Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹55.5 L
EMD Value
₹1.1 L
Closing Date
22 Oct 2026, 2:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
CE PDA PRAYAGRAJ
7-8 floor Indira Bhawan PDA Prayagraj
Widening and strengthening of the road from Jagram Crossing to Katra Link Road via Shamya Mai Park.
2026_ADAUP_1195270_1
30/11/CE/PDA/2026
Open Tender
Civil Works
Fixed-rate
180 days
7-8 floor Indira Bhawan PDA Prayagraj
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
Secretary PDA Prayagraj
₹1.1 L
10 Oct 2026
10 Oct 2026
22 Oct 2026
10 Oct 2026
22 Oct 2026
10 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge. (DSR 2.1.1/2023) | 1,080 | Cum | 95.44 | ₹1,03,075.2 |
| 2 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. (DSR 15.3/2023) | 46 | Cum | 2,610.17 | ₹1,20,067.82 |
| 3 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) (DSR 15.2.1/2023) | 157.5 | Cum | 1,789.17 | ₹2,81,794.28 |
| 4 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar (DSR 15.7.4/2023) | 46 | Cum | 1,514.24 | ₹69,655.04 |
| 5 | Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge With material conforming to Grade-I (size range 75 mm to 0.075 mm) having CBR Value-30(DSR 16.78.1/2023) | 450 | Cum | 2,046.24 | ₹9,20,808 |
| 6 | Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to 0.075 mm ) to wet mix macadam (WMM) specification including premixing the material with water at OMC in for all leads & lifts, laying in uniform layers with mechanical paverfinisher in sub- base / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achievethe desired density, complete as per specifications and directions of Engineer-in-Charge. (DSR 16.79/2023) | 210 | Cum | 2,142.01 | ₹4,49,822.1 |
| 7 | Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom. On bituminous surface @ 0.25kg/sqm (DSR 16.31.2.2/2023) | 3,200 | Sqm | 10.33 | ₹33,056 |
| 8 | Providing and applying tack coat using hot straight run bitumen of grade VG - 10, including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications : On W.B.M. @ 0.75 Kg / sqm (DSR 16.30.1/2023) | 3,200 | Sqm | 44.47 | ₹1,42,304 |
| 9 | Providing and laying Dense Graded Bituminous Macadam using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers as per specifications to achieve the desired compaction and density, complete as per specificatons and directions of Engineer-in-Charge 50 to 100 mm average compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity. (DSR 16.54.1/2023) | 160 | Cum | 8,180.22 | ₹13,08,835.2 |
| 10 | Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. 40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity. (DSR 16.57.1/2023) | 96 | Cum | 8,912.76 | ₹8,55,624.96 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.50 MB
BOQ_2257092.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .