Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Fee/PreQual/Technical/Finance | Admitted-Fee/PreQual/Technical/Finance |
| 2 | Admitted-Fee/PreQual/Technical/Finance | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹12 L
EMD Value
₹12,000
Closing Date
21 Jun 2023, 4:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
BLOCK DEVELOPMENT OFFICER SHENKOTTAI
BLOCK DEVELOPMENT OFFICE SHENKOTTAI
Construction of 100000 litre Capacity Sump at Kattalaikudiiruppu village in Karkudi Panchayat of Shencottai Panchayat Union AD WELFARE FUND -2022-23
2023_RDTN_328214_1
A3/1741/2023/BDOSCT DT 13.06.2023
Open Tender
Civil Works
Item Rate
180 days
SHENKOTTAI
Refer tender notice
2 documents required · 2 mandatory
₹0
₹12,000
21 Jun 2023
16 Jun 2023
21 Jun 2023
16 Jun 2023
21 Jun 2023
16 Jun 2023
Amount
Earthwork excavation in hard stiff clay,black cotton, hard red earth, shales,murrams, ordinary gravel stoney earth mixed with 50% fair sized boulders etc.,with an initial lead of 10m and lift of 2m. and as directed by TWAD BOARD Officers.
First depth of 0 to 2 m
2nd depth of 2m to 3m
Filling with clean m.sand complying with standard specification including watering ramming and consolidation etc., complete and as directed by TWAD BOARD Officers.
Levelling coarse in cement concrete 1:4:8 (one cement,four sand and eight aggregate) using 40mm hard broken stone for foundation and leveling coarse including cost of all materials,mixing,placing, ramming, curing,finishing etc., complete and as directed by TWAD BOARD Officers.
Reinforced Cement Concrete with M30 Design Mix for the following members excluding the cost of reinforcement and fabricating, centering, shuttering and strutting charges but including the cost of all materials, mixing, placing position, lifting, vibrating, finishing curing,finishing etc., complete and as directed by TWAD BOARD Officers.
Beyond 1.50 m & upto 4.50 m below GL
Upto 1.50 m Below GL
Upto 4.50 m above GL
Supply and erection of steel centering,shuttering for soffits and sides including necessary supports and strutting for all RCC works using MS sheets of suitable size of BG 10stiffened with MS angle of size 25 X 25 X 3mm for boarding laid over Silver Oak joists of size 10cm X 6.5cm space at 10cm c/c and supported by Casurino Props 10cm - 13cm spaced at 75cm c/c etc., complete and as directed by TWAD Board Officers.
For 0.00 to 3.30 M (Plane Surface)
For 0.00 to 3.30 M (Curved Surface)
For 0.00 to 3.30 M (FOR ROUND COLUMN)
For 3.30 M- 4.3 M (Plane Surface)
For 3.30 M TO 4.30M (Curved Surface)
Supplying, fabricating and placing in position of RTS rods for reinforcement including cost of steel and binding wire, labour charges etc., complete for RCC works and as directed by TWAD Board Officers.
Providing and fixing of cut stone (Rough dressed) set in CM 1:3 of size 0.45 X 0.45 X 0.15M at site including cost of all materials, mixing, placing position, lifting, vibrating, finishing curing,finishing etc., complete and as directed by TWAD BOARD Officers.
Providing RCC Ventilator of 0.15 m dia using 20mm HBG stone including cost of all materials, centering, shuttering, strutting,reinforcement, placing of concrete, finishing, curing and fixing in position on the roof slab with mosquito proof net arrangement and etc.,
Supply,Delivery and fixing of CI Manhole frame with cover of following size including cost of all materials, fixing of MS clamps,Bolt and nuts etc.,complete and as directed by TWAD Board Officers.
Colour washing two coats using cement paint includingcost of cement paint cost of all materials, labour charges, etc.,
Refilling the foundation with excavated Soil (other than sand) in layers of not more than 15cm thick, watering, well ramming, consolidating, complying with standard specification and as directed by TWAD Board Officers.
GST Amount for providing Service to Government Contract Works for the above RENEWAL Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Sheikushman abdul Razeeth
stage.html
html • 0.02 MB
finance_389450.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .