| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Rejected-Technical | Rejected-Technical bid docs not as per PQC |
Tender Value
₹11.6 L
EMD Value
₹23,000
Closing Date
2 Sept 2024, 1:00 pmClosed
SE, OMC-4, BTPS
Office of SE, OMC-4, BTPS
OH of Toshiba make 40MVA CW Transformer, BTPS,Anpara
2024_RVUNL_942205_1
W-ANP/B/OMC4/EMD1/6000005825
Open Tender
Electrical Works
Fixed-rate
365 days
BTPS, anpara
As per tender documents
2 documents required · 2 mandatory
₹1,180
Dy CAO CFA and BO, BTPS, Anpara
₹23,000
10 Oct 2024
3 Aug 2024
3 Sept 2024
3 Aug 2024
2 Sept 2024
3 Aug 2024
Amount
Pre-Electrical Testing of CW Transformer.
Pre-Transformer Oil Testing of CW Transformer (All DGA, BDV,Furan etc.) as per scope of work.
Preparation of temporary oven for heating and dryout process as per scope of work.
Shifting of OIL filteration machine at site.
Shifting of OIL storage Tank(02 nos.) at site.
Draining and refilling of Transformer Oil in Tank after Filteration.
Filteration of Transformer Oil till BDV>75KV is achieved in main tank.
Dismantling and Erection of all HV Bushing, HV Turret.
Dismantling and Erection of LV Bushing, Neutral Bushing.
Dismantling, Overhauling and Erection of radiators.
Dismantling, Overhauling and Erection of Cooling Fans
Dismantling, Overhauling and Erection of Buttrfly valve
Servicing of Marshalling Box
Dismantling, Overhauling and Erection of OLTC & its Driving Mechanism.
Dismantling and Installation of Top cover and internal inspection of Transformer along with internal cleaning of tank .
Replacement of all erection gaskets of proper size by cutting,machining with proper cure as per scope of work.
Replacement of all gaskets of inspection cover, LV, HV turret etc. and all opening of butterfly valves of all header lines as per scope of work.
Overhauling of Conservator tank,MOG alongwith replacement of all erection gaskets and charging of Aircell.
Arrangement of Dry Air/N2 Cylinders for Dryout process of Transformer.
Dry out process of main tank to achieve dew point of <-20ºC atleast 03 cycle.
Post Transformer Oil testing(All DGA, BDV,Furan etc.) as per scope of work.
Post Electrical Testing.
Painting of CW Transformer of Surface Area=683 Sq. Mtr. (approx.).
Filteration Machine on rental basis if Departmental Filteration Machine not available
Deen Dayal
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .