KMC, 212, Rashbehari Avenue, Kolkata -700019
M.S. JACKETING AT THE DAMAGED PORTION OF EXISTING 800 MM DIA D I FILTERED WATER DADICATED MAIN NEAR THE 38 R.K CHATTERJEE ROAD IN WD NO 67.
2026_KMC_1034049_1
KMC/WS/PG_67/T-07/26-27
Open Tender
CIVIL WORKS
Percentage
10 days
NEAR THE 38 R.K CHATTERJEE ROAD IN WD NO 67.
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹5,665
Yes
23 Jul 2026
23 Jul 2026
12 Aug 2026
23 Jul 2026
10 Aug 2026
24 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.4 Excavation of trial pit (3.0 m x 1.0 m x (upto) 3.0 m) for fixing of pumping main, washout line raking every detection against damage of S.W. pipe line electrical cable etc. as underground obstruction including 37.5 mm timber shuttering, earth cutting, dewatering, barricading and back filling etc. as per directionj of E-I-C | 6 | EA | 1,867 | ₹11,202 |
| 2 | CHAPTER - VIII SUPPLYING OF MATERIALS HIRE CHARGES OF MACHINERIES 8.27Hire charges of moveable type mounted earth excavator having minimum cutter size (1.0 cubic meter) & loader size (2.0 meter length x 0.75m width) for cutting & removal of any kind of soil, spoli etc. including cost of fuel, lubricants & manpower etc. in Water Supply Works. [ This item will be operated on prior permission from the concerned SE/Dy. Chief Engineer] For minimum engagement of 8 hrs. In a day | 3 | DAY | 8,951 | ₹26,853 |
| 3 | CHAPTER - VIII SUPPLYING OF MATERIALS HIRE CHARGES OF MACHINERIES 8.27Hire charges of moveable type mounted earth excavator having minimum cutter size (1.0 cubic meter) & loader size (2.0 meter length x 0.75m width) for cutting & removal of any kind of soil, spoli etc. including cost of fuel, lubricants & manpower etc. in Water Supply Works. [ This item will be operated on prior permission from the concerned SE/Dy. Chief Engineer] For beyond 8hrs. of working | 3 | HR | 1,119 | ₹3,357 |
| 4 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.1 Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. | 11.1 | %M3 | 119.27 | ₹1,323.9 |
| 5 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.1 Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (b) Depth of excavation for additional depth beyond 1,500 mm. and upto3,000 mm. but not requiring shoring | 11.1 | %M3 | 192.38 | ₹2,135.42 |
| 6 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.1 Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.(c) Depth of excavation for additional depth beyond 3000 mm. upto 4000mm. excluding cost of shoring as necessary | 8.88 | %M3 | 234.7 | ₹2,084.14 |
| 7 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC.1.6 Hire and labour charges for shoring work(including necessary close plank walling, framing,Eucalyptus/Jhou bulla piling, strutting etc)complete as per direction of the Engineer-in charge for foundation excavation (vertical surface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge).(a) Depth upto 1.5 m. | 6.7 | SQM | 386 | ₹2,586.2 |
| 8 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC.1.6 Hire and labour charges for shoring work(including necessary close plank walling, framing,Eucalyptus/Jhou bulla piling, strutting etc)complete as perdirection of the Engineer-in charge for foundation excavation (verticalsurface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge).(b) For additional depth beyond 1.5 m. and upto 3.00 m | 6.7 | SQM | 439 | ₹2,941.3 |
| 9 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.6 Hire and labour charges for shoring work(including necessary close plank walling, framing,Eucalyptus/Jhou bulla piling, strutting etc)complete as perdirection of the Engineer-in charge for foundation excavation (verticalsurface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge).(c) For additional depth beyond 3.00 m. | 5.36 | SQM | 498 | ₹2,669.28 |
| 10 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.8 Hire and labour charges for 75 mm dia bamboo railing on Jhau/Eucalyptusor other approved timber\bamboo posts 1.4 m above G.L and 0.60 m below G.L including tying strongly with coir ropes and boring holes for posts in any soil/ concrete surface/Bituminious surface packing the sides etc including cost of carriage of all materials and labour complete including cost of restoration to the damages of the ground to its original condition as per direction of Engineer in charge after removing the barricade.(Cost of restoration would be paid seperately. a) 75mm. dia bamboo railing & 125mm. Dia Jhau/Eucalyptus/other approved timber posts @ 1.60m apart (ii) Railing with 3 rows. | 6.7 | MTR | 49 | ₹328.3 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.05 MB
tbid.pdf
Tender Documents • 0.91 MB
BOQ_2539606.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].