Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹2.5 CrAdmitted-Finance | -32.38% | ₹2.5 Cr | L1 | Admitted-Finance |
| 2 | L2₹2.8 Cr+₹31.4 L (12.7%)Admitted-Finance | -23.80% | ₹2.8 Cr+₹31.4 L (12.7%) | L2 | Admitted-Finance |
| 3 | L3₹2.9 Cr+₹46.2 L (18.7%)Admitted-Finance | -19.75% | ₹2.9 Cr+₹46.2 L (18.7%) | L3 | Admitted-Finance |
Tender Value
₹3.7 Cr
EMD Value
₹8.6 L
Closing Date
9 Jun 2026, 4:00 pmClosed
Executive Engineer Construction Division Leh
Office of the Executive Engineer Construction Division Leh
Construction of Community Eco-Park at Matho..(Under District Capex)
2026_PWD_18971_1
CDL 42 of Leh of 2026-27
Open Tender
Civil Works - Buildings
Percentage
540 days
leh
Please refer Tender documents.
3 documents required · 3 mandatory
₹4,320
Executive Engineer Construction Division Leh
₹8.6 L
17 Jun 2026
21 May 2026
10 Jun 2026
21 May 2026
9 Jun 2026
21 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) over areas (exceeding 30cm in depth,1.5m in width as well as10sqm on plan) including getting out and disposal of excavated earth lead upto 50m and liftupto1.5m, as directed by Engineer-in-charge.
All kinds of soil | 409.65 | Cum | 208.42 | ₹85,379.25 |
| 2 | Filling availableexcavatedearth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm indepth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 262.72 | Cum | 220.41 | ₹57,906.12 |
| 3 | Supply and stacking of Fly ash conforming to IRC- 58 at site, including carriage, loading , unloading & stacking up to any lead (measured stacks will be reduced by 20% for payment). | 363.41 | Cum | 223.4 | ₹81,185.79 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : a) 1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 40 mm nominal size derived from natural sources) | 16.12 | Cum | 7,839.48 | ₹1,26,372.42 |
| 5 | b) 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 75.67 | Cum | 5,725.33 | ₹4,33,235.72 |
| 6 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 11.89 | Cum | 9,671.18 | ₹1,14,990.33 |
| 7 | Providing and laying damp-proof course 50mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 20mm nominal size). | 66.56 | Sqm | 486.19 | ₹32,360.81 |
| 8 | Providing & applying a coat of residual petroleum bitumen of grade of VG-10 of approved quality using 1.7kg per square metre on damp proof course after cleaning the surface with brushes and finally with apiece of cloth lightly soaked in kerosene oil. | 66.56 | Sqm | 173.75 | ₹11,564.8 |
| 9 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement- All work up to plinth level :
1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 77.65 | Cum | 9,557.34 | ₹7,42,127.45 |
| 10 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) | 21.03 | Cum | 11,102.31 | ₹2,33,481.58 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.25 MB
BOQ_45303.xls
BOQ • 0.58 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .