| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹94.9 LAccepted-AOC | ₹94.9 L | L1 | Accepted-AOC L1 |
| 2 | L2₹96.1 L+₹1.2 L (1.29%)Rejected-AOC | ₹96.1 L+₹1.2 L (1.29%) | L2 | Rejected-AOC L2 |
| 3 | L3₹1.0 Cr+₹9.1 L (9.59%)Rejected-AOC | ₹1.0 Cr+₹9.1 L (9.59%) | L3 | Rejected-AOC L3 |
| 4 | L4₹1.1 Cr+₹15.5 L (16.3%)Rejected-AOC | ₹1.1 Cr+₹15.5 L (16.3%) | L4 | Rejected-AOC L4 |
| 5 | Not Admitted-Finance | - | - | Not Admitted-Finance Others-Bidder not submitted all pre -qualification documents and non responsive. Hence, Price Bid may not be Opened |
| Sl No | Description | Qty | Unit | DSA Construction L2 | RN Builders L3 | NATARAJAN L1 | S M CONSTRUCTIONS L4 |
|---|---|---|---|---|---|---|---|
| 1.00Strengthening of the Thamaleripatti road Km 0/0 - 2/500 H/o.Keelmorappur R-28 | |||||||
| 2.00Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. | |||||||
| 3.00 | KM 0/0-2/500 | 1,125 | Sq.m | 5.55 ₹6,243.75 | 5.91 ₹6,648.75 | 5 ₹5,625 Lowest | 65 ₹73,125 |
| 4.00Picking up existing BT surface upto 5 to 10 cm of Old metalled surface, cambering, sectioing of carriageway etc., complete | |||||||
| 5.00 | KM 0/0-2/500 | 3,121.21 | Sq.m | 20.37 ₹63,579.05 | 20.46 ₹63,859.96 | 20 ₹62,424.2 Lowest | 95 ₹2,96,514.95 |
| 6.00Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20A | |||||||
| 7.00 | KM 0/0-2/500 | 260.9 | Cum | 122.08 ₹31,850.67 | 130.2 ₹33,969.18 | 121 ₹31,568.9 | 120 ₹31,308 Lowest |
| 8.00Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS | |||||||
| 9.00 | KM 0/0-1/0 | 337.5 | Cu.m | 486.3 ₹1,64,126.25 | 585.9 ₹1,97,741.25 | 480 ₹1,62,000 | 210 ₹70,875 Lowest |
| 10.00 | KM 1/0-2/0 | 335.54 | Cu.m | 496.49 ₹1,66,592.25 | 595.2 ₹1,99,713.41 | 490 ₹1,64,414.6 | 210 ₹70,463.4 Lowest |
Tender Value
₹1.2 Cr
EMD Value
₹1.2 L
Closing Date
20 Feb 2026, 3:00 pmClosed
The Joint Director/ Project Director
DRDA, Dharmapuri
Strengthening of the Thamaleripatti road Km 0/0 - 2/500 H/o.Keelmorappur
2026_RDTN_657263_1
Roc.No.192/2026/R2 NABARD P04
Open Tender
Civil Works
Item Rate
180 days
DRDA
Can be seen in the tender documents
2 documents required · 2 mandatory
₹0
₹1.2 L
23 Jun 2026
13 Feb 2026
20 Feb 2026
13 Feb 2026
20 Feb 2026
14 Feb 2026
Strengthening of the Thamaleripatti road Km 0/0 - 2/500 H/o.Keelmorappur R-28
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking up existing BT surface upto 5 to 10 cm of Old metalled surface, cambering, sectioing of carriageway etc., complete
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20A
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5
Applying Prime Coat over WMM surface at 7.00 Kg of SS-1 Bitumen Emulsion / 10 Sq.m including labour for spraying, hire charges for bitumen sprayer etc., completion
Applying Tack Coat over WMM surface at 2.50 Kg of RS-1 Bitumen Emulsion / 10 Sq.m including labour for spraying, hire charges for bitumen sprayer etc., completion
BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Provision for Kilometer Stone
Provision for Hectometer Stone
Provision for Road Stud
Provision for Sign Board
Provision for Name Board
Routine Maintenance** after completion of construction works (Lump-sum Amount for each year Per Km.)
For 1st year maintenance
For 2nd year maintenance
For 3rd year maintenance
For 4th year maintenance
For 5th year maintenance
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.94 MB
BOQ_788224.xls
BOQ • 0.30 MB
Technical_Bid_04.pdf
Tender Documents • 0.57 MB
Price_Bid_04.pdf
Additional Documents • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .