| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹26.9 LAdmitted-Finance | -27.33% | ₹26.9 L | L1 | Admitted-Finance |
| 2 | L2₹27.7 L+₹82,467.51 (3.07%)Admitted-Finance | -25.10% | ₹27.7 L+₹82,467.51 (3.07%) | L2 | Admitted-Finance |
| 3 | L3₹29.9 L+₹3.0 L (11.2%)Admitted-Finance | -19.19% | ₹29.9 L+₹3.0 L (11.2%) | L3 | Admitted-Finance |
| 4 | L4₹31.0 L+₹4.1 L (15.3%)Admitted-Finance | -16.20% | ₹31.0 L+₹4.1 L (15.3%) | L4 | Admitted-Finance |
| 5 | L5₹31.4 L+₹4.6 L (17.0%)Admitted-Finance | -14.99% | ₹31.4 L+₹4.6 L (17.0%) | L5 | Admitted-Finance |
Tender Value
₹43.5 L
EMD Value
₹84,040
Closing Date
6 Jul 2026, 3:30 pmClosed
CE (EHT-Construction)
Block No. 4, Shakti Bhawan, Rampur, Jabalpur
(i) Const. of CC Road and RCC Drain in colony premises at 132 KV S/s Seoni (ii) Const. of CC Road, Fencing, Gate etc. for TLM Sub-Div. Store in premises of 132 KV S/s Seoni (iii) Const. of CC Road in colony premises at 132 KV S/s Chhindwara.
2026_MPPTC_515333_1
349
Open Tender
Civil Works - Others
Percentage
270 days
Seoni
As per tender
14 documents required · 14 mandatory
₹1,770
₹84,040
Yes
23 Jul 2026
12 Jun 2026
7 Jul 2026
12 Jun 2026
6 Jul 2026
12 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Repair, Renovation and Reconstruction of Demaged Boundary wall | - | - | - | - |
| 2 | 3011471,2.5(SOR w.e.f 01.01.2024),Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m lead and lift up to 1.5 m, disposed soil to be levelled and neatly dressed, All kinds of soil | 186 | Sqm | 43 | ₹7,998 |
| 3 | 3000140,37 NSOR,Providing & Fixing in position LDPE Film of 150 micron (0.15 mm ) , ISI mark- 2508 (Grade 231) , including heat sealed joints at ends as per IS 9698 including cost of all material, labour, T&P, taxes, transportation etc. complete as directed by Engineer in charge | 1,238 | M2 | 25 | ₹30,950 |
| 4 | 3011576,4.1.1.3(SOR w.e.f 01.01.2024),Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work upto plinth level : With 20mm nominal size graded stone aggregate. M-15 – Grade concrete | 186 | M3 | 4,471 | ₹8,31,606 |
| 5 | 3011589,4.3.1,Centering and shuttering including strutting, propping etc. and removal of form work for : Upto Foundations, footings, bases for columns, plinth beam, curtain wall, column below plinth " | 83 | M2 | 169 | ₹14,027 |
| 6 | 3000100,2NSOR,supplying and spreading in EHV Substation yard or road works with hard moorum/ hard copra having maximum dry desnsity not less than 2 MT per cum with stacking, boxing , including cost of material, T&P, Royalty, all lead & lift etc. complete in layers not exceeding 200 mm , as per specifications and direction of Engineer-in-Charge. but excluding compaction | 42 | M3 | 270 | ₹11,340 |
| 7 | 3000108,10 NSOR,Compaction of moorum /earth by using SRR/DRR including hire & running expenses of roller, cost of water, T&P, labour, transportation, taxes etc. complete as directed by Engineer in charge. (For Berms only) | 44 | M3 | 22 | ₹968 |
| 8 | 3011472,2.6,Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including dressing of sides and ramming of bottom disposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed earth to be levelled and neatly dressed. (No extra lift is payable if work is done by mechanical means)
All kinds of soil | 90 | CUM | 147 | ₹13,230 |
| 9 | 3011694,5.16.6(SOR w.e.f 01.01.2024),Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding including cost of binding wire all wastages and overlaps, couplers (overlaps shall be provided as .........Mechanically Treated bars. (TMT/TMX) FE 500 or more conforming to IS 1786 | 950 | KG | 80 | ₹76,000 |
| 10 | 3011633,5.1.1(SOR w.e.f 01.01.2024),Providing and laying in position specified grade of reinforced cement concrete (with 20mm nominal size graded stone aggregate) excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : M-20 Grade Concrete | 60 | M3 | 6,153 | ₹3,69,180 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.69 MB
Document374.pdf
Tender Documents • 1.43 MB
AffidavitNew.pdf
Other Document • 0.18 MB
Questionnaire.pdf
Other Document • 0.02 MB
BOQ_620726.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .