| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC PALANI MADURAI | DINDIGUL | TAMIL NADU | 624001 | ₹1.2 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.2 CrRejected-AOC | ₹1.2 Cr | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | TNK Construction L1 | S VELLAICHAMY CONTRACTOR L2 |
|---|---|---|---|---|---|
| 1.00Strengthening the road from Nilavarapatty TS Salai 208/8 to Thalaimalaikaradu Via Jarugumalai Km 0/0 - 1/100 H/o Nilavarapatti | |||||
| 2.00 | Clearing the Scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by the departmental officers including all incidental charges etc., complete. | 1,315.8 | Sqm | 6 ₹7,894.80 | 9 ₹11,842.20 |
| 3.00 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m | 2,014.23 | Cum | 22 ₹44,313.06 | 25 ₹50,355.75 |
| 4.00 | Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay concrete pavement per SS 20 A. | 502.57 | Cum | 140.45 ₹70,585.96 | 145 ₹72,872.65 |
| 5.00 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS | 531.67 | Cum | 341.07 ₹1.8 L | 345 ₹1.8 L |
| 6.00Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | |||||
| 7.00 | KM 0/0-1/1 | 889.48 | Cum | 2,431.44 ₹21.6 L | 2,435 ₹21.7 L |
| 8.00Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | |||||
| 9.00 | KM 0/0-1/1 | 5,569.85 | sqm | 86.48 ₹4.8 L | 90 ₹5.0 L |
| 10.00Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | |||||
Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
20 Feb 2026, 3:00 pmClosed
Joint Director/Project Director
DRDA,Salem
Salem District - Panamarathupatti Block - Strengthening and Five Year Maintenance of Nilavarapatty TS Salai 208/8 to Thalaiamalai karadu Via Jarugumalai in NABARD - RIDF- 2026-2027 Package No.15
2026_RDTN_656804_18
Roc.No.875/2026/A3
Open Tender
Civil Works - Roads
180 days
DRDA
As per tender document
3 documents required · 3 mandatory
₹0
₹1.3 L
DRDA,Salem
29 May 2026
14 Feb 2026
20 Feb 2026
14 Feb 2026
20 Feb 2026
14 Feb 2026
16 Feb 2026
Strengthening the road from Nilavarapatty TS Salai 208/8 to Thalaimalaikaradu Via Jarugumalai Km 0/0 - 1/100 H/o Nilavarapatti
Clearing the Scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by the departmental officers including all incidental charges etc., complete.
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay concrete pavement per SS 20 A.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 34.04 Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5
BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Provision for Kilo Metre Stone - Nos
Provision for HectaMetre Stone - Nos
Provision for 3.00m Span RCC Slab Culvert Ch 80m
Dismantling Clearing away and carefully Stacking materials useful for reuse for any tk of wall stone masonry in cm walls under 3m high
Dismantling Clearing away and carefully Stacking materials useful for reuse for any tk of wall removal of cut stone slabs/RCC Cover Slabs
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay concrete pavement per SS 20 A.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc..
Below Ground Level
Slab Bottom
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works..etc…,
PlainCement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum
provision for Bitumen Pad
provision for Weep holes
Provision for 1.50m Span RCC Slab Culvert Ch 456m
Dismantling Clearing away and carefully Stacking materials useful for reuse for any tk of wall stone masonry in cm walls under 3m high
Dismantling Clearing away and carefully Stacking materials useful for reuse for any tk of wall removal of cut stone slabs/RCC Cover Slabs
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay concrete pavement per SS 20 A.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc..
Below Ground Level
Slab Bottom
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works..etc…,
PlainCement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum
provision for Bitumen Pad
provision for Weep holes
CC Pavement and Drain Ch 0m to164m
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay concrete pavement per SS 20B.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc..
Below
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse an
provision for Bitumen Pad
Provision for Protection wall Km 0/0 - 1/0
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc..
provision for Weep holes
Provision for Cautionary Sign board charges (60cm equilateral triangle)
Reflector
Towards the charges for routline maintenance of the road work executed under NABARD including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost for carriageway width of 3.00m & 3.75m
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.15 MB
15.pdf
Tender Documents • 1.47 MB
BOQ_788517.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid