKHAND PIN 834002 | RANCHI | RANCHI | JHARKHAND | 834002 | - | - | Rejected-Technical As per DTCN |
| 5 | Rejected-Technical | - | - | Rejected-Technical As per DTCN |
Tender Value
₹3.4 Cr
EMD Value
₹3.4 L
Closing Date
26 Mar 2026, 5:00 pmClosed
CCE, Eastern (R and B) Circle, Balasore
O/o CCE, Eastern (R and B) Circle, Balasore
Building
2026_EICCL_127182_3
CCEEC-21/2025-26
National Competitive Bid
Civil Works - Buildings
Percentage
180 days
Mayurbhanj
Please refer Tender documents.
4 documents required · 4 mandatory
₹10,000
₹3.4 L
Yes
18 Aug 2026
12 Mar 2026
30 Mar 2026
12 Mar 2026
26 Mar 2026
12 Mar 2026
12 Mar 2026 - 26 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | CIVIL WORK Dismantling and removing 2.5 cmthick grading concrete from roofslab cleaning the surface loweringand removing the debris within 50m | 2,312.23 | Sqm | 128.54 | ₹2,97,214.04 |
| 2 | Removing old lime or cementplaster from walls including rakingout joints 12 mm deep andremoving the debris within 50mlead | 504.13 | Sqm | 57.13 | ₹28,800.95 |
| 3 | Dismantling and removing doors, windows and ventilators including removal of frame, hinges, fastening and stacking the for reuse and removing the debris within 50m lead | 96.72 | Sqm | 455.75 | ₹44,080.14 |
| 4 | Dismantling G.C.I. or A.C. sheet roofing after carefully removing the bolts and nuts including stacking of he materials for reuse and removing the debris within 50m lead | 648.43 | Sqm | 104.1 | ₹67,501.56 |
| 5 | Dismantling brickwork, stone nasonry in Cement mortar above 3meter height including stacking the useful material for reuse and removing the debris within 50 meter lead. | 372.07 | Cum | 1,706.54 | ₹6,34,952.34 |
| 6 | Dismentaling & removing R.C.C columns beams, slab, staircase, landing, lintels, including stacking the useful materials for the reuse and removing the debries within 50 m lead. | 117.22 | Cum | 1,696.95 | ₹1,98,916.48 |
| 7 | Earth Work in exavation of foundation in hard soil within initial leads of 50m & lifts of 1.5m including dressing and levelling of bed etc. and adding contractor's profit and over head charges, etc. complete in all respect. | 1,779.02 | Cum | 276.88 | ₹4,92,575.06 |
| 8 | Supplying, & filling in foundation and plinth with good quality river sand including watering, ramming with cost, conveyance, royalties, , of all materials and cost of all labour with T&P, sundries required for the work etc., complete (Measurement will be taken on finished compacted section) as per specification and direction of Engineer-in-charge. | 955.85 | Cum | 1,172.2 | ₹11,20,447.37 |
| 9 | Cement concrete of proportion (1:3:6) in foundation and floors using 4cm size black broken granite stone aggregates of approved quality and from approved quarry including hoisting, lowering and laying concrete in layers not exceeding 15cm(6") thick to the required level ramming, watering, curing etc. complete including cost and conveyance royality taxes of all materials and labour with T&P required for the work etc. complete i as per direction of the Engineer-in-charge. | 215.71 | Cum | 7,522.88 | ₹16,22,760.44 |
| 10 | Brick work with Flyash Bricks 25cm x 12cm x 8cm size having crushing strength not less than 75Kg/cm2 with dimensional tolerance ±2 percent in cement mortar (1:6) in Foundation and Plinth including watering curing, cost of carriage, royalty and taxes of all materials, cost of all labour, etc complete as per the direction of E.I.C. | 159.19 | Cum | 5,671.25 | ₹9,02,806.29 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.01 MB
dtcn3.pdf
Tender Documents • 1.91 MB
BOQ_584856.xls
BOQ • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .