Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹44.9 LAccepted-Finance | ₹44.9 L | 1 | Accepted-Finance below estimate rate |
| 2 | 2₹44.9 LRejected-Finance | ₹44.9 L | 2 | Rejected-Finance above estimate rate |
| 3 | 3₹45.4 LRejected-Finance | ₹45.4 L | 3 | Rejected-Finance above estimate rate |
| 4 | 4₹45.6 LRejected-Finance | ₹45.6 L | 4 | Rejected-Finance above estimate rate |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | SAV CONSTRUCTION L4 | RRR ENGINEERING CONSTRUCTION L3 | Thangamani L1 | sukaraman R L2 |
|---|---|---|---|---|---|---|---|
| 1.00 | Clearing the Light jungle including all labour charges for burying and burning etc., complete. | 1,845 | Sqm | 6.5 ₹11,992.50 | 6.35 ₹11,715.75 | 6 ₹11,070 | 5 ₹9,225 |
| 2.00 | Earthwork excavation and Deposting on bank with in initial lead and including all etc Complete | 1,033.2 | Sqm | 141 ₹1.5 L | 140 ₹1.4 L | 138 ₹1.4 L | 130 ₹1.3 L |
| 3.00 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m including all labour charges etc., complete. | 1,643.75 | cum | 24 ₹39,450 | 23 ₹37,806.25 | 20 ₹32,875 | 20 ₹32,875 |
| 4.00 | Collection and supply of gritty gravel from approved quarry including all labour charges for spreading and compaction with power roller etc. complete, for Shoulders Km 0/0 - 1/0 | 312.5 | cum | 612 ₹1.9 L | 611 ₹1.9 L | 600 ₹1.9 L | 610 ₹1.9 L |
| 5.00 | Km 1/0-1/280 | 87.5 | cum | 622 ₹54,425 | 621 ₹54,337.50 | 615 ₹53,812.50 | 610 ₹53,375 |
| 6.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5 | 616.41 | cum | 2,461 ₹15.2 L | 2,460.1 ₹15.2 L | 2,450 ₹15.1 L | 2,455 ₹15.1 L |
| 7.00 | Providing and laying of Prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. Etc Complete | 4,931.26 | Sqm | 89 ₹4.4 L | 87.4 ₹4.3 L | 85 ₹4.2 L | 85 ₹4.2 L |
| 8.00 | Providing and laying of Tack Coate using Emulsion at the rate of 2.5 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 4,931.26 | Nos | 21 ₹1.0 L | 20.5 ₹1.0 L | 18 ₹88,762.68 | 19.5 ₹96,159.57 |
| 9.00 | BITUMINOUS CONCRETE 30 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregate Including all etc Cmplete | 123.28 | Sqm | 9,134 ₹11.3 L | 9,132.9 ₹11.3 L | 9,128 ₹11.3 L | 9,120 ₹11.2 L |
| 10.00 | Provision of 15 nos. rumble strips covered with premix bituminous carpet, 15-20 mm high at centre, 250 mm wide placed at 1 m centre-to-centre at approved locations to control speed, marked with white strips of road marking paint. | 7.2 | Sqm | 385 ₹2,772 | 383.6 ₹2,761.92 | 375 ₹2,700 | 350 ₹2,520 |
Tender Value
₹47.5 L
EMD Value
₹47,500
Closing Date
26 Feb 2026, 3:15 pmClosed
Block Development Officer VP Avinashi
Panchayat Union Office Avinashi
Strengthening to the road from NH 47 Selam Kochin Road to Km 1 2 of Thirumurugan Poondi Pachampalayam to Devampalayam Road Km 0 0 1 280
2026_RDTN_662940_1
3426/2024/A5 date 17.02.2026
Open Tender
Civil Works
Avinashi
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹47,500
Yes
2 Mar 2026
20 Feb 2026
26 Feb 2026
20 Feb 2026
26 Feb 2026
21 Feb 2026
20 Feb 2026 - 26 Feb 2026
Clearing the Light jungle including all labour charges for burying and burning etc., complete.
Earthwork excavation and Deposting on bank with in initial lead and including all etc Complete
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m including all labour charges etc., complete.
Collection and supply of gritty gravel from approved quarry including all labour charges for spreading and compaction with power roller etc. complete, for Shoulders Km 0/0 - 1/0
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5
Providing and laying of Prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. Etc Complete
Providing and laying of Tack Coate using Emulsion at the rate of 2.5 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
BITUMINOUS CONCRETE 30 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregate Including all etc Cmplete
Provision of 15 nos. rumble strips covered with premix bituminous carpet, 15-20 mm high at centre, 250 mm wide placed at 1 m centre-to-centre at approved locations to control speed, marked with white strips of road marking paint.
Provision for Road Marking with hot applied thermoplastic compound with reflectorising Glass beadson bitumious Surface
Provision for Km stone
Provision for Hm stone
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.91 MB
tkp.pdf
Tender Documents • 0.65 MB
BOQ_795865.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid