Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.4 LAccepted-AOC | ₹11.4 L | L1 | Accepted-AOC L1 |
| 2 | L2₹11.8 LRejected-AOC | ₹11.8 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | R VASANTHA L2 | M.PANDIAN L1 |
|---|---|---|---|---|---|
| 1.001.Construction PUE School Compound wall @ Sathiram in Polivakkam Panchayat | |||||
| 2.00 | Earthwork excavation in all classes of soils except hadr rock in hard ORDINARY SOIL with initial lead and lift including all other labour chargesetc. Complete as per SS 20 B. | 64.59 | m3 | 350 ₹22,606.50 | 263 ₹16,987.17 |
| 3.00 | Filling with good dry river sand including cost and conveyance to site and labour charges for filling, watering, tamping etc. complete | 6.99 | m3 | 2,500 ₹17,475 | 2,230 ₹15,587.70 |
| 4.00 | Cement Concrete 1:4:8 using 40 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc | 6.99 | m2 | 6,011 ₹42,016.89 | 6,011 ₹42,016.89 |
| 5.00 | Brickwork in cement mortar 1:5 mix using country bricks including cost and conveyance of all materials to site mixing, palcing, curing and all labour charges etc. complete | 30.89 | m3 | 6,210 ₹1.9 L | 6,210 ₹1.9 L |
| 6.00 | Supply and fabrication of steel including cost and conveyance of all materials to site and all labour charges for placing in position etc. complete. | 1.24 | mt | 95,858 ₹1.2 L | 91,858 ₹1.1 L |
| 7.00 | Reinforcement Cement Concrete 1:1.5:3 (One cement, One and Half sand, Three Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly for all RCC including cost conveyance and all labour charges etc. complete. | 20.77 | m3 | 9,733 ₹2.0 L | 9,733 ₹2.0 L |
| 8.00 | Above basement | 3.27 | m3 | 9,874 ₹32,287.98 | 9,874 ₹32,287.98 |
| 9.00 | Providing centering and shuttering for all RCC items including cost , conveyance and all labour charges etc complete | 94.02 | m2 | 747 ₹70,232.94 | 547 ₹51,428.94 |
| 10.00 | Above basement | 56.86 | m2 | 1,095 ₹62,261.70 | 1,095 ₹62,261.70 |
Tender Value
₹11.5 L
EMD Value
₹11,550
Closing Date
21 Jan 2026, 3:00 pmClosed
BDO (B.P)Kadambathur block
BDO (B.P)Kadambathur block
Construction PUE School Compound wall at Sathiram in Polivakkam Panchayat
2026_RDTN_640414_1
Rc No 1600/2025 /A2 dt 06.01.2026
Open Tender
Civil Works
Kadambathur block
Contractors Pre Qualification Details
4 documents required · 4 mandatory
₹0
₹11,550
Yes
5 Feb 2026
8 Jan 2026
21 Jan 2026
8 Jan 2026
21 Jan 2026
8 Jan 2026
Earthwork excavation in all classes of soils except hadr rock in hard ORDINARY SOIL with initial lead and lift including all other labour chargesetc. Complete as per SS 20 B.
Filling with good dry river sand including cost and conveyance to site and labour charges for filling, watering, tamping etc. complete
Cement Concrete 1:4:8 using 40 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc
Brickwork in cement mortar 1:5 mix using country bricks including cost and conveyance of all materials to site mixing, palcing, curing and all labour charges etc. complete
Supply and fabrication of steel including cost and conveyance of all materials to site and all labour charges for placing in position etc. complete.
Reinforcement Cement Concrete 1:1.5:3 (One cement, One and Half sand, Three Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly for all RCC including cost conveyance and all labour charges etc. complete.
Above basement
Providing centering and shuttering for all RCC items including cost , conveyance and all labour charges etc complete
Above basement
Plastering in CM 1:5 mix, 12mm thickness including cost and conveyance of all materials to work site from approved quarry sources and labour charges etc. complete.
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification
Provision for main gate charges
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_766865.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.41 MB
pricebid02.pdf
Additional Documents • 0.62 MB
BOQ_766865.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid