SE Basti Circle PWD Basti
O/F SUPRINTENDING ENGINEER BASTI CIRCLE PWD BASTI
Construction of Rampur Medical College Bhawanipur Puliya to Khadara Shivmandir Nahar Patari Road
2026_CEUBZ_1184134_1
4934/4E-NIVIDA-BASTI CIRCLE/2026 DATED-25-08-2026
Open Tender
Civil Works
Lump-sum
180 days
WORK
as per sbd
2 documents required · 2 mandatory
₹2,714
₹10.7 L
O/F SUPRINTENDING ENGINEER BASTI CIRCLE PWD BASTI
29 Sept 2026
10 Sept 2026
29 Sept 2026
10 Sept 2026
29 Sept 2026
10 Sept 2026
10 Sept 2026 - 29 Sept 2026
14 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1 for proper completion of work detailed specification & direction of E/I. for Embankment work. as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) with all aspects | 9,500 | Cum | 87.5 | ₹8,31,250 |
| 2 | Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. as per Technical
Specification Clause 302(II) as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) with all aspects | 102.3 | Cum | 64 | ₹6,547.2 |
| 3 | Construction of granular sub-base by providing Shankargarh material, spreading in uniform layers with motor grader on prepared surface and compacting in two layers at OMC with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. for proper completion of work as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) with all aspects | 588 | Cum | 4,200 | ₹24,69,600 |
| 4 | Providing ,Laying ,spreading and compacting stone aggregates of 53-22.4 mm size material to water bound macadam specification including spreading in uniform thickness, hand packing ,rolling with Smooth wheel roller 80-100 KN in stages to proper grade and camber ,applying and brooming ,Stone screening grit to fill up the interstices of coarse aggregate ,watering and compacting to the required density grading 3 as per Technical specification clause 405. as per Technical Specification Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.). | 517 | Cum | 4,750 | ₹24,55,750 |
| 5 | Construction of un-reinforced, plain cement concrete pavement with M30 grade concrete, thickness as per design, over a prepared sub base with 43 grade cement as per Clause 1501.2.2, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.20 cum capacity and appropriate weight batcher using approved mix design, laid in approved fixed side framework(steel channel, laying and fixing of 125 micron thick polythene film including levelling the framework as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in a continuous operation including provision of contraction joints, applying curing of concrete slabs for 14-days and water finished to lines and grades as per drawing and MORD specification Clause 1501. in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) | 1,012.5 | Cum | 9,800 | ₹99,22,500 |
| 6 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical
Specification Clause 303.1 Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) | 2,350 | Cum | 87.5 | ₹2,05,625 |
| 7 | Cost of IInd Year Maintenaince @0.25% as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) with all aspects | 1 | Job | 42,000 | ₹42,000 |
| 8 | Cost of IIIrd Year Maintenaince @0.5% as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) with all aspects | 1 | Job | 85,000 | ₹85,000 |
| 9 | Cost of IVth Year Maintenaince @0.75% as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) with all aspects | 1 | Job | 1,27,000 | ₹1,27,000 |
| 10 | Cost of Vth Year Maintenaince @1.00% as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.) with all aspects | - | Job | 1,69,000 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.06 MB
Tendernotice_2.pdf
PDF • 1.03 MB
Tendernotice_3.pdf
PDF • 0.37 MB
BOQ_2227392.xls
BOQ • 0.42 MB
4934D.pdf
PDF • 0.21 MB
4934.pdf
PDF • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .