| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹99.5 LAccepted-AOC | ₹99.5 L | L1 | Accepted-AOC L1 bidder |
| 2 | L2₹1.0 Cr+₹51,249.36 (0.52%)Rejected-Finance | ₹1.0 Cr+₹51,249.36 (0.52%) | L2 | Rejected-Finance L2 bidder |
| 3 | L3₹1.0 Cr+₹81,780.89 (0.82%)Rejected-Finance | ₹1.0 Cr+₹81,780.89 (0.82%) | L3 | Rejected-Finance L3 bidder |
| 4 | Rejected-Technical | - | - | Rejected-Technical Techno-Commercially Dis-Qualified |
| 5 | Not Admitted-Fee/PreQual/Technical B 4 PLOT NO 114 GURU KIRPA BUILDING SHIV SHAKTI NAGAR TN MISHRA MARG NIRMAN NAGAR JAIPUR JAIPUR RAJASTHAN JAIPUR RAJASTHAN 302019 | JAIPUR | RAJASTHAN | 302019 | - | - | Not Admitted-Fee/PreQual/Technical Others-Offline bid not received |
Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
29 Jun 2026, 3:00 pmClosed
DGM C and P division
Omkareshwar Power Station, Administrative Block, URJA VIHAR, Siddhwarkut Distt. Khandwa
Construction of New Badminton Hall at Urja Vihar Parisar
2026_NHDC_912942_1
NHDC/3C/367/NIT-791/26/429 dated 13.06.2026
Open Tender
Civil Works
Percentage
365 days
Omkareshwar Power Station NHDC Ltd Siddhwarkut
Please refer Tender documents.
14 documents required · 14 mandatory
₹1,180
NHDC LIMITED
₹2.2 L
Yes
28 Jul 2026
13 Jun 2026
2 Jul 2026
13 Jun 2026
29 Jun 2026
13 Jun 2026
13 Jun 2026 - 23 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in- Charge.In cement mortar. | 51.03 | Cum | 580.41 | ₹29,618.32 |
| 2 | Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead :Of area 3 sq. metres and below. | 9 | Each | 101.3 | ₹911.7 |
| 3 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in- Charge. | 12.51 | Cum | 1,005.88 | ₹12,583.56 |
| 4 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including dressing of sides and ramming of bottom disposal of excavated earth, lead up to 50m and lift up to 1.5m, disposed earth to be levelled and neatly dressed. (No extra lift is payable if work is done by mechanical means) All kinds of soil. | 414.6 | Cum | 175.2 | ₹72,637.92 |
| 5 | Providing and laying in position cement concreteof specified grade excluding the cost of centering and shuttering - All work upto plinth level :M-10Nominal (Mix-1 Cement : 3 sand : 6 graded stone aggregate ). | 0.6 | Cum | 4,636.1 | ₹2,781.66 |
| 6 | Providing and laying in position specified grade of reinforced cement concrete (nominal / design mix with 20mm nominal size graded stone aggregate) excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level M-20 Grade Concrete. | 0.6 | Cum | 7,333.15 | ₹4,399.89 |
| 7 | Centering and shuttering in cluding strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for concrete upto plinth level. | 477.24 | Sqm | 227.16 | ₹1,08,409.84 |
| 8 | Brick work with well burnt chimney bricks in bulls pattern trench kiln manufactured by ghol process, crushing strength not less than 40kg /cm2 and water absorption not more than 15% in foundation and plinth i/c curing etc. complete.Cement mortar 1:6 (1 cement : 6 sand). | - | Cum | 6,705.07 | - |
| 9 | Filling available excavated earth (excluding hard rock/Ordinary rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 86.56 | Cum | 113.22 | ₹9,800.32 |
| 10 | Supplying and filling in plinth under floors including watering ramming consolidating in layers not exceeding 20cm in depth and dressing complete.Supplying and filing in plinth with soil (other then BC soil ) having MDD not less than 1.85 t/m3 under floors including watering, ramming and compacting (minimum compaction 95% of MDD) in layers not exceeding 15cm depth and dressing complete. | 179.45 | Cum | 394.49 | ₹70,791.23 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.66 MB
BOQ_959438.xls
BOQ • 0.32 MB
367tender.pdf
Tender Documents • 19.77 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .