The Superintending Engineer/ CEDC/Metro/ Coimbatore
Construction of a Lift room for accommodating the 8 passengers gearless lift of size 1300x 1100 mm, at center wing of the Central office building, Tatabad, Coimbatore.
2022_EB_258019_1
Spec.No.13/2022-2023, Dt.21.10.2022
Open Tender
Civil Works
Works
180 days
SE/Metro/Coimbatore
Refer tender documents
2 documents required · 2 mandatory
₹0
₹12,200
11 Nov 2022
21 Oct 2022
8 Nov 2022
21 Oct 2022
7 Nov 2022
21 Oct 2022
21 Oct 2022 - 7 Nov 2022
Amount
Dismantling the existing RCC flooring concrete including all labour,machineries, as instructed by the site incharge including all lead, lift, etc., complete.
Dismantling the existing PCC flooring concrete including alll labour,machineries, as instructed by the site incharge including all lead, lift, etc., complete.
Dismantling the existing brick /stone masonry works in cement mortar including all labour,machineries, as instructed by the site incharge including all lead, lift, etc., complete.
Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc., complete as per standard specification
Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m in soft disinegrated rock, laterite, soft rock or kankar, not requiring blasting etc., complete as per standard specification.
Supplying and filling with M-Sand for foundation including cost of sand, all labour, lead,lift, consolidation etc. complete.
PCC 1:3:6, using 40mm HBG metal foundation including cost of cement, all materials, labour, lead, lift, etc. complete.
RCC 1:1.5:3 using 12-20mm HBS machine crushed metal for raft foundation including cost of all materials, curing, vibrating charges, centering, labour, lead, lift, etc., complete, but excluding cost of steel reinforcement.
RCC 1:1.5:3 using 12-20mm HBS machine crushed metal for column upto Ground level with form work including cost of all materials,curing, vibrating charges, centering, labour, lead, lift, etc., complete, but excluding cost of steel reinforcement.
RCC 1:1.5:3 using 12-20mm HBS machine crushed metal for column above Ground level upto 4.50 m with form work including cost of all materials, curing, vibrating charges, centering, labour, lead, lift, etc., complete, but excluding cost of steel reinforcement.
RCC 1:1.5:3 using 12-20mm HBS machine crushed metal for column for first floor with form work including cost of all materials, curing, vibrating charges, centering, labour, lead, lift, etc., complete, but excluding cost of steel reinforcement.
RCC 1:1.5:3 using 12-20mm HBS machine crushed metal for column for second floor with form work including cost of all materials, curing, vibrating charges, centering, labour, lead, lift, etc., complete, but excluding cost of steel reinforcement.
RCC 1:1.5:3 using 12 to 20mm HBS machine crushed metal for lift side wall including cost of all materials, curing, vibrating charges, centering, labour, lead, lift, etc., complete, but excluding cost of steel reinforcement.
RCC 1:1.5:3 mix using 12-20mm HBS machine crushed metal for grade beam in ground floor (floor level) with form work including cost of all labour, materials, M.Sand,curing, vibrating charges, labour, lead, lift, etc. complete but excluding cost of steel reinforcement.
RCC 1:1.5:3 mix using 12-20mm HBS machine crushed metal for grade beam in Ground floor (roof level) with form work including cost of all labour, materials, M.Sand,curing, vibrating charges, labour, lead, lift, etc. complete but excluding cost of steel reinforcement.
RCC 1:1.5:3 mix using 12-20mm HBS machine crushed metal for grade beam in First floor (roof level) with form work including cost of all labour, materials, M.Sand, curing, vibrating charges, labour, lead, lift, etc. complete but excluding cost of steel reinforcement.
RCC 1:1.5:3 mix using 12-20mm HBS machine crushed metal for grade beam in Second floor (roof level) with form work including cost of all labour, materials, M.Sand, curing, vibrating charges, labour, lead, lift, etc. complete but excluding cost of steel reinforcement.
RCC 1:1.5:3 mix using 12-20mm HBS machine crushed metal for lintel beam in ground floor with form work including cost of all labour, materials, M.Sand, curing, vibrating charges, labour, lead, lift, etc. complete but excluding cost of steel reinforcement.
RCC 1:1.5:3 mix using 12-20mm HBS machine crushed metal for lintel beam in first floor with form work including cost of all labour, materials, M.Sand, curing, vibrating charges, labour, lead, lift, etc. complete but excluding cost of steel reinforcement.
RCC 1:1.5:3 mix using 12-20mm HBS machine crushed metal for lintel beam in second floor with form work including cost of all labour, materials, M.Sand, curing, vibrating charges, labour, lead, lift, etc. complete but excluding cost of steel reinforcement.
Providing steel reinforcement MS/RTS rod for reinforced concrete works, including cost of steel MS/RTS rods, binding wire, labour charges for cutting, straightening, bending, placing aligning and tying properly including cost of all materials lead and lift, etc., complete as per standard specification.
Brick work in CM 1:5 using class II Table moulded chamber bricks for basement & Super structure including cost of all materials, labour , lead, lift, etc,. complete.
Brick work in CM 1:5 using class II Table moulded chamber bricks for first floor including cost of all materials, labour , lead, lift, etc,. complete.
Brick work in CM 1:5 using class II Table moulded chamber bricks for second floor including cost of all materials, labour , lead, lift, etc,. complete.
Plastering with CM 1:5, 12mm thick using M Sand including cost of all materials, labour,curing , lead, lift, etc. complete.
Applying two coats of wall putty paste of approval quality for wall surface by scrapping sand paper etc.,as directed by the engineer at site including cost of all materials, scaffolding, labour, lead, lift, etc., complete.
Painting two coats of plastic emulsion paint over a coat of primer of approved quality and colour including cost of all materials, labour, through scarpping , scafolding, lead, lift, etc ., complete.
Supplying and laying of acid proof Non - slippery Jiont free Ceramic floor tiles of 305x 305 x 8 mm of approved size, quality and colour laid in CM. 1:3, 20 mm thick and pointing with white cement using 0.40Kg./m2 including finishing joint and pointing flush with tiled surface including cost of cement, all materials, labour, curing, lead, lift etc., complete.
Dadooing wall with Fine polished ruby red of size 4'x2' 18mm to 20 mm thick granite slab of approved quality laid in CM.1:2 ,10 mm thick after scrapping & cleaning the existing wall surface as instructed and pointing with white cement using 0.40Kg /Sqm. including finishing the joint and pointing flush with tiled surface including cost of cement all materials labour curing , leads lifts etc., as per standard specification complete.
Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride) Louvered Ventilators of from the profile the size of outer frame 60mmx58mm and shutter profile size of 60x78mm both profiles are reinforced with GI/1mm 125GSM and 100% corrosion free, the profile are multi chambered sections with wall thick of 2mm. The EPDM rubber (black colour) covered with all over the edges of frame and shutter. The corners and joints should be welded and cleaned. Radiations pin headed glass 4mm thick should be provided in the louers. The window should be fixed to the wall with 100% packing with screws and silicon packing all round the frames.
Wiring with 2 x 1.5 sq.mm. (22 / 0.3) PVC insulated single core unsheathed copper conductor of 1100V grade in suitable PVC rigid pipe concealed in wall and ceiling with PVC accessories in flush with wall with 3mm thick hylum sheet cover with TW switch box and 5A FT switch with continuous earth wire connection of 14 SWG TC wire for making good of the concealed portion with suitable colour for PVC concealed light point. (SD No.23)
Supply and run of 4x4 sq.mm (56/0.3) PVC insulated Multistrand unsheathed copper conductor of 1100 V grade on 7/20 GI bearer wire for service main connection including cost of all materials, labour, lead, lift etc., complete,as per standard specification.
Supply and fixing of 18 W LED 3000K flu.type fitting complete on wall/ceiling with tubes and PVC unsheathed Copper leads from terminal to the fitting(SD 88).
Supply and fixing of W.T bulk head fitting (Philips/Balaji/K.Lite/Crompton Greaves) suitable for 9 W CFL bulp with guard including cost of all materials, labour, lead, lift etc., complete,as per standard specification.
Earthing as per PWD standard with an earth electrode of 2 mtr. Class 'B' GI pipe of dia not less than 32mm complete with necessary masonry work including cost of all materials, labour, lead, lift etc., complete,as per standard specification
Supply and laying of 4 x 6 Sqmm PVC armoured LTUG cable in a trench to be eXcavated at a depth of 0.75 m putting 0.15 mtr layer of sand and covering the cable completely with brick and sand and refilling the earth to make good (SD 201)
Supply and fixing of 63 A TPNMC switch on suitable angle iron frame work with MS cable entry box with PWD earthing (SD 165)
SGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only
CGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only
Inter-state GST @18% for other than Tamil Nadu supplier. If the contractor is within Tamil Nadu may be quoted as "0" only
TAJ INFRA
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .