| 1 | L1₹72.9 CrAccepted-AOC 201 202 2 FLOOR FIT WELL HOUSE OPP HOME TOWN LBS MARG VIKHROLI WEST MUMBAI 400083 | MUMBAI | MUMBAI SUBURBAN | MAHARASHTRA | 400083 | L1 | Accepted-AOC Low Rate | |
| 2 | L2₹80.8 Cr+₹6.1 Cr (8.21%)Rejected-Finance | L2 | Rejected-Finance High Rate | |
| 3 | Not Admitted-Fee/PreQual/Technical A 201 2ND FLOOR FORTUNE 2000 C 3 G BLOCK BANDRA KURLA COMPLEX BANDRA EAST MUMBAI 400 051 | MUMBAI | MUMBAI | MAHARASHTRA | 400051 | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification | |
| 4 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | Relcon Infraprojects Ltd L2 | Generic Engineering Construction and Projects Limited L1 |
|---|---|---|---|---|---|
| 1.00Construction of Proposed Office Building on G-Block, Plot No. C-47, at Bandra Kurla Complex, Mumbai for Maharashtra Maritime Board | |||||
| 1.01 | Item No. 01 Excavation for foundation in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 100 Km. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.5 m.) | 857.84 | Cubic Metre | 759 ₹6,51,100.56 | 757 ₹6,49,384.88 Lowest |
| 1.02 | Item No. 02 Excavation for foundation in earth, soils of all types, sand,gravel and soft murum, including removing the excavated material upto a distance of 100 Km. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift from 1.5m to 3.0m) By Mechanical Means. Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | 759 ₹37,950 Lowest | 795 ₹39,750 |
| 1.03 | Item No. 03 Excavation for foundation in earth, soils of all types, sand,gravel and soft murum, including removing the excavated material upto a distance of 100 Km. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. ( Lift from 3.00m to 4.50m) By Mechanical Means Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | 825 ₹41,250 Lowest | 835 ₹41,750 |
| 1.04 | Item No. 04 Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 100 km. beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth /murum, ramming, watering including shoring and strutting etc. complete (lift upto 1.5m) Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | 924 ₹46,200 | 892 ₹44,600 Lowest |
| 1.05 | Item No. 05 Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 100 km. beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth/murum, ramming ,watering including shoring and strutting etc. complete. (Lift from 1.5m To 3.0 m.) Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | 1,452 ₹72,600 | 937 ₹46,850 Lowest |
| 1.06 | Item No. 06 Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 100 km. beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth/murum, ramming ,watering including shoring and strutting etc. complete(Lift from 3.00m to 4.50m)Including royalty and other taxes and lead upto 100 Kms | 25 | Cubic Metre | 1,650 ₹41,250 | 983 ₹24,575 Lowest |
| 1.07 | Item No. 07 Excavation for foundation in Hard rock by chiselling, wedging, line drilling, etc. including trimming and levelling the bed, removing the excavated material upto a distance of 100 km. beyond the building area stacking as directed, dewatering and back filling with available earth/ murum watering, ramming etc. complete. (Lift upto 1.5 m). Including royalty and other taxes and lead upto 100 Kms | 25 | Cubic Metre | 2,508 ₹62,700 | 1,296 ₹32,400 Lowest |
| 1.08 | Item No. 08 Excavation for foundation in Hard rock by chiselling, wedging, line drilling, etc. including trimming and levelling the bed, removing the excavated material upto a distance of 100 km. beyond the building area stacking as directed, dewatering and back filling with available earth/ murum watering, ramming etc. complete. (Lift from 1.50m to 3.0m) Including royalty and other taxes and lead upto 100 Kms | 24.52 | Cubic Metre | 2,772 ₹67,969.44 | 1,360 ₹33,347.2 Lowest |
| 1.09 | Item No. 09 Providing preconstructional antitermite treatment as per I.S. 6313 (Part-I) to the soil along the external face of building by punching holes of 1.2 of 1.5 C.M. diaMeter about 30 -60 cm deep at 15 cm c/c as close to the wall as possible and to inject 0.5 percent of aldrin or clorophyrifos at the rate of 7.5 litres per hole and sealing the same with proper filling and covering 10 years guarantee on bond paper. | 3,032.98 | Square Metre | 132 ₹4,00,353.36 | 90 ₹2,72,968.2 Lowest |
Tender Value
₹68.2 Cr
EMD Value
₹35 L
Closing Date
7 Sept 2022, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
CEO MMB
Chief Executive Officer, Maharashtra Maritime Board, Indian Mercantile Chamber, 2nd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001
Construction of Proposed Office Building on G- Block, Plot no. C-47, at Bandra Kurla Complex, Mumbai for Maharashtra Maritime Board
2022_MMB_820191_1
MMB/CEO/ ENGG/Thn/21-22/64
Open Tender
Civil Works - Buildings
Item Rate
730 days
G- Block, Plot no. C-47, at Bandra Kurla Complex
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,540
₹35 L
Mumbai
27 Jan 2023
21 Jul 2022
9 Sept 2022
21 Jul 2022
7 Sept 2022
3 Aug 2022
21 Jul 2022 - 3 Aug 2022
3 Aug 2022
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of Proposed Office Building on G-Block, Plot No. C-47, at Bandra Kurla Complex, Mumbai for Maharashtra Maritime Board | |||||
| 1.01 | Item No. 01 Excavation for foundation in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 100 Km. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.5 m.) | 857.84 | Cubic Metre | - | - |
| 1.02 | Item No. 02 Excavation for foundation in earth, soils of all types, sand,gravel and soft murum, including removing the excavated material upto a distance of 100 Km. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift from 1.5m to 3.0m) By Mechanical Means. Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | - | - |
| 1.03 | Item No. 03 Excavation for foundation in earth, soils of all types, sand,gravel and soft murum, including removing the excavated material upto a distance of 100 Km. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. ( Lift from 3.00m to 4.50m) By Mechanical Means Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | - | - |
| 1.04 | Item No. 04 Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 100 km. beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth /murum, ramming, watering including shoring and strutting etc. complete (lift upto 1.5m) Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | - | - |
| 1.05 | Item No. 05 Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 100 km. beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth/murum, ramming ,watering including shoring and strutting etc. complete. (Lift from 1.5m To 3.0 m.) Including royalty and other taxes and lead upto 100 Kms | 50 | Cubic Metre | - | - |
| 1.06 | Item No. 06 Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 100 km. beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth/murum, ramming ,watering including shoring and strutting etc. complete(Lift from 3.00m to 4.50m)Including royalty and other taxes and lead upto 100 Kms | 25 | Cubic Metre | - | - |
| 1.07 | Item No. 07 Excavation for foundation in Hard rock by chiselling, wedging, line drilling, etc. including trimming and levelling the bed, removing the excavated material upto a distance of 100 km. beyond the building area stacking as directed, dewatering and back filling with available earth/ murum watering, ramming etc. complete. (Lift upto 1.5 m). Including royalty and other taxes and lead upto 100 Kms | 25 | Cubic Metre | - | - |
| 1.08 | Item No. 08 Excavation for foundation in Hard rock by chiselling, wedging, line drilling, etc. including trimming and levelling the bed, removing the excavated material upto a distance of 100 km. beyond the building area stacking as directed, dewatering and back filling with available earth/ murum watering, ramming etc. complete. (Lift from 1.50m to 3.0m) Including royalty and other taxes and lead upto 100 Kms | 24.52 | Cubic Metre | - | - |
| 1.09 | Item No. 09 Providing preconstructional antitermite treatment as per I.S. 6313 (Part-I) to the soil along the external face of building by punching holes of 1.2 of 1.5 C.M. diaMeter about 30 -60 cm deep at 15 cm c/c as close to the wall as possible and to inject 0.5 percent of aldrin or clorophyrifos at the rate of 7.5 litres per hole and sealing the same with proper filling and covering 10 years guarantee on bond paper. | 3,032.98 | Square Metre | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
BOQ_1416748.xls
BOQ Document • 0.92 MB
102049193.pdf
Tender Document • 1.14 MB
DTP1.pdf
Tender Document • 1.78 MB
DTP2.pdf
Tender Document • 2.80 MB
Drawing.pdf
Tender Document • 27.68 MB
102049204.html
Tender Document • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .