| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹94,756Accepted-AOC | ₹94,756 Quoted ₹1.1 L | L1 | Accepted-AOC Work was Awarded |
| 2 | L2₹1.2 LRejected-AOC | ₹1.2 L | L2 | Rejected-AOC Work was Not Awarded |
| Sl No | Description | Qty | Unit | R.K.V. ENTERPRISES L1 | SARASWATHY ENGINEERING AND CONTRACTORS L2 |
|---|---|---|---|---|---|
| 1.00 | Dismantling the motor from MCP bed by carrying out the following works:
Disconnection of 6.6kv power cables from the motor power terminal. Disconnection of earth flat connection & space heater connection. Removing all the bed bolt. Opening the grill at 13.5mtr floor and lifting the motor from the bed using sling & pull lift, placing the motor at 13.5mtr floor. Closing the grill at 13.5 mtr floor. | 4 | Opn | 33,520 ₹39,553.60 | 34,840 ₹41,111.20 |
| 2.00 | Erection of the motor at MCP bed after completion of pump/motor works by carrying out the following works.
Opening the grill at 13.5mtr floor and lifting the motor from 13.5 mtr floor using sling & pull lift. Placing the motor at MCP bed. Closing the grill at 13.5mt floor. Fixing all the bed bolts , connecting the 6.6kv Power cables with motor terminals. Connecting the earth flat & space heater to the motor Putting the motors in to trial run and checking the performance of the motor after coupled the motor with pump such as vibration etc. | 4 | Opn | 77,200 ₹91,096 | 80,284 ₹94,735.12 |
Tender Value
Refer Docs
EMD Value
₹1,000
Closing Date
31 Dec 2025, 2:00 pmClosed
CE/TTPS
Chief Engineer Tuticorin Thermal Power Station-Tuticorin
TTPS ES Circle EM I Lifting the MC pump motors to enable works on MC pump motors and erecting the same after Completion of works during 2026 2027
2025_EB_633044_1
CE/SE/ES/TTPS/39/2026-27
Open Tender
Electrical and Maintenance Works
365 days
TTPS
As per BQR conditions in NIT
6 documents required · 6 mandatory
₹0
₹1,000
Yes
17 Mar 2026
16 Dec 2025
2 Jan 2026
16 Dec 2025
31 Dec 2025
16 Dec 2025
Dismantling the motor from MCP bed by carrying out the following works: Disconnection of 6.6kv power cables from the motor power terminal. Disconnection of earth flat connection & space heater connection. Removing all the bed bolt. Opening the grill at 13.5mtr floor and lifting the motor from the bed using sling & pull lift, placing the motor at 13.5mtr floor. Closing the grill at 13.5 mtr floor.
Erection of the motor at MCP bed after completion of pump/motor works by carrying out the following works. Opening the grill at 13.5mtr floor and lifting the motor from 13.5 mtr floor using sling & pull lift. Placing the motor at MCP bed. Closing the grill at 13.5mt floor. Fixing all the bed bolts , connecting the 6.6kv Power cables with motor terminals. Connecting the earth flat & space heater to the motor Putting the motors in to trial run and checking the performance of the motor after coupled the motor with pump such as vibration etc.
SARASWATHY ENGINEERING AND CONTRACTORS (BID ID -1549089)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.25 MB
BOQ_757371.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid