Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹24.8 LAccepted-AOC MUNDADA NAGAR MUNDADA APARTMENT JALGAON | JALGAON | JALGAON | MAHARASHTRA | ₹24.8 L | 1 | Accepted-AOC ac |
| 2 | 2₹25.1 L+₹24,837 (1.00%)Rejected-Finance SOLAPUR | MAHARASHTRA | 413001 | ₹25.1 L+₹24,837 (1.00%) | 2 | Rejected-Finance re |
| 3 | 3₹25.3 L+₹49,673 (2.00%)Rejected-Finance | ₹25.3 L+₹49,673 (2.00%) | 3 | Rejected-Finance re |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹24.8 L
EMD Value
₹24,837
Closing Date
8 May 2026, 6:00 pmClosed
ADD CEO
DWCO
Name of Work Special Repairs To Percolation Tank At Palwan ( 18.013654, 75.29864 ) Taluka Madha District Solapur
2026_SOLAP_1297603_1
DWCO/22/2025-26
Open Tender
Civil Works
Percentage
90 days
Name of Work Special Repairs To Percolation Tank
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,000
₹24,837
17 Aug 2026
24 Apr 2026
11 May 2026
24 Apr 2026
8 May 2026
24 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | Item No. 1 : Cleaning grass and removal of rubbish , including all lead and depositing outside the periphery of the area as directed, including 1 % Cess for labour welfare etc. complete | - | Sq m | - | - |
| - | Item No. 2 : Dismentalling dry rubble stone pitching including stacking them neatly including all lead & lift , including 1 % Cess for labour welfare etc. complete | - | Sq m | - | - |
| - | Item No.3 : Stripping Up to 10 cm depth in all kind of soil, Soft Murum hard murum, with all lead & Lift and depositing as directed by Engineer in charge including 1 % Cess for labour welfare etc. complete | - | Cum | - | - |
| - | Item No.4 : Excavation in all kinds of Soils & Soft murum including boulders up to 0.6 m diameter (0.113cum) for COT / WW Bar & Flank Wall / Tail & Approach Channel and placing the excavated stuff neatly in dump area or for formation of service road / embankment as directed including cost of all materials, machinery, labour, dressing bed and sides to required level and profile with all lead and lift. including 1 % Cess for labour welfare etc. complete . | - | Cum | - | - |
| - | Item No.5 : Excavation in Hard Murum including boulders up to 0.6 m diameter (0.113 cum) for COT / WW Bar & Flank Wall / Tail & Approach Channel and placing the excavated stuff neatly in dump area or for formation of service road / embankment as directed including cost of all materials, machinery, labour, dressing bed and sides to required level and profile with all lead and lift. including 1 % Cess for labour welfare etc. complete . | - | Cum | - | - |
| - | Item No.6 : Excavation in Soft Rock without blasting including boulders up to 0.6 m diameter (0.113 cum) for COT / WW Bar & Flank Wall / Tail & Approach Channel and placing the excavated stuff neatly in dump area or for formation of service road / embankment as directed including cost of all materials, machinery, labour, dressing bed and sides to required level and profile with all lead and lift. including 1 % Cess for labour welfare etc. complete . | - | Cum | - | - |
| - | Item No.7 : Providing cut off trench filling using selected impervious soil from approved borrow areas ( Government acquired land ) including cost of all materials, machinery, labour, all other operations such as collection of soil, spreading soil in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compacter including cost of water with all lead and lift excluding royalty charges including 1 % Cess for labour welfare etc. complete . | - | - | - | - |
| - | A) with borrow material from Other Place | - | - | - | - |
| - | i). Including Watering and Consolidation by mechanical means | - | Cum | - | - |
| - | Item No. 8 : Providing casing embankment using selected pervious material available directly from excavation , laying in layers including cost of all materials, machinery, labour, all other operations such as collection of material, spreading material in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, including watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compactor including cost of water / excluding compaction etc., complete with all lead and lift excluding royalty charges including 1 % Cess for labour welfare etc. complete . | - | - | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.65 MB
Tendernotice_2.pdf
PDF • 0.81 MB
BOQ_2228892.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .