| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.4 LAccepted-AOC JAMBAD COLLIERY PARSEA CHURULIA KAJORA 713384 WEST BENGAL INDIA | KAJORA | PASCHIM BARDHAMAN | WEST BENGAL | 713384 | ₹3.4 L | L1 | Accepted-AOC SINCE THE BIDDER IS L1 |
| 2 | L2₹3.6 L+₹24,992.40 (7.45%)Rejected-Finance | ₹3.6 L+₹24,992.40 (7.45%) | L2 | Rejected-Finance AS THE BIDDER IS NOT L1 |
| 3 | L3₹3.6 L+₹26,019 (7.76%)Rejected-Finance | ₹3.6 L+₹26,019 (7.76%) | L3 | Rejected-Finance AS THE BIDDER IS NOT L1 |
Tender Value
₹3.4 L
EMD Value
₹4,300
Closing Date
14 Oct 2024, 5:00 pmClosed
Area Engineer (EnM) Kajora Area ECL
Office of The General Manager, Kajora Area ECL WB - 713338
Fitting of Submersible pump motor pipe complete set delivery pipeline repairing in highwalls, suction and delivery pipeline work at turbine pumps of Jambad OCP, Kajora Area
2024_ECL_318196_1
NIT No. GM/ Kaj/AE(EnM)/ e-Tender/24-25/19 Date 25.09.2024
Open Tender
Electrical and Maintenance Works
Item Rate
30 days
Kajora Area, ECL
As per Tender Documents
4 documents required · 4 mandatory
₹4,300
14 May 2025
27 Sept 2024
16 Oct 2024
27 Sept 2024
14 Oct 2024
27 Sept 2024
27 Sept 2024 - 10 Oct 2024
Amount
Item Description/ Heading
Fitting of Submersible pump motor set and pontoon for the new sump at coalface for pump
Installation of submersible pump motor pipe line suction and delivery range and fitting of foot valve
Doing the same job for 2nd and 3rd pump succession one after the same .
Before the joining of the pipeline fitting of flange and welding of flange in the pipes
Again as the water recedes, shiftying of both the submersible pumps from the 2nd loacation to the submersible pumps from the 2nd location to the 3rd location along with pontoon and valves after dismantling from the old location
Maintenance of the delivery pipelines for the next couple of weeks
Suction and delivery pipe line work of turbing pump as the water level reduces
Carring, loading transporting of 6 inch dia pipes 4 nos. on dumper from weighbridge site to Mahalaxmi site and then laying them and helping to make road for water draining
Non return and footvalve changing of NO 1 turbing pump after taking repaired valves from fitter store to site
Sliice valve changing of domestic pump. Pluro 1-4 stage after taking repaired valves from fitter store to site
Lifting of motor or and pump in case there is fault in the motor in the coming months then necessary on site repairing and lowering of the pump
Delivery pipeline repairing in the highwalls
Supply of nut bolt 5/8'' X 2''
Supply of heliflex hose of submersible pump durable quality cable of handling 1800 ft
Total impact of GST for the purpose of CTC
KHALSA ENTERPRISE
SATGURU ENGG WORKS
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .