Superintending Archaeologist
O/o The SA, ASI Kendriya sadan, Sultan Bazar, KotiHyderabad
Removal of vegetation and debris earthwork excavation and providing sand filling and providing lime concrete and RR masnory wall etc
2026_ASI_930768_1
T-15015/35/2025-Hyderabad Circle/1253
Open Tender
Civil Works
Works
Golconda Fort
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹2.2 L
Yes
O/o The SA, ASI Kendriya sadan Hyderabad
19 Oct 2026
19 Oct 2026
10 Nov 2026
19 Oct 2026
9 Nov 2026
19 Oct 2026
26 Oct 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Name of the Monument / Site: Naya Quilla, Golconda Fort, Hyderabad | |||||
| 1.01 | Removal of vegetation / jungle growth over the rocky and sloppy soil before execution of restoration work of Majnu bastion and dispose the same far away from work site including cost of material, all labor charges, applicable taxes etc. complete all as per specification and directions of the department officials | 750 | Sqm | 45.61 | ₹34,205.25 |
| 1.02 | Removal of debris/site clearance before execution of restoration work on south east side of Majnu bastion including sorting, stacking the useful material (80%) for reuse and dispose the waste (20%) material far away from work site including cost of material, labour charges, tools, applicable taxes etc. complete all as per specification and directions of the department officials | 225 | Cum | 2,627.34 | ₹5,91,151.73 |
| 1.03 | Earthwork excavation on south east portion of Majnu bastion for laying foundation in hard / dense soil (or) disintegrated root where the natural stone boulders are not available including dressing of sides, ramming of bottoms and disposal of surplus of excavated material, cost of material, labour charges, applicable taxes etc. complete all as per specification and directions of the department officials | 24 | Cum | 5,546 | ₹1,33,104 |
| 1.04 | Providing sand filling and compacting in foundation trenches on south east portion of Majnu bastion including watering, ramming, levelling to required grades & profiles including cost of material, labour charges, applicable taxes etc. complete all as per specification and directions of the department officials | 12.96 | Cum | 11,387 | ₹1,47,575.52 |
| 1.05 | Providing Lime Concrete as foundation Bed on south east portion of Majnu bastion using 40mm HBG metal, River Sand and unslaked lime in proportion 1:4:8 for providing firm and level base for the foundation including cost of material, labour charges, applicable taxes etc. complete all as per specification and directions of the department officials | 1.44 | Cum | 14,831.42 | ₹21,357.24 |
| 1.06 | Construction of RR masonry wall using available RR stones at site on south east portion of Majnu bastion in Lime Mortar (1:2) as foundation below the ground level laying to proper course and bond including cost of material, labour charges, machinery charges, applicable taxes etc. complete all as per specification and directions of the department officials | 9.6 | Cum | 14,813.19 | ₹1,42,206.62 |
| 1.07 | Identification, selection and resetting the original stone members of fallen bastion on south east portion of Majnu bastion in Lime Mortar (1:2) as per the existing pattern using necessary machinery for lifting of stone members for re-assemble in original position and equipment like 12T Crane, derrick poles, chain pulley blocks, scaffolding etc. all and skilled labour using traditional methods including cost of material, labour charges, machinery charges, applicable taxes etc. complete all as per specification and directions of the department officials | 297.43 | Cum | 24,085.23 | ₹71,63,669.96 |
| 1.08 | Providing pointing to the external joints of the bastion in lime mortar (1:2) including cleaning of joints and refilling with fresh lime mortar, cost of material, labour charges, applicable taxes etc. complete all as per specification and directions of the department officials | 411.81 | Sqm | 790.52 | ₹3,25,545.77 |
| 1.09 | Creating working space and earthen ramps for movement of men, material, machinery equipment etc. by cutting earth at heaps and filling the same in low lying areas etc. all complete as and when required including cost of material, labour charges, applicable taxes etc. complete all as per specification and directions of the department officials | 125 | Cum | 2,857.96 | ₹3,57,245 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 9.42 MB
BOQ_978123.xls
BOQ • 0.29 MB
RFpMajnuBastionatNayaQuilla.pdf
Tender Documents • 9.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .